THE RESOLUTION OF THE NATIONAL COMMISSION PERFORMING STATE REGULATION IN THE FIELD OF POWER AND UTILITIES OF UKRAINE

of June 30, 2015 No. 1972

About approval of the Procedure for forming of investing programs of licensees on transfer of electrical energy the high-level and interstate power networks and on production of heat and/or electrical energy on nuclear power plants, hydroelectric power stations and pumped storage power plants

(as amended on 27-06-2019)

According to item 4 of the Regulations on the National commission performing state regulation in the field of power and utilities, No. approved by the Presidential decree of Ukraine of September 10, 2014 715, the National commission performing state regulation in the field of power and utilities decides:

1. Approve the Procedure for forming of investing programs of licensees on transfer of electrical energy by the high-level and interstate power networks and on production of heat and/or electrical energy on nuclear power plants, hydroelectric power stations and pumped storage power plants which is applied.

2. On regulation of the relations in the field of power in accordance with the established procedure to provide to department submission of this resolution on state registration in the Ministry of Justice of Ukraine.

3. This resolution becomes effective from the date of its official publication.

Commission chairman

D. Wolf

 

Approved by the Resolution of the National commission performing state regulation in the field of power and utilities of Ukraine of June 30, 2015 No. 1972

Procedure for forming of investing programs of licensees on transfer of electrical energy the high-level and interstate power networks and on production of heat and/or electrical energy on nuclear power plants, hydroelectric power stations and pumped storage power plants

I. General provisions

1.1. This Procedure determines the procedure of giving, forming, consideration, approval and accomplishment of investing programs of licensees for the purpose of determination of justification of the capital investments and/or expenses planned by the licensee in structure of rates (prices) of transfer of electrical energy the high-level and interstate power networks or on production of heat and/or electrical energy on nuclear power plants (further - the NPP), hydroelectric power stations (further - hydroelectric power station) and pumped storage power plants (further - pumped storage power plant) on the principles of economic feasibility and target use of means by the licensee.

1.2. This Procedure extends to subjects of managing who obtained the license for implementation of economic activity (further - licensees) with:

transfer of electrical energy high-level and interstate power networks;

production of heat and/or electrical energy on the NPP;

production of electricity on hydroelectric power station and pumped storage power plant.

1.3. In this Procedure terms are used in the following values:

base period - the period of action of investing program preceding forecast period lasting, as a rule, calendar year;

the accounting period - the period of action of investing program for which the licensee reports on accomplishment of investing program (quarterly with the accruing result and following the results of year);

investing program - the plan of use of means for increase in level of reliability and profitability of work of fixed assets which contains complex of obligations of the licensee for accomplishment on development of the licensee, sources of its financing, the schedule of accomplishment and the explanatory note;

forecast period - the period of action of investing program during which the licensee plans accomplishment of investing program (as a rule, calendar year);

structure of rate - structure of reasonable costs of the licensee (operating expenses and expenses on profit) on implementation of the licensed activities, are grouped in economic elements and on the basis of which rates are calculated and affirm.

1.4. The licensee shall use the means determined as financing source of investing program, is exclusive on its accomplishment according to the schedule determined by investing program.

1.5. Consideration of question of approval of investing program is preceded by carrying out open discussion by the licensee on places according to Procedure for carrying out open discussion of drafts of decisions of the National commission performing state regulation in spheres of power and utilities, the approved resolution of NKREKP of June 30, 2017 No. 866.

1.6. The decision on approval of investing program or introduction of changes in it is accepted by NKREKP at its meeting in the form of open hearing by comprehensive and complete clarification of line items of all participants of open session after consideration and processing of NKREKP of investing program or the offered changes and the provided materials according to requirements of this Procedure.

By consideration of question of approval of investing program or introduction of changes in it representatives of the licensee and the central executive body which creates and provides realization of state policy in electrical power complex, and other concerned parties (in case of need) are invited to meeting of NKREKP in the form of open hearing.

The decision of NKREKP on approval of investing program or introduction of changes in it is published according to Regulations of the National commission performing state regulation in spheres of power and utilities, to No. 2133 approved by the resolution of NKREKP of December 6, 2016.

II. Requirements to investing programs

2.1. For the purpose of reasons for the planned expenses of the licensee directed to reconstruction, technical retrofitting and development of fixed assets, other assets of the licensee to NKREKP the investing program the licensee on transfer of electrical energy the high-level and interstate power networks in the form given in appendix 1 to this Procedure, the licensee on production of electrical energy on the NPP - in the form given in appendix 2 to this Procedure, and the licensee on production of electrical energy on hydroelectric power station and pumped storage power plant - in the form given in appendix 3 to this Procedure moves.

2.2. Financing sources of investing program are created by the licensee of such Articles:

depreciation charges;

profit on production investments, provided by structure of rates (prices);

the planned amount of receipts for overflows of reactive electrical energy;

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.