of September 26, 2025 No. 398
About introduction of amendments to the order of the acting minister of the industry and infrastructure development of the Republic of Kazakhstan of July 11, 2019 No. 500 "About approval of Rules of representation of special economic and industrial zones of the reporting by managing company"
I ORDER:
1. Bring in the order of the Minister of investments and development of the Republic of Kazakhstan of July 11, 2019 No. 500 "About approval of Rules of representation of special economic and industrial zones of the reporting by managing company" (further - Governed) (it is registered in the Register of state registration of regulatory legal acts for No. 19021) the following changes:
state preamble in the following edition:
"According to the subitem 11) of article 11 of the Law of the Republic of Kazakhstan "About special economic and industrial zones" and the subitem 2) of Item 3 of article 16 of the Law of the Republic of Kazakhstan "About the state statistics" I ORDER:";
in Rules of representation by managing company of the special economic and industrial zones of the reporting approved by the specified order:
be reworded as follows appendix according to appendix, to this order.
2. To provide to development department of industrial infrastructure and intra country value of the Industry ministry and construction of the Republic of Kazakhstan in the procedure established by the legislation:
1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;
2) placement of this order on Internet resource of the Industry ministry and construction of the Republic of Kazakhstan.
3. To impose control of execution of this order on the supervising vice-Minister of Industry and construction of the Republic of Kazakhstan.
4. This order becomes effective after ten calendar days after day of its first official publication.
Minister of Industry and constructions of the Republic of Kazakhstan
E.Nagaspayev
|
It is approved Bureau of national statistics of the Agency on strategic planning and reforms of the Republic of Kazakhstan |
|
|
It is approved Ministry of national economy of the Republic of Kazakhstan |
|
|
It is approved Ministry of Finance of the Republic of Kazakhstan |
|
to the Order of the Minister of Industry and construction of the Republic of Kazakhstan of September 26, 2025 No. 398
Rules of representation of special economic and industrial zones of the reporting by managing company
Forms, intended for collection of administrative data
It is represented: in the Industry ministry and constructions of the Republic of Kazakhstan and the Single coordination center for special economic and industrial zones in the Republic of Kazakhstan.
The form intended for collection of administrative data on a grant basis is placed on Internet resource: www.gov.kz/memleket/entities/mps.
Name of administrative form: Project information of the single card of industrialization.
Index of the form intended for collection of administrative data on a grant basis (short alphanumeric expression of the name of form): IPEKI-1.
Frequency: annually for special economic zones; quarterly for industrial zones.
Accounting period: 20 ____ year.
The group of people, representing the form intended for collection of administrative data on a grant basis: managing companies of special economic and industrial zone.
The term of representation of the form intended for collection of administrative data on a grant basis:
- annually, in time no later than April 15 of the year following after accounting year for special economic zones;
- quarterly to the tenth, the following reporting quarter for industrial zones.
IIN/BIN 
(it is not filled in case of data presentation by physical persons, and also in aggregative type)
Collection method: in electronic form.
