ORDER OF THE MINISTER OF ENERGY OF THE REPUBLIC OF KAZAKHSTAN

of October 29, 2015 No. 627

About approval of the regulating technical document in the field of technical and economic characteristics of the equipment of energy objects

According to the subitem 49) article 5 of the Law of the Republic of Kazakhstan of July 9, 2004 "About power industry", PRIKAZYVAYU:

1. Approve the enclosed regulating technical document in the field of technical and economic characteristics of the equipment of energy objects.

2. To provide to department of power industry of the Department of Energy of the Republic of Kazakhstan in the procedure established by the legislation of the Republic of Kazakhstan:

1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;

2) the direction on official publication of the copy of this order within ten calendar days after its state registration in the Ministry of Justice of the Republic of Kazakhstan in periodic printing editions and in information system of law of Ad_let;

3) the direction of the copy of this order within ten calendar days from the date of its obtaining in the republican state company on the right of economic maintaining "The republican center of legal information" of the Ministry of Justice of the Republic of Kazakhstan;

4) placement of this order on official Internet resource of the Department of Energy of the Republic of Kazakhstan and on the intranet portal of state bodies;

5) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Department of legal service of the Department of Energy of the Republic of Kazakhstan of data on execution of the actions provided by subitems 2), 3) and 4) of this Item.

3. To impose control of execution of this order on the supervising vice-Minister of Energy of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Minister of Energy of the Republic of Kazakhstan

B. School student

It is approved

Minister of national economy of the Republic of Kazakhstan

November 17, 2015

 

______________ E.Dosayev

Approved by the Order of the Minister of Energy of the Republic of Kazakhstan of October 29, 2015, No. 627

The regulating technical document in the field of technical and economic characteristics of the equipment of energy objects

Section 1. General provisions

1. This Regulating technical document in the field of technical and economic characteristics of the equipment of energy objects (further – the specifications and technical documentation) is developed according to the laws of the Republic of Kazakhstan of July 9, 2004 "About power industry", of July 16, 2001 "About architectural, town-planning and construction activities in the Republic of Kazakhstan" and determines functions and relations of the organizations which are taking part in accomplishment of commissioning on the equipment of energy objects are established by the general principle of the organization of commissioning on the equipment of energy objects, their staging and content on stages, and also procedure for their accomplishment, determines quotations for calculation of estimated cost of accomplishment of commissioning on the equipment of energy objects.

2. Action of this specifications and technical documentation extends to commissioning period on the equipment of energy objects up to acceptance for operation, and the rules of this specifications and technical documentation are respected by the companies and the organizations of all patterns of ownership performing commissioning on the equipment of energy objects of the Republic of Kazakhstan.

3. In this specifications and technical documentation the following basic concepts are applied:

1) autonomous adjustment – adjusting without external technology and managing relations;

2) the leading adjustment organization – the adjustment organization which is carrying out the main amount of works on adjustment of functional node and bearing responsibility for results of works on this node;

3) trial operation – the operation of control facilities and management which is carried out by the customer's forces for the purpose of determination of readiness of nodes and systems, operational and maintenance force to long operation with observance of the technology modes and guaranteed performances of reliability. At the same time detection of defects and malfunctions makes personnel of the customer, and elimination – the organization, them allowed (construction, mounting, adjustment);

4) functional and technology node (functional node) – functionally allocated complex of constructions, the equipment and devices (designs, devices, machines and mechanisms, fittings, pipe and electric postings, controls and control) combined by process of accomplishment of autonomous production and technology function and in total with other functional nodes the providing single process of release of end products. Allocation of functional nodes is made for the purpose of ensuring technology of functional and nodal production of commissioning for increase in their quality, organizational technological level and efficiency.

Section 2. Commissioning of the equipment of energy objects

1. Organization of commissioning of the equipment of energy objects

4. The main technology of commissioning (further – the Party of Russian Taxpayers) is carrying out them by the principle of adjustment of functional and technology nodes (pouzlovy adjustment).

Pouzlovy adjustment begins after carrying out individual testing of the equipment and continues before input of the equipment in operation.

5. Preparation for the Party of Russian Taxpayers begins:

1) for power stations (objects) with head and experimental samples of the capital equipment or for the first power stations on again under construction and reconstructed objects – from the moment of exit of specifying (decision) of the customer on appointment of the parent adjustment organization, but not later than 18 months till the planned beginning of the period of complex approbation;

2) for power stations (objects) with mass-produced models of the capital equipment – no later than 12–18 months till the planned beginning of the period of complex approbation.

Need for the parent adjustment organization is determined by the customer. At the same time appointment of the parent adjustment organization is made by the customer in coordination with the prime contractor (further – the General contractor).

6. Organizational support of the Party of Russian Taxpayers includes:

1) creation of the coordination plan of the Party of Russian Taxpayers;

2) development of estimate documentation on the Party of Russian Taxpayers;

3) the conclusion of works agreements on production of the Party of Russian Taxpayers;

4) opening of financing of the Party of Russian Taxpayers in the terms providing settlings with the attracted commissioning organizations at all stages.

