of October 16, 2026 No. 383-n/k
About modification and amendments in some orders of the Minister of Energy of the Republic of Kazakhstan
I ORDER:
1. Approve the enclosed list of some orders of the Minister of Energy of the Republic of Kazakhstan to which changes and additions are made.
2. To provide to development department of power industry of the Department of Energy of the Republic of Kazakhstan in the procedure established by the legislation of the Republic of Kazakhstan:
1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;
2) placement of this order on official Internet resource of the Department of Energy of the Republic of Kazakhstan after its official publication;
3) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Department of legal service of the Department of Energy of the Republic of Kazakhstan of data on execution of the actions provided by subitems 1) and 2) of this Item.
3. To impose control of execution of this order on the supervising vice-Minister of Energy of the Republic of Kazakhstan.
4. This order becomes effective after ten calendar days after day of its first official publication.
Minister of Energy of the Republic of Kazakhstan
E.Akkenzhenov
|
It is approved Ministry of Finance of the Republic of Kazakhstan |
|
|
It is approved Industry ministry and constructions of the Republic of Kazakhstan |
|
|
It is approved Ministry of water resources of the Republic of Kazakhstan
|
|
|
It is approved Ministry of national economy of the Republic of Kazakhstan |
|
|
It is approved Ministry of Internal Affairs of the Republic of Kazakhstan |
|
Approved by the order of the Minister of Energy of the Republic of Kazakhstan of October 16, 2026, No. 383-n/k
1. Bring in the order of the Minister of Energy of the Republic of Kazakhstan of December 18, 2014 No. 210 "About approval of Power grid rules" (it is registered in the Register of state registration of regulatory legal acts at No. 10899) the following changes and amendments:
in the Power grid rules approved by the specified order:
add item 4 with part six of the following content:
"Effective period" of the scheme of issue of power of the power plant" constitutes 3 (three) years from the date of approval by the system operator.";
be reworded as follows Item 6:
"6. The power transferring (power making) organization to which networks joining of the user of network is planned issues specifications in which the following is specified:
1) surname, name, middle name (in the presence) physical or the name of the legal entity to which the specification is issued;
2) name of object of issue of electric power;
3) location of object (city, settlement, street);
4) the approved size of power of the power plant;
5) nature of power generation (permanent, temporary, seasonal);
6) category of reliability of electric utility service;
7) the permitted power factor of power plant;
8) connection points (substation, power plant or power line) with indication of the scheme of connection (the scheme "calling exit", branch from power line, connection to tires of the distributing device of substation and power plant);
9) the main technical requirements to the connected power lines (further – the power transmission line) and to the equipment of substations;
10) reasonable requests on strengthening of the existing power network in connection with emergence of new power plant – increase in sections of wires, replacement or increase in capacity of transformers, construction of additional cells of distributing devices;
11) reason of issue of specifications;
12) effective period of specifications;
13) requirements for the organization of commercial accounting of the electric power using ASKUE;
14) requirements for equipment of power plant devices of relay protection and automatic equipment, dispatching management: telemetry, telecontrol and organization of communication channel;
15) requirements for compensation of reactive capacity.
Specifications are issued in the following terms:
1) for technically simple objects – within five working days;
2) for technically difficult objects – within ten working days.
Effective period of specifications on accession of power plants, including objects for use of renewable energy resources, corresponds to their normative terms of designing and construction.
The validity of specifications on begun construction to objects is extended for construction according to the application of the owner submitted before the expiration of their effective period and on condition of submission of supporting documents about the beginning of construction.
Full text is available with an active Subscribtion after logging in.
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Search in text CTRL-F
If you are guest on our site, you will work in Demo mode. In Demo mode you can see only first page of each document.
With full access you can
Database include more 65000 documents. You can find needed documents using search system.
For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions.
This section provides answers to questions set by users.