Form 1
General indicators of special economic and industrial zones (SEZ/IZ)
|
Name (SEZ/IZ) (years of functioning) | ||||||||||
|
1№ |
Main indicators |
year the first * |
year of the second |
year third |
… |
year current (quarter 1) |
year current (quarter 2) |
year current (quarter 3) |
year current (quarter 4) |
for all years |
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
|
11 |
Amount of actually enclosed investments by participants into projects (billions of tenges) |
|||||||||
|
22 |
Amount of direct foreign investments (billions of tenges) |
|||||||||
|
33 |
Volume of production and services (billions of tenges) |
|||||||||
|
44 |
Amount of tax assignments (billions of tenges) |
|||||||||
|
55 |
Amount of the received tax preferences |
|||||||||
|
66 |
Amount of the received customs preferences |
|||||||||
|
77 |
Products export volume (billions of tenges) |
|||||||||
|
88 |
Permanent workplaces (with accounting of employees of managing company) |
it is not filled | ||||||||
* from the moment of creation of SEZ/IZ (to specify every year)
Form 2
Projects of special economic and industrial zones
(it is filled separately for the existing projects and projects on implementation phase)
|
№ |
Name SEZ/IZ |
The name of the participant of SEZ or person performing non-core types of activity |
Name of the project |
Products |
Industry |
The OKED code at the level of 2 signs | ||
|
Product name |
The Commodity Nomenclature of Foreign Economic Activity code at the level of 10 signs |
The SKPP code at the level of 9 signs | ||||||
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
Continuation of the table
|
Category of the subject of entrepreneurship (micro, small, average, large) |
The occupied land area, hectare |
The date of receipt of the parcel of land on gos.akta |
For what term the parcel of land on gos.akta is issued |
Project cost, one billion тг |
Amount of actually invested funds, one billion тг | |||||
|
Year the first |
Year of the second |
Year third |
… |
Current year |
During all the time | |||||
|
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
Continuation of the table
|
Foreign participation in the authorized capital of the participant of SEZ (in the presence) |
Capacity of the project | |||||||||
|
Country |
Name of the company foreign participant |
Share, % |
Amount of actually made foreign investments, one billion тг |
|||||||
|
Year the first |
Year of the second |
Year third |
… |
Current year |
During all the time |
In kind |
In value term, one billion тг | |||
|
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
Continuation of the table
|
Amount of the made products by the product range, one billion tenges |
Products export volume by the product range, one billion tenges |
The exported countries | ||||||||||
|
Year the first |
Year of the second |
Year third |
… |
Current year |
During all the time |
Year the first |
Year of the second |
Year third |
… |
Current year |
During all the time |
|
|
32 |
33 |
34 |
35 |
36 |
37 |
38 |
39 |
40 |
41 |
42 |
43 |
44 |
Continuation of the table
|
Permanent workplaces, piece |
Date of commissioning |
Tax assignments, one billion tenges |
Current status |
Contact information | ||||||
|
month |
year |
Year the first |
Year of the second |
Year third |
… |
Current year |
During all the time |
|||
|
45 |
46 |
47 |
48 |
49 |
50 |
51 |
52 |
53 |
54 |
55 |
Form 3
Infrastructure
1) Financing of infrastructure facilities of SEZ/IZ
|
№ |
Name SEZ/IZ (object) |
Total cost of construction of infrastructure of SEZ/IZ, billions of tenges according to the feasibility statement |
Allocated funds, billions of tenges | ||||||||
|
year the first * |
year of the second |
year third |
… |
year current (quarter 1) |
year current (quarter 2) |
year current (quarter 3) |
year current (quarter 4) |
for all years | |||
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 | |
Continuation of the table
|
The mastered means, billions of tenges |
Not development reasons |
Completeness of infrastructure (%) |
Additional requirement for financing, billions of tenges |
Notes | ||||||
|
year current |
year subsequent |
year subsequent |
year subsequent |
year subsequent |
year subsequent |
year subsequent |
||||
|
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
2) General information on capacities of infrastructure facilities of SEZ/IZ
|
Infrastructure facilities |
Measurement unit |
Capacities of SEZ/IZ | |||||
|
Existing * |
Consumed ** |
Free *** |
Planned **** | ||||
|
1 |
2 |
3 |
4 |
5 |
6 | ||
|
Water supply, including following infrastructure facilities: |
cubic meters an hour |
||||||
|
1 |
|||||||
|
Sewerage, including following infrastructure facilities: |
cubic meters an hour |
||||||
|
1 |
|||||||
|
Electric utility service, including following infrastructure facilities: |
Megawatt |
||||||
|
1 |
|||||||
|
Heat supply, including following infrastructure facilities: |
Gigacalories per hour |
||||||
|
1 |
|||||||
|
Gas supply, including following infrastructure facilities: |
cubic meters an hour |
||||||
|
1 |
|||||||
|
Steam supply, including following infrastructure facilities: |
Gigacalories per hour |
||||||
|
1 |
|||||||
|
Telephone communication, including following infrastructure facilities: |
lines |
||||||
|
1 |
|||||||
|
Internet, including following infrastructure facilities: |
Megabit a second |
||||||
|
1 |
|||||||
|
Utilization of solid waste, including following infrastructure facilities: |
