Document from CIS Legislation database © 2012-2026 CIS Legislation Company

ORDER OF THE GOVERNMENT OF THE RUSSIAN FEDERATION

of February 20, 2014 No. 130

About modification of the Order of the Government of the Russian Federation of December 27, 2004 No. 861

(as amended of the Order of the Government of the Russian Federation of 07.05.2017 No. 542)

The government of the Russian Federation decides:

1. Approve the enclosed changes which are made to the order of the Government of the Russian Federation of December 27, 2004 No. 861 "About approval of Rules of non-discriminatory access to services in transfer of electrical energy and rendering these services, Rules of non-discriminatory access to services in supervisory control in power industry and rendering these services, Rules of non-discriminatory access to services of Trading System Administrator of the wholesale market and rendering these services and Rules of technological connection of power receiving devices of consumers of electrical energy, facilities for production of electrical energy, and also the objects of electric grid economy belonging to the network organizations and other persons to power networks" (The Russian Federation Code, 2004, No. 52, Art. 5525; 2007, No. 14, Art. 1687; 2009, No. 8, Art. 979; No. 17, Art. 2088; 2010, No. 21, Art. 2607; No. 40, Art. 5086; 2011, No. 10, Art. 1406; 2012, No. 4, Art. 504; No. 23, Art. 3008; No. 41, Art. 5636; No. 49, Art. 6858; No. 52, Art. 7525; 2013, No. 31, Art. 4226, 4236; No. 32, Art. 4309; No. 33, Art. 4392; No. 35, Art. 4523; No. 42, Art. 5373; No. 44, Art. 5765; No. 48, Art. 6255; No. 50, Art. 6598; in edition of the order of the Government of the Russian Federation of February 10, 2014 No. 95).

2. This resolution becomes effective since March 25, 2014.

Russian Prime Minister

D. Medvedev

 

Approved by the Order of the Government of the Russian Federation of February 20, 2014 No. 130

Changes which are made to the Order of the Government of the Russian Federation of December 27, 2004 No. 861

1. Item 13 paragraph two (1) Rules of non-discriminatory access to services in transfer of electrical energy and rendering these services approved by the specified resolution to state in the following edition:

"If in documents on technological accession the size of the maximum capacity of power receiving devices is not specified and (or) if documents on technological accession are lost, the size of the maximum capacity is determined according to the Section VIII of Rules of technological connection of power receiving devices of consumers of electrical energy, facilities for production of electrical energy, and also the objects of electric grid economy belonging to the network organizations and other persons to power networks.".

2. In Rules of technological connection of power receiving devices of consumers of electrical energy, facilities for production of electrical energy, and also the objects of electric grid economy belonging to the network organizations and other persons, to power networks, approved by the specified resolution:

a) in Item 1 after words" (further - specifications)," to add with the words "procedure for conducting check of accomplishment by the applicant and network organization of specifications";

b) to state the subitem "d" of Item 7 in the following edition:

"e) creation of the act of implementation of technological accession in form according to appendix No. 6 (further - the act of implementation of technological accession), the act of differentiation of borders of balance sheet accessory of the parties in form according to appendix No. 7 (further - the act of differentiation of borders of balance sheet accessory of the parties), the act of differentiation of operational responsibility of the parties in form according to appendix No. 8 (further - the act of differentiation of operational responsibility of the parties), and also the act of approval of technological and (or) emergency armor (for the applicants specified in Item 14 (2) these rules).";

c) Item 8 in paragraph one (2) the words "220 kV and above" shall be replaced with words "110 kV and above";

d) in Item 8 (3):

add paragraph two with the offer of the following content: "In case of the direction the applicant within 3 working days from the date of the direction of the second and the subsequent requests shall notify by the applicant of 2 and more requests in the different network organizations for technological connection of power receiving devices to which the category of reliability of electric utility service providing use of 2 and more sources of electric utility service is applied on it each network organization to which the request is sent.";

the ninth to declare the paragraph invalid;

e) to add the subitem "k" of Item 9 after words of "input terms" with words ", set of loading";

e) in Item 15:

the paragraph one to state in the following edition:

"15. To the applicants specified in Items 12 (1) and 14 these rules, the network organization the completed and signed draft agreement, in paper form for signing, in 2 copies and specifications as the integral appendix to the agreement within 15 days from the date of receipt of the request from the applicant (authorized representative) or other network organization, directed including by means of the official site of the network organization or other official site on the Internet determined by the Government of the Russian Federation directs.";

after the paragraph of third to add with paragraphs of the following content:

"For the purpose of temporary technological accession the network organization sends to the applicant in paper form for signing the draft agreement completed and signed by it in 2 copies and specifications as the integral appendix to such agreement within 10 days from the date of receipt of the request, directed including by means of the official site of the network organization or other official site on the Internet determined by the Government of the Russian Federation.

The network organization along with the direction of the agreement to the applicant (except for the applicants specified in Item 13 of these rules) also notifies the applicant on possibility of the temporary technological accession provided by the Section VIII of these rules.";

g) subitems "v" and "g" of Item 16 (to state 2) in the following edition:

"c) 45 percent of payment for technological accession are brought within 15 days from the date of the actual accession;

d) 10 percent of payment for technological accession are brought within 15 days from the date of signing of the act of implementation of technological accession.";

h) subitems "g" and "d" of Item 16 (to state 4) in the following edition:

"d) 30 percent of payment for technological accession are brought within 15 days from the date of the actual accession;

e) 10 percent of payment for technological accession are brought within 10 days from the date of signing of the act of implementation of technological accession.";

i) to state the subitem "d" of Item 18 in the following edition:

"e) check of accomplishment by the applicant and the network organization of specifications according to the Section IX of these rules, and also the admission to operation of the metering device of electrical energy established in the course of technological accession including creation of the act of the admission of the metering device to operation according to the procedure, provided by Basic provisions of functioning of the retail markets of electrical energy;

the paragraph third the subitem "i" of ceased to be valid according to the Order of the Government of the Russian Federation of 07.05.2017 No. 542

j) in Item 18 (2):

paragraph two of the subitem "k" of ceased to be valid according to the Order of the Government of the Russian Federation of 07.05.2017 No. 542

add with the subitem "g" of the following content:

"d) copies of the Sections of the project documentation providing the technical solutions providing accomplishment of specifications including decisions according to the scheme of external electric utility service (the scheme of issue of capacity of facilities for production of electrical energy), relay protection, except as specified, when in accordance with the legislation of the Russian Federation about town-planning activities development of the project documentation is not obligatory.";

k) in Item 18 (the word of "objects" to replace 3) with the word of "electroinstallations";

l) Item 18 in paragraph one (to add 5) after the words "constitutes less than 150 kW" with the word "inclusive";

m) state Item 19 in the following edition:

"19. Upon termination of implementation of actions for technological accession of the party constitute the following documents:

act of implementation of technological accession;

act of differentiation of borders of balance sheet accessory of the parties;

act of differentiation of operational responsibility of the parties.

Upon termination of implementation of actions for technological accession of the party draw up the statement of approval of technological and (or) emergency armor according to Item 14 (2) these rules.

It is forbidden to impose to the applicant of service and the obligation, not provided by these rules.";

o) add with Item 19 (1) the following content:

free document

Full text available after Login.

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Search in text CTRL-F

Demo Access

If you are guest on our site, you will work in Demo mode. In Demo mode you can see only first page of each document.


Full Access

With full access you can

  • see full text
  • see original text of document in Russian
  • download attachment (if exist)
  • see History and statistics

Get Full Access Now

Effectively work with search system

Database include more 65000 documents. You can find needed documents using search system.
For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions.
This section provides answers to questions set by users.

Search engine created by CIS Legislation Company