Characteristics of works on organizational support of the Party of Russian Taxpayers are given in appendix 1 to this specifications and technical documentation.

The recommended form of the coordination plan of accomplishment of the Party of Russian Taxpayers is given in appendix 2 to this specifications and technical documentation.

7. Technical supply of the Party of Russian Taxpayers includes:

1) project of the Party of Russian Taxpayers;

2) acquaintance with the project of the power station and (or) energy object, project analysis and issue of notes on the project;

3) development of commissioning documentation;

4) development of temporary operational documentation;

5) training of operational personnel for production of the Party of Russian Taxpayers;

6) incoming inspection of processing equipment, pipelines, equipment and electrotechnical equipment, control facilities and management of engineering procedures;

7) control of installation and construction works.

The characteristic of works on technical supply during preparation of the Party of Russian Taxpayers is given in appendix 3 to this specifications and technical documentation.

Recommended forms of the list and structure of the equipment of functional and technology nodes, and also the general technology schedule of the Party of Russian Taxpayers entering technical supply of the Party of Russian Taxpayers are given in appendices 4 and 5 to this specifications and technical documentation.

8. The material security of the Party of Russian Taxpayers includes:

1) financing of the Party of Russian Taxpayers;

2) ensuring production of the Party of Russian Taxpayers with the equipment, devices, materials, energy resources and communication;

3) providing the organizations participating in the Party of Russian Taxpayers, production and sanitary and household rooms, medical attendance, individual protection equipment, transport services.

9. The list of the equipment, devices and systems of automated management of energy object on which are made by the Party of Russian Taxpayers is given in appendix 6 to this specifications and technical documentation.

10. The technology sequence, duration and priority of carrying out prestarting and the Party of Russian Taxpayers is determined by the schedule of carrying out the Party of Russian Taxpayers which is part of commissioning documentation.

The schedule provides parallel carrying out autonomous adjustment of means of the automated process control system (further – industrial control system) and installation of the capital equipment. In graphics the following organizational and technical events are reflected:

1) the advancing completion of construction and finishing works in block control panel with inclusion of systems of lighting, fire extinguishing, ventilation, conditioning and transfer of these rooms under installation of the industrial control system technical means;

2) anticipatory giving of tension and adjustment of system of uninterrupted food of means of industrial control system in block control panel;

3) for timely scrolling of mechanisms, successful adjustment of systems, functional group management (further – federal state institution) and functional groups early giving of tension in the main body for own needs of energy object;

4) providing necessary time for high-quality carrying out pouzlovy starting adjustment, the end of installation and individual testing of the capital power equipment prior to pouzlovy adjustment;

5) the rational procedure for carrying out complex adjustment allowing to complete complex approbation of the block (installation) and trial start-up in the shortest possible time.

Values of the minimum terms of accomplishment of the main actions in case of accomplishment of the Party of Russian Taxpayers for power units (separate boiler rooms or turbine installations) with developed by industrial control system (where these means perform the main management functions and displays of information) are given in appendix 7 to this specifications and technical documentation.

2. Stages of commissioning, organization of accomplishment of commissioning

11. According to requirements of this specifications and technical documentation complete providing the Party of Russian Taxpayers is performed by the customer, including:

1) organizational;

2) technical;

3) material.

12. The complete cycle of carrying out the Party of Russian Taxpayers includes eight main stages:

1) preparatory stage;

2) premounting audit and check of the equipment: machines and mechanisms, devices, fittings, controls and submission of information;

3) step-by-step acceptance from installation and individual testing of the equipment;

4) pouzlovy acceptance from individual testing of the equipment of functional nodes (including necessary control of completeness and quality of installation). According to Construction Norms and Regulations of PK 3.05-09, Construction Norms and Regulations PK 4.04-10 and Construction Norms and Regulations 3.05.07 for different types of the equipment terms of stages of step-by-step acceptance of the equipment from installation and individual testing depend on equipment type. Pouzlovy acceptance serves for check of readiness of all equipment of node for pouzlovy adjustment at the time of its beginning;

5) pouzlovy starting (further – starting) adjustment of functional nodes on the idle equipment (further – cold adjustment) and their approbation under loading. Delivery of functional nodes from starting adjustment in the operation mode, in check of construction readiness and in pouzlovy complex adjustment on the working equipment;

6) approbation of the block (or the separate package boiler, turbine unit) with synchronization (or without it for the separate package boiler) and set of loading for check of its complete construction readiness;

7) pouzlovy complex (further – complex) adjustment and testing of functional nodes, including subsystems of industrial control system and operational contour of block control panel for working off of the modes of the equipment. Trial operation of functional and technology nodes, including control and management system, identification and elimination of defects, transfer of functional nodes to commercial operation. Carrying out complex approbation of the block (installation);

8) acceptance of the block (installation) in operation is performed by the customer with carrying out necessary testing of the power equipment and with execution of the relevant act according to requirements of Chapter 32 of the Civil code and Chapter 11 of the Law of the Republic of Kazakhstan "About architectural, town-planning and construction activities in the Republic of Kazakhstan".

