of March 1, 2016 No. 169
About approval of comprehensive plan of development of the electrical power sphere till 2025 taking into account input of the Belarusian nuclear power plant and cross-industry package of measures for increase in electric power consumption till 2025
The Council of Ministers of the Republic of Belarus DECIDES:
1. Approve enclosed:
comprehensive plan of development of the electrical power sphere till 2025 taking into account input of the Belarusian nuclear power plant (further - comprehensive plan);
cross-industry package of measures for increase in electric power consumption till 2025 (further - cross-industry package of measures).
2. Responsible for coordination of work on accomplishment of comprehensive plan to determine the Department of Energy.
2-1. To impose control over the implementation of cross-industry package of measures on Department for energy efficiency of the State committee on standardization.
3. To perform financing of actions of comprehensive plan and cross-industry package of measures at the expense of the means of the republican budget provided within implementation of state programs, own means of the organizations - contractors of comprehensive plan, and also other sources.
4. To represent to the republican state bodies and other state organizations subordinated to the Government of the Republic of Belarus, regional executive committees and the Minsk Gorispolkom annually till February 15 of the year following reporting:
in the Department of Energy - information on the course of accomplishment of comprehensive plan;
in Department on energy efficiency of the State committee on standardization - information on the course of accomplishment of cross-industry package of measures.
Inform Council of Ministers of the Republic of Belarus annually till March 1 of the year following reporting:
To Department of Energy - about the course of accomplishment of the actions included in comprehensive plan;
To department on energy efficiency of the State committee on standardization - about the course of accomplishment of the actions included in cross-industry package of measures.
Prime Minister of the Republic of Belarus
A. Kobyakov
Approved by the Resolution of Council of Ministers of the Republic of Belarus of March 1, 2016 , No. 169
Name of actions |
Realization term |
Contractors |
The expected result |
Realization of technical actions | |||
1. Completion of construction of the Belarusian nuclear power plant |
2019–2022 |
Ministry of Energy, republican unitary enterprise "Belarusian Nuclear Power Plant" |
commissioning of the Belarusian nuclear power plant (2400 MW) |
2. Development and implementation of subprogrammes (Sections of subprogrammes) of the state programs, the industry development program of power industry including: |
2016–2020, |
Ministry of Energy, GPO "Belenergo" |
share of the dominating resource (gas) in production of heat and electrical energy: |
in 2020 – 70 percent | |||
in 2025 – 60 percent | |||
the balanced development and upgrade of the generating sources based on implementation of innovative technologies and conclusion from operation physically and the obsolete energy equipment |
2016–2025 |
Ministry of Energy |
the total relation of installed capacity to the maximum actual load in power supply system: |
in 2020 – 160 percent | |||
in 2025 – 155 percent | |||
specific weight of accumulated depreciation in original cost of fixed assets of the organizations for production of electricity: | |||
in 2020 – no more than 43 percent | |||
in 2025 – less than 45 percent | |||
construction and reconstruction of power networks and substations, including in areas of the housing estate, the individual housing estate and in rural settlements, of annually at least 1500 km |
2016–2025 |
" |
the relation of average daily number of violations of electric utility service of settlements to total quantity of settlements – percent 0,4 |
specific weight of accumulated depreciation in original cost of fixed assets of the organizations for construction and reconstruction of power networks and substations: | |||
in 2020 – 50 percent | |||
in 2025 – 45 percent | |||
construction and reconstruction of thermal networks, including infrastructures to housing (amounts of replacement of thermal networks are determined annually taking into account their technical condition and the allocated financing) |
2016–2025 |
Ministry of Energy, GPO "Belenergo" |
specific weight of accumulated depreciation in original cost of fixed assets of the organizations for construction and reconstruction of thermal networks: |
in 2020 – 45 percent | |||
in 2025 – 45 percent |
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions. This section provides answers to questions set by users.