tons per day |
||||||
|
1 |
|||||||
|
Utilization of liquid waste, including following infrastructure facilities: |
tons per day |
||||||
|
1 |
|||||||
|
Access railway way, including following infrastructure facilities: |
kilometers |
||||||
|
1 |
|||||||
|
Highways, including following infrastructure facilities: |
kilometers |
||||||
|
1 |
Vnutrennyaya Highway |
||||||
|
2 |
The bringing highway |
||||||
|
3 |
|||||||
|
** |
The capacities consumed by the current participants and administrative objects | ||||||
|
*** |
Capacities of infrastructure facilities, free for new participants of SEZ/IZ | ||||||
|
**** |
The capacities planned to creation in the territory of SEZ/IZ (expansion of present objects, construction of new objects) | ||||||
3) Cost of utilities
|
№ |
Utility |
Unit of measure |
Cost, tenge |
|
1 |
2 |
3 | |
|
1 |
Water supply |
cubic meter |
|
|
2 |
Heat supply |
Gigacalories |
|
|
3 |
Electric utility service |
kilowatt |
|
|
4 |
Sewerage |
cubic meters an hour |
|
|
5 |
Gas supply |
cubic meters an hour |
4) Need for infrastructure facilities
|
№ |
Name of infrastructure facility |
Capacities |
Requirement, billions of tenges | |
|
1 |
2 |
3 | ||
|
Objects of basic infrastructure (prime necessity) | ||||
|
1 |
||||
|
2 |
||||
|
Objects of additional infrastructure | ||||
|
1 |
||||
|
2 |
||||
Form 4
Parcels of land
1) Distribution of the territory
|
Area (hectare) |
Note | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
1 |
2 |
3 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
General territory of special economic and industrial zones |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Usable space |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Allocated under projects |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The territory of the existing projects (general) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The territory of projects on implementation phase (general) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Allocated under infrastructure |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Constructed |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
At construction stage |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Free useful |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Provided with infrastructure |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Not the useful territory |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
IN TOTAL |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
2) the usable space Allocated to participants
|
3) Distribution of the other territory
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Contractor:
__________________________________________________________ ________
(signature) surname, name and middle name (in case of its availability)
The head of managing company or person fulfilling its duties:
___________________________________________________________ ________
(signature) surname, name and middle name (in case of its availability)
Locus sigilli (in the presence)
* it is filled after each form
Form 5
Share of intra country value
|
№ |
Name SEZ |
The name of the participant of SEZ or person performing non-core types of activity |
Identification number (BIN / IIN) |
Acquisition code (0 goods, 1 work, 2 - service) |
The name and the short (additional) description of acquired I RUB |
The OKED code at the level of 4 signs or the Commodity Nomenclature of Foreign Economic Activity code at the level of 6 signs |
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
Continuation of the table
|
Name of the supplier |
Amount of the acquired goods in kind |
Total amount under the agreement, tenge |
BIN/IIN of the producer of goods to which statements from the register of the Kazakhstan producers / the certificate of "CT-KZ" is issued |
statement No. from the register of the Kazakhstan producers / the certificate of "CT-KZ" |
|
8 |
9 |
10 |
11 |
12 |
Continuation of the table
|
Statement series from the register of the Kazakhstan producers / the certificate of "CT-KZ" |
Date of issue of the statement from the register of the Kazakhstan producers / the certificate of "CT-KZ", (day, month, year) |
The intra country value in goods specified in the statement from the register of the Kazakhstan producers / the certificate of "CT-KZ", % |
Intra country value in work (service), % |
|
13 |
14 |
15 |
16 |
__________________________________________________ phone
E-mail address ___________________________________
Contractor ______________________________________________
surname, name and middle name (in case of its availability) the signature, phone
The head or person fulfilling its duties
___________________________________________________ ______
surname, name and middle name (in case of its availability) the signature
Locus sigilli
(except for persons which are subjects of private entrepreneurship)
__________________________________________________________
Appendix
to the form intended for collection of the administrative data "Project Information of the Single Card of Industrialization"
The explanation on filling of forms 1-5, of the administrative data intended for collection on a grant basis
Chapter 1. General provisions
1. This explanation determines single requirements for filling of forms 1-5, of the administrative data intended for collection on a grant basis, including the Share of Intra Country Value form (further – the Form).