13. Two organization types of the Party of Russian Taxpayers on the equipment are provided:

1) works, the made specialists of one profession (heatmechanics, electricians, specialists of industrial control system) completed in crews and who are carrying out adjustment transactions irrespective of specialists of other professions;

2) the works which are made integrated pouzlovy teams (further – nodal crews). Each nodal crew includes workers of all professions necessary for adjustment of this functional and technology node.

14. The first organization type of works is applied:

1) in case of premounting audit, check, step-by-step acceptance from installation and individual testing of the equipment;

2) on initial stage of complex adjustment of nodes in case of feasibility of carrying out initial ensuring reliability of operation of the equipment in project amount separately by its types.

15. Since stage of pouzlovy acceptance from individual approbation and before acceptance of the block (installation) by the customer (except for initial stage of complex adjustment) the Party of Russian Taxpayers is carried out by forces of nodal crews and will be organized by complex working subcommittees.

16. The nodal crew will be organized by the solution of complex working subcommittee during individual testing of the equipment from among leading experts of the organizations performing installation and adjustment works on this functional node on agreements. For accomplishment of the Party of Russian Taxpayers workers from structure of the mounting and adjustment organizations can be attracted by nodal crew in addition.

The nodal crew is headed by the foreman appointed from among highly qualified specialists of the leading adjustment organization in node, the customer, the research organization or manufacturing plant of the equipment.

Foremen of nodal crews, and in necessary cases and all structure of nodal crew, are appointed by the order of the customer or in case of "turnkey" commissioning of the object – the general contractor.

The foreman of nodal crew and the crew subordinated to him can carry out the Party of Russian Taxpayers on two and more functional nodes.

17. The complex working subcommittee includes in the structure workers of all specialties necessary for the organization and acceptance of works on node.

18. Complex working subcommittees are included:

1) foremen of the corresponding crews;

2) customer representatives;

3) representatives of manufacturing plants of the equipment;

4) general designer;

5) contract organizations;

6) representatives of the heatmounting organization;

7) representatives of the electromounting organization;

8) representatives of the leading adjustment organization;

9) the research organizations participating in designing of energy object.

The specified representatives are allocated by heads of production divisions of the relevant organizations for the request of the chairman of complex working subcommittee.

Chairmen of complex working subcommittees are appointed by the order of the customer, and in case of "turnkey" commissioning of the objects – the order of the general contractor from among experienced and competent specialists of the customer or (in coordination with management) the leading adjustment organizations on this node, the research organizations, and also manufacturing plants of the equipment. The same specialist can be appointed the chairman of two and more complex working subcommittees.

The chairman of complex working subcommittee is member of the working commission. Appointment of chairmen and creation of complex working subcommittees is made during individual testing of the equipment.

19. Acceptance and input of objects in the operation and creation of inspection stipulated in this NDT are performed according to requirements of Chapter 32 of the Civil code and Chapter 11 of the Law of the Republic of Kazakhstan "About architectural, town-planning and construction activities in the Republic of Kazakhstan".

Paragraph 1. The work content on stages of accomplishment and management of works

20. The Party of Russian Taxpayers production organization provides consecutive "coupling" of nodes of the block or separate installation with exit to their complete functional coordination during complex adjustment from stage to stage.

21. The preparatory stage of the Party of Russian Taxpayers begins after preparation (release) of working drawings. At this stage it is made:

1) studying and analysis of project and factory documentation, determination of compliance of the project documentation to regulating documents, prototype solutions and best practices, development of notes and recommendations about remedial action;

2) creation of the project of production of the Party of Russian Taxpayers, including actions for safety and labor protection;

3) development and approval of working programs for adjustment and launch of the equipment;

4) preparation of the park of the measuring equipment, test equipment and devices, organization and equipment of object laboratory, providing workplaces with devices, tool and instructive-methodological materials;

5) creation of the list of documentation necessary on different production stages and acceptance of the Party of Russian Taxpayers on each functional node;

6) development of the first edition of operational instructions.

22. Works on preparatory stage of the Party of Russian Taxpayers are performed by the participating organizations of the Party of Russian Taxpayers according to the coordination plan individually with necessary mutual consultations.

23. At stage of premounting audit and check of the equipment, machines, mechanisms, armature, control facilities and managements common operating-technical directorship is performed by the customer on behalf of the deputy chief engineer of energy object for repair or installation.

24. The procedure and amount of carrying out audits and checks are established according to rules, technical regulations, standards and instructions of manufacturing plants.

25. Audit is carried out by the respective workshops of energy objects with involvement of the mounting, repair and adjustment shops.

Workshops provide the organization of workplaces for maintenance and adjustment force in the rooms allocated for this purpose by management of energy object.

26. At stage of step-by-step acceptance of the equipment from installation and individual testing common operating-technical directorship is performed by the deputy chief engineer of energy object for installation.

