ORDER OF THE MINISTER OF INVESTMENTS AND DEVELOPMENT OF THE REPUBLIC OF KAZAKHSTAN

of April 24, 2017 No. 235

About approval of forms of the conclusions about quality of building and construction works and compliance of the performed works to the project, the declaration of conformity

(as amended on 28-03-2023)

According to subitem 22-1) of article 20 of the Law of the Republic of Kazakhstan of July 16, 2001 "About architectural, town-planning and construction activities in the Republic of Kazakhstan" PRIKAZYVAYU:

1. Approve:

1) form of the conclusion about quality of building and construction works according to appendix 1 to this order;

2) form of the conclusion about compliance of the performed works to the project according to appendix 2 to this order;

3) form of the declaration of conformity according to appendix 3 to this order.

2. To provide to committee on cases of construction and housing and communal services of the Ministry for Investments and Development of the Republic of Kazakhstan:

1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;

2) within ten calendar days from the date of state registration of this order the direction it the copy in paper and electronic type in the Kazakh and Russian languages in the Republican state company on the right of economic maintaining "The republican center of legal information" for official publication and inclusion in Reference control bank of regulatory legal acts of the Republic of Kazakhstan;

3) within ten calendar days after state registration of this order the direction it the copy on official publication in periodic printing editions;

4) placement of this order on Internet resource of the Ministry for Investments and Development of the Republic of Kazakhstan;

5) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Legal department of the Ministry for Investments and Development of the Republic of Kazakhstan of data on execution of actions, according to subitems 1), 2), 3) and 4) this Item.

3. To impose control of execution of this order on the supervising vice-minister of investments and development of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Minister of investments and development of the Republic of Kazakhstan

Zh. Kasymbek

Appendix 1

to the Order of the Minister of investments and development of the Republic of Kazakhstan of April 24, 2017 No. 235

form

Conclusion about quality of building and construction works

"__" ________ 20th years

Technical надзор______________________________________________________________

________________________________________________________________________________

name of the organization, surname, name, middle name (in the presence) head, legal address

on behalf of __________________________________________________________________________

________________________________________________________________________________

________________________________________________________________________________

surname, name, middle name (in the presence) experts, No. of certificates, the date of receipt

acting on основании_______________________________________________________

                                                                   No. of the agreement and date

on объекту:_____________________________________________________________________

_______________________________________________________________________________,

                                 name and location of object

which customer является______________________________________________________

_______________________________________________________________________________

 name of the organization, surname, name, middle name (in the presence) head

confirms that:

1. The asset construction was performed

1) contractor (prime contractor) ___________________________________

_________________________________________________________________________

            name of the organization, No. of the license and the date of receipt

in лице___________________________________________________________________

                       surname, name, middle name (in the presence) head

2) subcontract организациями___________________________________________

________________________________________________________________________

________________________________________________________________________

               name of the organization, No. of the license and the date of receipt

in лице___________________________________________________________________;

                     surname, name, middle name (in the presence) head

2. Building and construction works is carried out in terms:

beginning of works ____________________________;

                                   month, year

completion of works _________________________;

                                  month, year

at construction duration, month:

on regulation or on the project of the строительства_____________________________ organization month;

фактически________________________________________________________________ month;

3. Estimated cost on the approved project (design estimates): in total _______ thousands of tenges, including building and construction works ______ thousands of tenges, equipment, tool and stock ___________ thousands of tenges;

4. Estimated cost of the fixed assets accepted in operation _____ thousands of tenges including: cost of building and construction works _______ thousands of tenges; cost of the equipment, tool and stock _______ thousands of tenges;

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.