I.O'S ORDER. MINISTER OF ENERGY OF THE REPUBLIC OF KAZAKHSTAN

of July 27, 2016 No. 343

About approval of the standard agreement about connection of objects for use of renewable energy resources, objects for energy waste recycling, and also rules and terms of its conclusion

(as amended on 23-09-2024)

According to the subitem 376) of Item 15 of the Regulations on the Department of Energy of the Republic of Kazakhstan approved by the order of the Government of the Republic of Kazakhstan of September 19, 2014 No. 994, I ORDER:

1. Approve:

1) the Standard agreement about connection of objects for use of renewable energy resources, objects for energy waste recycling according to appendix 1 to this order;

2) Governed also closing dates of the standard agreement about connection of objects for use of renewable energy resources, objects for energy waste recycling according to appendix 2 to this order.

2. To provide to department on renewable energy resources of the Department of Energy of the Republic of Kazakhstan in the procedure established by the legislation of the Republic of Kazakhstan:

1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;

2) the direction of the copy of this order on official publication in periodic printing editions and information system of law of Ad_let within ten calendar days after its state registration in the Ministry of Justice of the Republic of Kazakhstan, and also in the Republican state company on the right of economic maintaining "The republican center of legal information" of the Ministry of Justice of the Republic of Kazakhstan" within five working days from the date of receipt of the registered order;

3) placement of this order on official Internet resource of the Department of Energy of the Republic of Kazakhstan and the intranet portal of state bodies;

4) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Department of legal service of the Department of Energy of the Republic of Kazakhstan of data on execution of the actions provided by subitems 2) and 3) of this Item.

3. To impose control of execution of this order on the supervising vice-Minister of Energy of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Deputy. Minister of Energy of the Republic of Kazakhstan

M. Myrzagaliyev

 

Appendix 1

to the Order of the acting minister of power industry of the Republic of Kazakhstan of July 27, 2016 No. 343

The standard agreement about connection of objects for use of renewable energy resources, objects for energy waste recycling

___________________________                                                "____" ____________ 20 __.

(place of agreement)

___________________________________________________________________

                   (full name of the organization),

hereinafter referred to as the Power transferring organization on behalf of

___________________________________________________________________

                         (position, First name, middle initial, last name)

acting on the basis of the, ________________________________, on the one hand, and ________________________________________________________

                                                                                                                                              (full name of the organization)

hereinafter referred to as the Power making organization on behalf of ___________________________________________________________________,

                                                                                                                                             (position, First name, middle initial, last name)

acting on the basis of the _______________________________, on the other hand, jointly the referred to as Parties, signed this Agreement (further - the Agreement) as follows.

Chapter 1. The basic concepts used in the Agreement

1. In the Agreement the following main determinations are used:

1) the system operator – the national company exercising centralized supervisory control, ensuring parallel work with power supply systems of other states, maintenance of balance in single electric utility system of the Republic of Kazakhstan, rendering system services and acquisition of support services at subjects of the wholesale market of electrical energy, and also maintenance and maintenance in operational readiness of national power grid and providing its development;

2) specifications - the technical requirements necessary for connection to power networks;

3) connection to power network - physical connection of object for use of renewable sources of energy/object for energy waste recycling of the Power making organization to power network of the Power transferring organization;

4) point of connection to power network - the place of physical connection of object for use of renewable sources of energies/objects for energy waste recycling of the Power making organization with power network of the Power transferring organization;

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.