27. The procedure for acceptance and individual testing of oborudovaniye is established by heads of workshops of energy object together with the corresponding heads of crews of the parent commissioning organization, division managers of the construction, mounting and adjustment organizations, chief personnel of manufacturing plants, according to rules, technical regulations, standards and instructions of manufacturing plants.

28. Adjustment works are performed by the adjustment organizations according to the coordination plan. Workshops provide the organization of workplaces of adjustment personnel in the rooms allocated for accomplishment of these works as management of energy object.

Result of accomplishment of this stage is execution of the act of the working commission of acceptance of the equipment after individual testing in the form provided by appendix 8 to this specifications and technical documentation.

Giving of tension for accomplishment of the Party of Russian Taxpayers is performed by the electric power supplier according to the Regulations for electrical installation approved by the order of the Minister of Energy of the Republic of Kazakhstan of March 20, 2015 No. 230 (it is registered in the Register of state registration of regulatory legal acts No. 10851).

29. At stage of pouzlovy acceptance of the equipment from installation and individual testing of the equipment of functional nodes of the capital and all-station equipment common operating-technical directorship is performed by the deputy chief engineer of energy object for operation.

30. Acceptance of functional nodes of the equipment from installation and individual testing is made in a complex from the construction, heatmounting, electromounting and adjustment organizations with consideration of readiness of node, regarding construction, heatmounting, electric installation work and individual testing, with consideration of acts for the hidden works and the documents (acts, protocols, entries in magazines) constituted in case of audit of the equipment, step-by-step acceptance after individual testing.

31. By the beginning of pouzlovy adjustment and pouzlovy approbation works completely come to the end:

1) on installation of processing equipment of node;

2) on processing equipment with accomplishment of the adjustment transactions which are not requiring turning on of the equipment in work;

3) on autonomous adjustment of sites of the subsystems of industrial control system entering this node in volume of the special software of subsystem of collection and preprocessing of information, information base, subsystem of submission of information, subsystem of technology seal of programs of diagnostics of technical means; information channels and panel of reproduction of signals; cases of subsystems of management, blocking, protection and alarm system; schemes of control of mechanisms, the locking and regulating armature; cases of subsystem of automatic control; cases (with their check on simulators) subsystems of federal state institution; operational contour of block control panel and all communications within block control panel.

32. Carrying out pouzlovy acceptance of the equipment from installation is performed by complex working subcommittee.

Following the results of the specified acceptance the acceptance act of functional node from installation and individual testing in starting nodal adjustment approved by the chief engineer of energy object is drawn up. The form of the act is given in appendix 9 to this specifications and technical documentation.

If in the course of acceptance of node from installation and individual testing defects and subquality work are revealed, then acceptance stops before their elimination.

Need of performance of works, not provided by the project, factory instructions and other documents on the Party of Russian Taxpayers, is drawn up by the separate act of the working commission.

33. At stage of starting adjustment of functional nodes on the idle equipment (cold adjustment) and their approbations under loading (with giving of tension, air, couple, waters, oils with carrying out kindling of copper), pouzlovy acceptance in the subsequent complex adjustment the common technical guidance is performed by the deputy chief engineer of energy object for operation.

34. Directly starting adjustment of node is carried out by nodal crew under the leadership of the foreman.

35. Works at stage of starting adjustment and approbation of functional nodes are carried out according to the working programs approved by the chief engineer of energy object.

36. Cold adjustment of functional node is considered complete, in cases:

1) accomplishment all of necessary calibrations of analog devices and check of factory settings;

2) checks of correctness of passing of all analog signals from sensors to means of automatic equipment, computer facilities, to devices and signaling devices;

3) exposure of all settings of protection and alarm system;

4) checks of the course of regulating authorities and electromagnetic valves;

5) checks of correctness of passing of signal of the discrete devices and sensors used in systems of protection, blocking, automatic control and alarm system to computer facilities and its means of display, individual devices, signaling devices and control units;

6) otkalibrovaniye and limiting checks of switches of torques of engines and indexes of provision;

7) checks of the switching equipment;

8) checks of the direction of rotation of drives of technology mechanisms;

9) checks of the direction of movement of executive mechanisms and the showing devices in case of corrective action;

10) establishments of possibility of operational management from control panel;

11) checks of system of protection, blocking, the alarm system and logical management (as far as it is possible without the technology mode);

12) checks of orientation of impact of systems of automatic control, exposure of calculated parameters of their setup;

13) sgenerirovannost and verifications of the general software of industrial control system;

14) loadings and checks on simulators of the special software of industrial control system (as far as it is possible without the technology mode);

15) accomplishment of scrolling of mechanisms idling, establishments of the parameters characterizing mechanism condition idling in the limits set by standards, factory, project and other normative and technology documentation.

37. Accomplishment of Items of cold adjustment is reflected in the Magazine of readiness of functional and technology node for testing under loading. The form of the magazine is given in appendix 10 to this specifications and technical documentation.

