of June 9, 2026 No. 291
About approval of form of the acceptance act of construction object in operation
According to the subitem 73) of article 24 of the Construction Code of the Republic of Kazakhstan, I ORDER:
1. Approve the enclosed form of the acceptance act of construction object in operation.
2. Declare invalid some orders, according to appendix to this order.
3. To provide to committee on cases of construction and housing and communal services of the Industry ministry and construction of the Republic of Kazakhstan in the procedure established by the legislation:
1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;
2) placement of this order on Internet resource of the Industry ministry and construction of the Republic of Kazakhstan after its official publication.
4. To impose control of execution of this order on the supervising vice-Minister of Industry and construction of the Republic of Kazakhstan.
5. This order becomes effective since July 1, 2026 and is subject to official publication.
Minister of Industry and constructions of the Republic of Kazakhstan
E.Nagaspayev
Approved by the Order of the Minister of Industry and construction of the Republic of Kazakhstan of June 9, 2026, No. 291
form
I claim
Customer ___________________
___________________________
(surname, name, middle name
(in case of its availability), the signature
head, date)
Locus sigilli (in the presence)
"____" _________ 20 __ years
Customer _______________________________________________________
____________________________________________________________________
(surname, name, middle name (in case of its availability) IIN, phone – for
physical persons, the name of the organization – for legal entities, the BIN,
phone, postal index, area, city, area, settlement,
name of the street, number of the house/building (stationary room))
on the basis:
Declarations of conformity (are attached) ___________________________
____________________________________________________________________,
(signature date of the declaration, name of contract (contract)
the organizations, surname, name, middle name (in case of its availability) the head, legal address, the BIN, phone)
The conclusions about quality of installation and construction works (are attached) ____
____________________________________________________________________,
(signature date of the conclusion, name of the organization, surname, name,
middle name (in case of its availability) experts of technical supervision,
No. and the date of receipt of the certificate, BIN, phone)
The conclusions about compliance of the performed works to the project (are attached) __
___________________________________________________________________,
(signature date of the conclusion, name of the organization, surname, name,
middle name (in case of its availability) experts author's maintenance,
No. and the date of receipt of the certificate, BIN, phone)
Conclusions about object compliance to requirements of fire safety
it (is applied) (in the presence) ___________________________________________,
(the document issued by territorial authority of authorized body
in the field of civil protection, about compliance of the constructed object with mass
stay of people and buildings more than twenty eight meters high
to requirements of fire safety before their acceptance in operation)
having examined readiness shown by the contractor (general
the contractor) to acceptance of construction object in operation:
____________________________________________________________________
____________________________________________________________________
(name of construction object, construction type (new, expansion,
upgrade, modernization, reconstruction, restoration
capital repairs, level of responsibility, technical and technological
complexity of object to the address
____________________________________________________________________
(area, area, settlement, residential district, quarter, street, house number (cases))
having checked completeness of executive technical documentation, including by means of the electronic module of executive technical documentation "__" ________ 20 __ years, date of acquaintance confirms that:
1. The construction of construction object is performed on the basis:
1) the title document on the parcel of land
from "___" _______________ 20 _____ years
№_________________________________________________________________;
(the document confirming occurrence of dispositive facts (legal
structures) based on which arise, change or stop
rights to the parcel of land, including agreements, decisions of the courts, legal
acts of executive bodies, certificate on the right to inheritance,
the transfer act or the separation balance sheet by reorganization
the non-state legal entities owning the parcel of land on
the property right or redeemed the right of temporary paid
land use (lease)) or decisions on reconstruction
(re-planning, re-equipment) rooms (separate parts)
the existing buildings from "___" _______ 20 ___ year
№_________________________________________;
____________________________________________________________________
(the name of the body which passed the decision)
2) the coupon about acceptance of the notification on the beginning of installation and construction works
____________________________________________________________________
____________________________________________________________________
(the name of the body which accepted the notification, date and No. of adoption of the coupon)
3) project (design estimates) _______________________
____________________________________________________________________
(name of the project organization, project number of approved)
____________________________________________________________________
___________________________________________________________________;
(date and project number, the name of the organization which claimed
(reapproved) the project and approval date)
2. Installation and construction works are carried out in terms:
beginning of works "___" __________ 20 ___ years;
completion of works "___" __________ 20 ___ years;
at construction duration, month:
on regulation or on the project
organizations of construction, month: _____________________________________;
actually, month: __________________________________________________;
3. Construction object (complex) has the following main technical and economic indicators (capacity, performance, floor space, extent, capacity, amount, handling capacity, transportation capability, number of workplaces and so forth, is filled on all objects (except apartment houses) in units of measure according to target products or main types of services):
|
Capacity, performance and so on |
Unit of measure |
On the project |
Actually | ||
|
general (taking into account earlier accepted) |
including start-up complex or queue |
general (taking into account earlier accepted) |
including start-up complex or queue | ||
Production (rendering services), provided by the project in the amount meeting standards of development of project
capacities during initial stage
___________________________________________________________________;
the fact of the beginning of production with indication of amount
The apartment house has the following indicators:
|
Indicators |
Unit of measure |
On the project |
Actually | ||||
|
Total area |
meter in square (further – m 2) |
||||||
|
Number of floors |
floor |
||||||
|
Total total structural volume |
meter cubed (further – m 3) |
||||||
|
Including underground part |
m3 |
||||||
|
The area of built-in, it is built-in - the attached and attached rooms |
sq.m |
||||||
|
Indicators |
On the project |
Actually | |||||
|
number of apartments |
area of apartments, sq.m |
number of apartments |
area of apartments, sq.m | ||||
|
general |
residential |
general |
residential | ||||
|
In total apartments, including: one-room two-room three-room four-room and more |
|||||||
4. Technology and architectural and construction solutions on construction object are characterized by the following data:
________________________________________________________________________
____________________________________________________________________;
(short technical characteristics on features of its placement, on
to the main materials and designs, engineering and processing equipment)
5. On construction object the equipment provided by the project in quantity according to acts of its acceptance after individual testing and complex approbation is installed;
6. Outside engineering communications (cold and hot water supply, the sewerage, heat supply, gas supply, electric utility service and communication) provide normal operation of object (the building, construction, the room) and are accepted by the city operational organizations;
Full text is available with an active Subscribtion after logging in.
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Search in text CTRL-F
If you are guest on our site, you will work in Demo mode. In Demo mode you can see only first page of each document.
With full access you can
Database include more 65000 documents. You can find needed documents using search system.
For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions.
This section provides answers to questions set by users.