2. The form is filled with managing companies of special economic and industrial zones.
3. The filled Form is represented annually for special economic zones; quarterly for industrial zones;
4. The form is signed by the head, or person fulfilling its duties with indication of its surname and initials, and also date of filling.
5. The form is filled in the Kazakh and Russian languages.
Chapter 2. The explanation on filling of the Form
Form 1. General indicators of special economic and industrial zones (SEZ/IZ)
1) in column 1 numbering is specified;
2) in column 2 it is specified the main indicators (amount of actually enclosed investments by participants into projects (one billion tenges), amount of direct foreign investments (one billion tenges), volume of production and services (one billion tenges), the amount of tax assignments (one billion tenges), amount of the received tax preferences, amount of the received customs preferences, products export volume (one billion tenges), permanent workplaces (with accounting of employees of managing company) - indicator is not filled);
3) it is specified to column 3 of value of the main indicators for the first year;
4) in column 4 it is specified values of the main indicators for the second year;
5) in column 5 it is specified values of the main indicators for the third year;
6) in column 6 it is specified values of the main indicators the next years with creation of additional columns;
7) in column 7 it is specified values of the main indicators the current year of 1 quarter;
8) in column 8 values of the main indicators the current year 2 quarters are specified;
9) in column 9 values of the main indicators the current year 3 quarters are specified;
10) in column 10 values of the main indicators the current year 4 quarters are specified;
11) in column 11 all values of the main indicators on from column 3 are summed up;
Form 2. Projects of special economic and industrial zones
1. in column 1 numbering of special economic or industrial zone is specified;
2. in column 2 the name of special economic or industrial zone is specified;
3. the name of the participant of SEZ or person performing non-core types of activity is specified to column 3;
4. in column 4 the name of the project is specified;
5. in column 5 the product name is specified;
6. in column 6 the Commodity Nomenclature of Foreign Economic Activity code at the level of 10 signs is specified;
7. in column 7 the SKPP code at the level of 9 signs is specified;
8. in column 8 the industry is specified;
9. in column 9 the OKED code at the level of 2 signs is specified;
10. in column 10 the category of the subject of entrepreneurship is specified (micro, small, average, large);
11. in column 11 the occupied land area, hectare is specified;
12. in column 12 the date of receipt of the parcel of land on state is specified. to the act;
13. in column 13 it is specified what term the parcel of land on state is issued. to the act;
14. in column 14 project cost, one billion tenges is specified;
15. in column 15 the amount of actually invested funds, one billion tenges for the first year is specified;
16. in column 16 the amount of actually invested funds, one billion tenges for the second year is specified;
17. in column 17 the amount of actually invested funds, one billion tenges for the third year is specified;
18. in column 18 the amount of actually invested funds, one billion tenges the next years is specified;
19. in column 19 the amount of actually invested funds, one billion tenges the current year is specified;
20. in column 20 the amount of amount of actually invested funds, one billion tenges during all the time is specified;
21. in column 21 the foreign country participating in the authorized capital of the participant of SEZ (in the presence) is specified;
22. in column 22 the name of the company foreign participant is specified;
23. in column 23 the percentage share, % is specified;
24. in column 24 the amount of actually invested funds, one billion tenges for the first year is specified;
25. in column 25 the amount of actually invested funds, one billion tenges for the second year is specified;
26. in column 26 the amount of actually invested funds, one billion tenges for the third year is specified;
27. in column 27 the amount of actually invested funds, one billion tenges the next years is specified;
28. in column 28 the amount of actually invested funds, one billion tenges the current year is specified;
29. in column 29 the amount of amount of actually invested funds, one billion tenges during all the time is specified;
30. in column 30 capacity of the project in kind is specified;
31. in column 31 capacity of the project in value term is specified, to one billion tenges;
32. in column 32 the amount of the made products by the product range is specified, to one billion тг for the first year;
33. in column 33 the amount of the made products by the product range is specified, to one billion тг for the second year;
34. in column 34 the amount of the made products by the product range is specified, to one billion тг for the third year;
35. in column 35 the amount of the made products by the product range is specified, to one billion тг the next years;
36. in column 36 the amount of the made products by the product range is specified, to one billion тг the current year;
37. in column 37 the amount of amount of the made products by the product range is specified, to one billion тг during all the time;