38. Approbation of node under loading is carried out after full completion of its cold adjustment.

39. The stage of starting adjustment and approbation of nodes of the equipment comes to an end with trial start-up during which adjustment of settings, debugging, check and inclusion in work (on the equipment put into operation) subsystems of protection, blocking, automatic control of excitement, the alarm system, automatic system of regulation, federal state institution and subsystem of submission of information in the amount necessary for safety and reliability of carrying out approbation of the block (or installations comes to the end) for the purpose of check of its construction readiness with capture of loading, with its exit in the mode of operation and complex adjustment. In technical programs of approbation of functional nodes under loading the role and the works performed by operational personnel is specified.

40. The organization of approbation of node after starting adjustment for the purpose of its acceptance for check of construction readiness and in complex adjustment is performed by complex working subcommittee.

41. If in the course of approbation of node damages, defects or subquality work are revealed, then approbation is interrupted and carried out after their elimination.

42. Completion of stage of pouzlovy starting adjustment of functional nodes on the idle equipment and their approbations under loading on each node is drawn up by the test report of functional and technology node approved by the chief engineer of energy object. The form of the protocol is given in appendix 11 to this specifications and technical documentation.

The node is deemed accepted for check of construction readiness and in complex adjustment if there are acceptance acts of functional node from installation and individual testing in starting nodal adjustment specified in Item 32 of this specifications and technical documentation and also the test report of node approved by the chief engineer of energy object.

43. Check of construction readiness of start-up complex of the power unit or separate aggregate is made according to the special technical program providing launch of the equipment according to project schemes. At the same time for the separate boiler aggregate receipt of vapor of project parameters, and for the power unit and separate turbine unit with the generator – synchronization and set of electric loading is provided.

44. The program of check of construction readiness is developed by the parent adjustment organization and affirms her chief engineer and the chief engineer of energy object.

In the absence of the parent commissioning organization the program is developed and approved by the customer, and in case of "turnkey" commissioning of the object – the general contractor, involving in development of the program the mounting and adjustment organizations.

45. Operational management of the equipment is exercised by operational personnel of the customer according to the operational instructions which are in advance developed according to instructions of manufacturing plants and the program of check of construction readiness.

46. Personnel of the mounting, adjustment, research organizations and chief personnel of manufacturing plants of the equipment take part in check of readiness according to the program.

47. The technical lead of check of construction readiness is the chief engineer of energy object.

48. In case of completion of stage of pouzlovy complex adjustment and testing of functional nodes of the Party of Russian Taxpayers the statement by working inspection about acceptance of the equipment after check of construction readiness is drawn up. The list of the defects of the equipment, installation and construction revealed when testing, and also the program schedule of complex adjustment of nodes and approbation of the block or the separate aggregate is attached to the act. The act is approved by the customer's head. The form of the act is given in appendix 12 to this specifications and technical documentation.

The defects of the equipment, construction and installation revealed when checking construction readiness of start-up complex are eliminated prior to complex pouzlovy adjusting.

49. At stage of complex adjustment of nodes pouzlovy adjustment, testing (research) of the equipment in different operating modes is carried out:

1) in case of the stopped block or the separate aggregate with inclusion in work of separate functional technology nodes;

2) in case of start-up and stops of the block or separate aggregate according to the program of adjustment testing;

3) in case of execution of electric loading at the level set according to the adjustment program.

Repair and honing works are carried out to the same period on the stopped equipment, the defects revealed in the course of adjustment of nodes are eliminated.

50. The program of complex adjustment of nodes provides at the first stage separate work of specialists of different professions for initial adjustment of separate types of the equipment for the purpose of ensuring reliability of installation in project amount, and then – complex work of the nodal crews created at acceptance stage under technical guidance of foremen.

51. Completion of adjustment on nodes is drawn up by nodal crews protocols of carrying out complex testing of nodes (in necessary operating modes of energy object which affirm the chief engineer of energy object).

During the same period complex adjustments of subsystems of industrial control system (including operational contour of block control panel), their trial operation and transfer to commercial operation are made.

52. Operation of the equipment during complex adjustment is provided according to separate programs and power generation according to the dispatching schedule is not planned for this period.

During complex adjustment it is carried out:

1) technology debugging of functional nodes during the operation of the equipment in the variable and stationary modes;

2) carrying out and working off of launches of the equipment from different thermal conditions according to schedules of manufacturing plants;

3) debugging of information channels of discrete and analog parameters, and also adjustment of information base by results of operation of the equipment;

4) experimental determination of static and dynamic characteristics of the equipment, inclusion in work of systems of automatic control in project amount;

5) adjustment and adjustment of technology algorithms and programs of complex of tasks of industrial control system on the operative equipment;

6) adjustment of systems of federal state institution with adjustment of technology algorithms and programs of federal state institution and blocking by results of start-up;

7) adjustment of operational technical documentation;

8) working off of control modes and interaction between operation personnel in the conditions of acting with industrial control system and in case of its refusals;

9) trial operation of complex of tasks and subsystems of industrial control system with carrying out testing in variable and stationary operating modes of the equipment, its check on capture greatest possible (within project) and the longest loading;

10) transfer of start-up complex of tasks and subsystems of industrial control system as a part of the power equipment put into commercial operation.

