Document from CIS Legislation database © 2003-2023 SojuzPravoInform LLC

It is registered

Ministry of Justice of Ukraine

April 14, 2017

No. 505/30373

ORDER OF THE MINISTRY OF REGIONAL DEVELOPMENT, CONSTRUCTION AND HOUSING OF UKRAINE

of March 23, 2017 No. 57

About approval of the Procedure for development, coordination and approval of schemes of sanitary cleaning of settlements

According to the Item "e" of article 25 of the Law of Ukraine "About waste" and for the purpose of introduction of single requirements to procedure for development, coordination and approval of schemes of sanitary cleaning of settlements I order:

1. Approve the Procedure for development, coordination and approval of schemes of sanitary cleaning of settlements which is applied.

2. To management of improvement of the territories and public service (Barinov N. A.) together with Legal department (Dorofeyev M. Yu.) provide in accordance with the established procedure provision of this order on state registration in the Ministry of Justice of Ukraine.

3. This order becomes effective from the date of its official publication.

4. To impose control of execution of this order on the deputy minister Kruglyak of E.B.

First Deputy Minister

V.A.Nepogoda

Approved by the Order of the Ministry of Regional Development, Construction and Housing of Ukraine of March 23, 2017, No. 57

Procedure for development, coordination and approval of schemes of sanitary cleaning of settlements

I. General provisions

1. This Procedure determines the mechanism of development, coordination, approval of schemes of sanitary cleaning of settlements (further - the Scheme).

2. The structure and contents of the Scheme are determined by GSN B.2.2-6: 2013 "Structure and contents of the scheme of sanitary cleaning of the settlement" (further - GSN B.2.2-6: 2013).

3. Development, coordination and approval of the Scheme perform executive bodies of village, settlement and city councils, the Kiev and Sevastopol city public administrations - for one or several settlements which are part of the relevant council; Council of Ministers of the Autonomous Republic of Crimea, regional and district public administrations - for the settlements which are part of two and more village, settlement and city councils (further - developer).

4. Aggregate term of development, coordination and approval of the Scheme shall not exceed 12 months (from decision date about its development) without the term of carrying out preproject researches.

5. Development, coordination and approval of the Scheme are performed with observance of requirements of the Law of Ukraine "About the state secret" and resolutions of the Cabinet of Ministers of Ukraine of August 9, 1993 No. 611 "About the list of data which are not trade secret".

6. Modification of the Scheme is performed according to this Procedure.

7. In this Procedure terms are used in the values given in the Law of Ukraine "About waste" and in the State sanitary standards and rules of content of the territories of the inhabited places approved by the order of the Ministry of Health of Ukraine of March 17, 2011 No. 145, registered in the Ministry of Justice of Ukraine on April 5, 2011 at No. 457/19195.

II. Development of the scheme

1. The developer performs development of the Scheme independently or acts as the customer of development of the Scheme on a contract basis.

2. Development of the Scheme is performed independently by the Developer on the following stages:

1) decision making about development of the Scheme;

2) creation of task for development of the Scheme agrees GSN B.2.2-6: 2013;

3) forming of basic data agrees GSN B.2.2-6 to development of the Scheme: 2013;

4) development of the Scheme as a part of text and graphical materials according to GSN B.2.2-6: 2013.

3. If the Developer acts as the customer of development of the Scheme (further - the Customer), its development is performed by subject of managing which has work experience in the sphere of the address with waste (further - the Contractor), based on the agreement on the following stages:

1) adoption by the Customer of the decision on development of the Scheme;

2) creation by the Customer of task for development of the Scheme agrees GSN B.2.2-6: 2013;

3) forming by the Customer of basic data agrees GSN B.2.2-6 to development of the Scheme: 2013;

4) determination of the Contractor on competitive basis and the conclusion of the contract with it;

5) development by the Contractor of the Scheme as a part of text and graphical materials according to GSN B.2.2-6: 2013.

4. At the Scheme development stage as a part of text and graphical materials coordination of the choice of locations of new objects which are planned by the Scheme is performed:

1) outside the settlement, set by the corresponding town-planning documentation, - with structural divisions of Council of Ministers of the Autonomous Republic of Crimea, regional and district public administrations concerning town planning and architecture, agro-industrial development, ecology and natural resources and health care in the territory of which placement of these objects is planned;

2) within the settlement, set by the corresponding town-planning documentation, - with the relevant structural divisions of the Kiev and Sevastopol city public administrations, executive bodies of village, settlement and city councils concerning construction, health care, land relations and protection of the surrounding environment.

For review the choice of locations of new objects which are planned by the Scheme are represented:

list of new objects;

data on the planned place of their placement;

the short feasibility statement on feasibility of placement of these objects on the chosen places.

III. Coordination of the scheme

1. The developed Scheme is approved with the interested bodies:

1) if the Scheme is developed by the Contractor, - the relevant structural divisions of the Customer concerning land relations and protection of the surrounding environment, construction, housing and communal services, the budget, finance and the prices;

2) territorial authority of Public service of Ukraine on safety issues of foodstuff and consumer protections;

3) territorial authority of the State ecological inspection of Ukraine;

4) territorial authority of Public service of Ukraine on emergency situations.

2. For review Schemes move:

text materials of the Scheme on paper and electronic carriers;

graphical materials of the Scheme on paper and electronic carriers (in the presence);

materials in coordination of the choice of locations of the new objects planned by the Scheme;

materials in coordination of the Scheme (in the presence).

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.