38. in column 38 products export volume by the product range is specified, to one billion тг for the first year;
39. in column 39 products export volume by the product range is specified, to one billion тг for the second year;
40. in column 40 products export volume by the product range is specified, to one billion тг for the third year;
41. in column 41 products export volume by the product range is specified, to one billion тг the next years;
42. in column 42 products export volume by the product range is specified, to one billion тг the current year;
43. in column 43 products export volume amount by the product range is specified, to one billion тг during all the time;
44. in column 44 it is specified the exported countries;
45. in column 45 permanent workplaces, the unit is specified;
46. in column 46 month of commissioning is specified;
47. in column 47 year of commissioning is specified;
48. in column 48 tax assignments, one billion tenges for the first year are specified;
49. in column 49 tax assignments, one billion tenges for the second year are specified;
50. in column 50 tax assignments, one billion tenges for the third year are specified;
51. in column 51 tax assignments, one billion tenges the next years are specified;
52. in column 52 tax assignments, one billion tenges the current year are specified;
53. in column 53 the amount of tax assignments, one billion tenges during all the time is specified;
54. in column 54 the current status is specified;
55. in column 55 contact information is specified.
Form 3. Infrastructure
1) Financing of infrastructure facilities of SEZ/IZ
1. in column 1 the name SEZ/IZ (object) is specified;
2. in column 2 the total cost of construction of infrastructure of SEZ/IZ, one billion tenges according to the feasibility statement is specified;
3. in column 3 allocated funds, one billion tenges for the first year is specified;
4. in column 4 allocated funds, one billion tenges for the second year is specified;
5. in column 5 allocated funds, one billion tenges for the third year is specified;
6. in column 6 allocated funds, one billion tenges the next years is specified;
7. in column 7 allocated funds, one billion tenges for 1 quarter of the current year is specified;
8. in column 8 allocated funds, one billion tenges for the 2nd quarter of the current year is specified;
9. in column 9 allocated funds, one billion tenges for 3rd quarter of the current year is specified;
10. in column 10 allocated funds, one billion tenges for the 4th quarter of the current year is specified;
11. in column 11 the amount of allocated funds, one billion tenges during all the time is specified;
12. in column 12 the mastered means, one billion tenges is specified;
13. in column 13 not development reasons are specified;
14. in column 14 completeness of infrastructure (%) is specified;
15. in column 15 the additional requirement for financing, one billion tenges the current year is specified;
16. in column 16 the additional requirement for financing, one billion tenges the next year is specified;
17. in column 17 the additional requirement for financing, one billion tenges the next year is specified;
18. in column 18 the additional requirement for financing, one billion tenges the next year is specified;
19. in column 19 the additional requirement for financing, one billion tenges the next year is specified;
20. in column 20 the additional requirement for financing, one billion tenges the next year is specified;
21. in column 21 the additional requirement for financing, one billion tenges the next year is specified;
22. in column 22 the note is specified.
2) General information on capacities of infrastructure facilities of SEZ/IZ
1. in column 1 the name of infrastructure facility is specified (water supply, including the following infrastructure facilities, the sewerage, including the following infrastructure facilities, electric utility service, including the following infrastructure facilities, heat supply, including the following infrastructure facilities, gas supply, including the following infrastructure facilities, steam supply, including the following infrastructure facilities, telephone communication, including the following infrastructure facilities, the Internet, including the following infrastructure facilities, utilization of solid waste, including the following infrastructure facilities, utilization of liquid waste, including the following infrastructure facilities, access railway track, including the following infrastructure facilities, highways, including the following infrastructure facilities, the internal highway, the bringing highway.);
2. in column 2 the unit of measure of capacity of object is specified (cubic meters an hour, megawatt, gigacalories per hour, lines, megabits a second, tons per day, kilometers);
3. in column 3 the existing capacities - the capacities which are actually available in the territory of SEZ/IZ on each infrastructure facility are specified;
4. in column 4 power consumptions - capacities which are used by SEZ/IZ and administrative objects operating with participants now are specified;
5. in column 5 free capacities - the capacities of infrastructure facilities available to connection of new participants of SEZ/IZ are specified;
6. in column 6 the planned capacities - capacities which are planned to be created in the territory of SEZ/IZ are specified.