Complex adjustment comes to an end with carrying out complex approbation of the equipment with execution of the act of the working commission of acceptance of the equipment after complex approbation in the form provided by appendix 13 to this specifications and technical documentation.

53. After completion of works on the program schedule of complex adjustment of the power unit or the separate aggregate and its complex approbation acceptance of the called equipment in operation is made. Acceptance for operation is made by the customer with appointment in necessary cases of control approbations and testing according to requirements of Chapter 32 of the Civil code and Chapter 11 of the Law of the Republic of Kazakhstan "About architectural, town-planning and construction activities in the Republic of Kazakhstan".

54. Approbations and testing are carried out under technical guidance of the chief engineer of energy object according to the program approved by the customer. At the same time it is made:

1) check of operating modes of the package boiler, turbine unit, the generator, transformer and service equipment during the work on the main fuel and control algorithms of functional nodes in the stationary and variable modes;

2) complex check of all subsystems of industrial control system;

3) check of joint operation of the main aggregates and the service equipment in case of greatest possible (within project) loading;

4) other necessary approbations and testing.

55. In case of successful acceptance by the customer of energy object or installation in operation the act of acceptance of object according to requirements of Chapter 32 of the Civil code and Chapter 11 of the Law of the Republic of Kazakhstan "About architectural, town-planning and construction activities in the Republic of Kazakhstan" is drawn up.

3. Distribution of the main works performed by the organizations participating in commissioning

56. The main members of the Party of Russian Taxpayers on energy object are:

1) customer;

2) contract organization;

3) subcontract specialized organizations (mounting, adjustment and others);

4) general designer;

5) subcontract project organizations;

6) the research organizations – developers of technical solutions;

7) adjustment personnel of manufacturing plants of the equipment.

Depending on specific conditions combination of functions of several participants by one organization is possible.

57. The customer together with the contract organization develops decisions on the organization of construction process, determines production technologies of works according to the plan of the Party of Russian Taxpayers.

58. The contract organization together with the project organizations participates in creation of project and technology documentation on accomplishment of the Party of Russian Taxpayers, the design estimates and working drawings and draws up the executive documentation and other necessary documents provided by agreements.

59. The customer together with the contract organization:

1) performs common, operational and technical management behind quality of construction, installation, adjustment and testing of the equipment;

2) participates in carrying out prestarting and starting transactions on the equipment, nodes and the block;

3) participates in work of inspections;

4) provides transaction and carrying out premounting audit of the equipment and equipment, elimination of defects of the equipment, construction and installation.

60. The customer provides financing of the Party of Russian Taxpayers in the terms providing settlings with the attracted commissioning organizations at all stages.

61. The customer together with the contract organization provides carrying out the Party of Russian Taxpayers at all stages:

1) qualified operational personnel (since pouzlovy approbation);

2) working means and materials in necessary quantities;

3) model devices, project and factory technical documentation on the equipment and equipment.

62. The customer together with the contract organization controls ensuring safety of the equipment and installations, systems of experimental control, and also documentation, the equipment and the equipment of the organizations participating in carrying out the Party of Russian Taxpayers on energy object and the mode excluding access for strangers.

63. The customer together with the contract organization controls providing personnel of the commissioning and research organizations with service and laboratory premises.

64. The customer together with the general contractor develops the actions providing safe working conditions and controls taking measures of general nature to labor protection, industrial, fire and ecological safety on energy object when carrying out the Party of Russian Taxpayers according to requirements of Chapter 35 of the Labor Code of the Republic of Kazakhstan, Chapter 30 of the Ecological code of the Republic of Kazakhstan, the Regulations for electrical installation approved by the order of the Minister of Energy of the Republic of Kazakhstan of March 20, 2015 No. 230 (it is registered in the Register of state registration of regulatory legal acts No. 10851).

65. Under the organization of "turnkey" construction of facilities the customer can transfer part of the functions to the general contractor.

In this case the contract organization performs works and functions of the customer in relations with the specialized organizations to which under agreements of sub contracting accomplishment of separate types or complexes of works is entrusted.

66. The general contractor eliminates at own expense (or provides elimination by subcontractor) the defects allowed through his fault (or because of subcontractor) in the performed works, found in warranty periods.

67. The decision of the contract organization is determining by any production question which arose in case of asset construction and carrying out the Party of Russian Taxpayers.

68. The parent adjustment organization provides accomplishment of amounts of the Party of Russian Taxpayers on the equipment according to the approved distribution of amounts between the attracted adjustment organizations, implementation of management in carrying out prestarting and starting transactions on the equipment, nodes and the block, participation in work of inspections.

