ORDER OF THE GOVERNMENT OF THE RUSSIAN FEDERATION

of August 9, 2016 No. 759

About refining of procedure of technology accession to the objects of electric grid economy belonging to the organization for management of single national (all-Russian) power network

The government of the Russian Federation decides:

1. Approve the enclosed changes which are made to Rules of technology connection of power receiving devices of consumers of electrical energy, facilities for production of electrical energy, and also the objects of electric grid economy belonging to the network organizations and other persons, to power networks, approved by the order of the Government of the Russian Federation of December 27, 2004 No. 861 "About approval of Rules of non-discriminatory access to services in transfer of electrical energy and rendering these services, Rules of non-discriminatory access to services in supervisory control in power industry and rendering these services, Rules of non-discriminatory access to services of Trading System Administrator of the wholesale market and rendering these services and Rules of technology connection of power receiving devices of consumers of electrical energy, facilities for production of electrical energy, and also objects of electric grid economy, belonging to the network organizations and other persons, to power networks" (The Russian Federation Code, 2004, No. 52, Art. 5525; 2015, No. 40, Art. 5574).

2. Determine that implementation of technology accession to objects of the organization for management of single national (all-Russian) power network at the level of voltage below 110 kV is allowed:

concerning power receiving devices of consumers of electrical energy and objects of electric grid economy according to the requests for technology accession which are not cancelled at the time of entry into force of this resolution submitted to the organization for management of single national (all-Russian) power network according to the procedure, established by Rules of technology connection of power receiving devices of consumers of electrical energy, facilities for production of electrical energy, and also the objects of electric grid economy belonging to the network organizations and other persons, to power networks, approved by the order of the Government of the Russian Federation of December 27, 2004 No. 861 "About approval of Rules of non-discriminatory access to services in transfer of electrical energy and rendering these services, Rules of non-discriminatory access to services in supervisory control in power industry and rendering these services, Rules of non-discriminatory access to services of Trading System Administrator of the wholesale market and rendering these services and Rules of technology connection of power receiving devices of consumers of electrical energy, facilities for production of electrical energy, and also objects of electric grid economy belonging to the network organizations and other persons to power networks", before entry into force of the Federal Law "About introduction of amendments to the Federal law "About Power Industry" and article 81 of the Federal law "About Joint-stock Companies";

concerning power receiving devices of again constructed objects (put into operation after entry into force of this resolution) greenhouse facility according to the list approved by the Government of the Russian Federation based on the approved offers of the Ministry of Energy of the Russian Federation and Ministry of Agriculture of the Russian Federation created proceeding from the most effective placement of hothouse complexes taking into account minimization of total costs on functioning of hothouse complexes and creation of the corresponding energy infrastructure.

Russian Prime Minister

D. Medvedev

Approved by the Order of the Government of the Russian Federation of August 9, 2016 No. 759

Changes which are made to Rules of technology connection of power receiving devices of consumers of electrical energy, facilities for production of electrical energy, and also the objects of electric grid economy belonging to the network organizations and other persons to power networks

Item 8 (to add 2) with paragraphs of the following content:

"technology connection of the power receiving devices providing power supply of specially created technical devices, performing acceptance, processing and transfer of audio-and (or) audiovisual, and also other messages on origin threat about emergence of emergency situations and rules of conduct of the population in such situations.

At the level of voltage below 110 kV technology connection of again attached power receiving devices of consumers of electrical energy and the territorial network organizations to the objects of electric grid economy belonging to the organization for management of single national (all-Russian) power network, put into operation till January 1, 2018 and included in the list of the objects of electric grid economy belonging to the organization for management of single national (all-Russian) power network to which implementation of technology connection of again attached power receiving devices of consumers at the level of voltage below 110 kV, No. 1671-r approved by the order of the Government of the Russian Federation of August 9, 2016, in the absence of need of implementation of construction and (or) reconstruction with increase in transformer capacity of such objects is allowed is allowed except for construction of facilities of electric grid economy from the existing objects of electric grid economy to the attached power receiving devices and (or) power generation facilities.

Modification of the list specified in paragraph seven of this Item is performed by the Government of the Russian Federation based on the offers of Government Commission on Electricity Generation created taking into account the corresponding reasons provided by the Ministry of Energy of the Russian Federation and the Ministry of Economic Development of the Russian Federation.".

 

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.