3) Cost of utilities
1. in column 1 the name of utility (water supply, heat supply, electric utility service, the sewerage, gas supply) is specified;
2. in column 2 the unit of measure is specified (cubic meter, gigacalories, kilowatt, cubic meters an hour);
3. in column 3 service unit cost in tenge is specified (it is specified according to applicable fares, taking into account or excluding VAT - depending on the accepted procedure in SEZ/IZ).
4) Need for infrastructure facilities
1. in column 1 the name of object of basic infrastructure (prime necessity) or additional infrastructure which need is had is specified (for example, transformer substation, power line, boiler room, water supply system, the sewerage, the highway);
2. in column 2 capacities of required object are specified (in the corresponding units of measure: cubic meters an hour, megawatts, gigacalories per hour, tons per day, kilometers);
3. in column 3 the approximate need for financing is specified construction or reconstruction of object, in billions of tenges.
Form 4. Parcels of land
in the Section 1 "Distribution of the Territory":
1. in column 1 distribution of the territory of SEZ/IZ is specified: General territory of special economic and industrial zones; usable space; allocated under projects; the territory of the existing projects (general); the territory of projects on implementation phase (general); allocated under infrastructure; constructed; at construction stage; free useful; provided with infrastructure; not the useful territory; in total.
2. in column 2 the area in hectares is specified;
3. in column 3 the note is specified;
in the Section 2 "The Usable Space Allocated to Participants":
1. in column 1 the name of the participant is specified;
2. in column 2 the area in hectares is specified;
3. in column 3 the note is specified;
in the Section 3 "Distribution of the Other Territory":
1. in column 1 the name of infrastructure facility is specified;
2. in column 2 the occupied territory in hectares is specified;
3. in column 3 the note is specified.
Form 5. Share of intra country value
1. in column 1 numbering is specified;
2. in column 2 the name SEZ is specified;
3. in column 3 the name of the participant of SEZ or person performing non-core types of activity is specified;
4. in column 4 identification number (BIN / IIN) is specified;
5. in column 5 the acquisition code is specified (0 goods, 1 work, 2 - service);
6. in column 6 the name and the short (additional) description acquired is specified I RUB;
7. in column 7 the OKED code at the level of 4 signs or the Commodity Nomenclature of Foreign Economic Activity code at the level of 6 signs is specified;
8. in column 8 the name of the supplier is specified;
9. in column 9 the amount of the acquired goods in kind is specified;
10. in column 10 total amount under the agreement, tenge is specified;
11. in column 11 BIN/IIN of the producer of goods to which statements from the register of the Kazakhstan producers of certificate "/CT-KZ" are issued is specified;
12. in column 12 statement No. from the register of the Kazakhstan producers / the certificate of "CT-KZ" is specified;
13. in column 13 statement series from the register of the Kazakhstan producers / the certificate of "CT-KZ" is specified;
14. in column 14 date of issue of the statement from the register of the Kazakhstan producers / the certificate of "CT-KZ" is specified, (day, month, year);
15. in column 15 the intra country value in goods specified in the statement from the register of the Kazakhstan producers / the certificate of "CT-KZ", % is specified;
16. in column 16 intra country value in work (service) is specified, to %.
The certificate of origin of the CT-KZ form keeps the action till January 1, 2026.
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Search in text CTRL-F
If you are guest on our site, you will work in Demo mode. In Demo mode you can see only first page of each document.
With full access you can
Database include more 65000 documents. You can find needed documents using search system.
For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions.
This section provides answers to questions set by users.