69. The parent adjustment organization in addition to accomplishment of the amount of the Party of Russian Taxpayers performs:

1) distribution of amounts of adjustment works (in case of creation of the coordination plan);

2) coordination of actions of all members of the Party of Russian Taxpayers: development of engineering support of adjustment works, participation in development and approval of the combined schedule of construction, installation and adjustment works, development or approval of working and technical programs of the Party of Russian Taxpayers according to instructions of appendix 2 to this specifications and technical documentation, participation in forming of summary adjustment pouzlovy crews, including allocation from the list of pouzlovy foremen;

3) control of results of accomplishment of the Party of Russian Taxpayers by all participants and participation in work of inspections;

4) ensuring the round-the-clock watch of leading experts for rendering operational technical assistance during starting transactions on the equipment;

5) removal at consideration of the starting headquarters of the questions and offers concerning the organization and the course construction mounting and the Party of Russian Taxpayers;

6) generalization together with the organizations collaborators of results of the Party of Russian Taxpayers and on their basis – operational issue to the customer and the contract organization, project organizations and manufacturing plants of suggestions for improvement of technology, schemes, the modes and designs of the equipment and observation of their implementation;

7) generalization of operating experience of the similar equipment and issue to the customer (the contract organization) of offers for implementation;

8) development together with the customer of instructive technical documentation on operation of energy object, systems and nodes.

70. The parent adjustment organization together with the contract organization are responsible before the customer for terms and quality of accomplishment of the Party of Russian Taxpayers and input of the equipment in operation.

71. Instructions of the parent commissioning organization regarding technology and terms of the Party of Russian Taxpayers are observed by all organizations participating in launch of the equipment.

72. The main form of activities of the parent commissioning organization is the conclusion of the agreement of the single contract on accomplishment of all complex of the Party of Russian Taxpayers with involvement of other adjustment organizations on the terms of sub contracting.

73. In the absence of the parent commissioning organization of its function regarding distribution, control and coordination of works the customer or the general contractor in case of "turnkey" commissioning of the object carries out.

74. Accomplishment of the Party of Russian Taxpayers is made according to the amounts approved with the customer, the general contractor and the parent commissioning organization. Participation in step-by-step acceptance and individual testing of the equipment, and also in acceptance, starting, complex adjustment and testing of functional nodes and the block in general is performed according to requirements of this specifications and technical documentation.

75. Collaborators of the Party of Russian Taxpayers according to the coordination plan exercise control of installation and individual testing of the equipment as a part of crews:

1) is constituted by sheets of defects of the equipment, installation, the project and develop offers on their elimination;

2) exercise technical supervision of installation;

3) adjustment of the scheme of experimental control on the equipment determined by the protocol of job sharing;

4) as a part of nodal crews perform starting adjustment of functional nodes, conduct researches at stage of complex adjustment of functional nodes in the amount necessary for ensuring their working capacity and determination of parameters for setup of industrial control system, participate in work of inspections and complex working subcommittees.

76. Production of electric installation work and the Party of Russian Taxpayers of the equipment of energy objects is performed according to requirements of the Regulations for electrical installation of the Republic of Kazakhstan approved by the order of the Minister of Energy of the Republic of Kazakhstan of March 20, 2015 No. 230 (it is registered in the Register of state registration of regulatory legal acts No. 10851) and RD 34 RK 20/03.501/202.

77. The Party of Russian Taxpayers is allowed to make to persons not more young than 18 years which passed:

1) corresponding medical examination;

2) induction;

3) training in safety and labor protection;

4) examination with receipt of the corresponding group on electrical safety;

5) primary instructing;

6) training during 3-10 changes under observation of the experienced specialist. These persons get the admission to independent work.

78. Are responsible for safety and labor protection:

1) senior operator (division manager);

2) the head of the Party of Russian Taxpayers on object;

3) head of crew;

4) head of link;

5) serviceman.

79. Division manager:

1) is responsible for the organization of all work on safety and labor protection in the division;

2) is controlled by accomplishment by employees of division of requirements of this specifications and technical documentation and security guidelines and labor protection;

3) is responsible for accomplishment of general terms of safety, labor protection and production sanitation on objects;

4) is determined by need and amount of works;

5) appoints heads of the Party of Russian Taxpayers on objects (heads of crews);

6) sends assemblers and servicemen to the order of heads of the Party of Russian Taxpayers on objects;

7) is responsible for qualification of heads of the Party of Russian Taxpayers on objects and servicemen;

8) carries out primary instructing.

80. The head of the Party of Russian Taxpayers on object is their main organizer, is responsible for implementation of actions for safety and labor protection on object.

Head of the Party of Russian Taxpayers:

1) is received from the designated his face by accurate task for accomplishment of the Party of Russian Taxpayers, electric installation work (further – EMR) and instructing about features of the organization of safe works and labor protection;

2) is approved with the customer by regulations on Party of Russian Taxpayers production organization, according to standard document forms, drawn up under the organization and carrying out the Party of Russian Taxpayers, specified in appendix 14 to this specifications and technical documentation, and control its accomplishment;

3) is received by general instructing in safety and labor protection from the responsible customer representative on object;

4) is guided by regulations and system of admissions on object;

5) appoints heads and determines structures of crews;

6) is issued to crews by task (order) for production of EMR and Party of Russian Taxpayers;

7) before works instructs with heads of crews on safety and labor protection about features and conditions of safe works on object;

8) organizes safe work of all commissioning personnel on object at all stages and in case of all work types taking into account all requirements for safety and labor protection;

9) is organized by the combined production of the Party of Russian Taxpayers and EMR;

10) provides crews with individual protection equipment and other remedies;

11) is controlled by observance by commissioning personnel on subject of requirements of this specifications and technical documentation and security guidelines and labor protection.

81. The head of the Party of Russian Taxpayers on object is appointed from among the specialists having group on electrical safety not lower than IV.

82. The head of crew is the main organizer of work of servicemen on the site of work of the crew and the responsible person from the commissioning organization for observance of requirements for safety and labor protection, and also safe production of the Party of Russian Taxpayers and EMR on this site.

Head of crew:

1) is provided by accomplishment by the customer, mounting and other adjacent organizations of general terms of safety and labor protection on the site of work of the crew at all stages and in case of all types of the Party of Russian Taxpayers and EMR;

2) organizes safe work of members of the crew at all stages and in case of all types of EMR and Party of Russian Taxpayers;

3) is provided by completeness, operability of the individual protection equipment and remedies which are in collective use of crew;

4) exercises periodic control of observance by servicemen of requirements of this specifications and technical documentation and security guidelines and labor protection;

5) appoints heads of links and determines structure of links;

6) is issued to links by task (order) for production of the Party of Russian Taxpayers and EMR;

7) is performed by the admission of links to production of the Party of Russian Taxpayers and EMR.

The head of crew is appointed from among the specialists having group on electrical safety not lower than IV.

83. The head of link is the main contractor of the Party of Russian Taxpayers and the direct organizer of safe work of members of link on workplace.

Head of link:

1) is received by task from the head of crew;

2) is responsible for sufficiency of measures for safety and labor protection in the working area of link;

3) knows the scheme of electric utility service of the working area of link, the place from where tension, and switching devices by which this stress can be removed can be given;

4) when giving tension according to temporary schemes takes measures for prevention of inclusion of tension in chains outside the working area of link;

5) takes measures for exception of access for persons who do not have relations to EMR and Party of Russian Taxpayers to the working area of link;

6) is provided by accomplishment by all members of link of requirements for safety and labor protection;

7) is carried out by daily oral instructing of members of the link on workplace on safety and labor protection.

The head of link is appointed from among the specialists having group on electrical safety not lower than III for work on electroinstallations up to 1000 V and not lower than IV – over 1000 V.

84. The serviceman (the construction electrician-serviceman, the technician or the engineer on adjustment and testing of any category) is the main contractor of the Party of Russian Taxpayers and EMR.

85. Serviceman:

1) performs only those works which are determined in task to link and are charged to it by the head of link;

2) observes requirements of security guidelines and labor protection, and also the instructions received when instructing on workplace;

3) uses operational remedies and applies them to destination;

4) works at object in specialized clothes, carries protective helmet and other means of individual and collective protection.

86. Combination by one person of obligations of two persons from among the following is allowed:

1) the division manager is the head of the Party of Russian Taxpayers and EMR on object if other person is not designated;

2) the head of the Party of Russian Taxpayers and EMR can fulfill similar duties on several objects;

3) the head of the Party of Russian Taxpayers and EMR on object can be the head of one of crews;

4) the head of crew can be the head of one of links.

Section 3. Equipment of thermal power plants

1. Quotations for calculation of estimated cost of accomplishment of commissioning (The heat power equipment)

87. In this specifications and technical documentation the following structure of works is considered:

1) preparatory work – acquaintance with task; studying project, factory and specifications and technical documentation; creation and approval of the technical program and agreement; creation, approval and adjustment of the schedule of carrying out Party of Russian Taxpayers; check of compliance of the technology scheme and the main characteristics of the equipment to requirements of the legislation of the Republic of Kazakhstan in the field of power industry, to standards of manufacturing plants, Construction Norms and Regulations, labor protections, fire safety, safety in gas economy; development of offers and recommendations for elimination of the variations and defects found in the project documentation for the purpose of ensuring normal input of the equipment in operation; development and approval of programs and schemes of washing, purge, trial start-up, individual testing of the equipment and pipelines of installation (system); development and approval of technology schemes design assignments of temporary pipelines and devices for Party of Russian Taxpayers; creation of specifications on temporary elements and pipelines of schemes of washings, purges and individual testing; creation of the list and determination of consumption of the reagents, material and energy resources necessary for carrying out the Party of Russian Taxpayers, including complex approbation; accomplishment of testing calculations; determination of the mode of works providing testing of system; development of actions for safe engineering, labor protection and fire safety, necessary for production of the Party of Russian Taxpayers;

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.