ORDER OF THE GOVERNMENT OF THE RUSSIAN FEDERATION

of August 6, 2015 No. 814

About approval of Rules of preparation, consideration and approval of plans and schemes of development of mining operations by types of minerals

According to article 24 of the Law of the Russian Federation "About subsoil" the Government of the Russian Federation decides:

1. Approve the enclosed Rules of preparation, consideration and approval of plans and schemes of development of mining operations by types of minerals.

2. The realization of this resolution is enabled within the number of employees of Federal Service for Environmental, Technological and Nuclear Supervision, and also budgetary appropriations provided to Service on management and management in the field of the established functions established by the Government of the limiting Russian Federation.

Russian Prime Minister

D. Medvedev

Approved by the Order of the Government of the Russian Federation of August 6, 2015 No. 814

Rules of preparation, consideration and approval of plans and schemes of development of mining operations by types of minerals

1. These rules establish procedure for preparation, consideration and approval of plans and schemes of development of mining operations by types of minerals.

2. Plans and schemes of development of mining operations are prepared by types of minerals (solid minerals, hydrocarbonic raw material, underground waters, popular minerals) and contain actions for fulfillment of requirements of the legislation of the Russian Federation on subsoil and legislations of the Russian Federation in the field of industrial safety on providing safe operation connected with use of natural resources and also data on losses of minerals.

3. Plans and schemes of development of mining operations determine the directions of development of mining operations, conditions, technical and technology solutions in case of operation of subjects to conducting mining operations, amounts of production and conversion of minerals.

4. Plans and schemes of development of mining operations are constituted concerning the following types of mining operations - overburden, preparatory, recultivation, surveying, works on mining and the works connected with primary conversion of mineral raw materials.

5. The development plan for mining operations is constituted for 1 year by all planned types of mining operations. The scheme of development of mining operations is constituted according to the decision of the subsoil user for the term which is not exceeding 5 years on one or several work types, stipulated in Item 4 these rules.

If the engineering design on development of mineral deposits provides working off of inventories of mineral deposits no more than 5 years in time, the scheme of development of mining operations is constituted for the entire period of mining.

6. Plans and schemes of development of mining operations are constituted on the basis of the engineering designs approved in accordance with the established procedure and other project documentation on performance of works connected with use of subsoil plots, conditions of licenses to use of subsoil, production sharing agreements and normative requirements in the field of subsurface use.

7. Preparation of plans and schemes of development of mining operations is performed by the subsoil user or the organization attracted by the subsoil user which have the license for production of surveying works.

8. The plan and the scheme of development of mining operations affirm the head of the organization - the subsoil user.

9. Plans and schemes of development of mining operations before their approval are subject to approval of Federal Service for Environmental, Technological and Nuclear Supervision (further - body of the state mountain supervision).

10. In case of change of conditions of the license to use subsoil and the conditions provided by the project documentation to plans and schemes of development of mining operations makes the changes connected with ensuring safe use of natural resources, observance by the subsoil user of requirements for technology of conducting the works connected with use of natural resources, to forecasting and the prevention of dangerous situations with the corresponding adjustment of technical and technology solutions, parameters and indicators of mountain developments. The specified changes are approved with body of the state mountain supervision according to the procedure, established by these rules, and affirm the head of the organization - the subsoil user prior to works.

11. Plans and schemes of development of mining operations consist of graphical part and the explanatory note with tabular materials.

12. Plans and schemes of development of mining operations are constituted for each site, right to use by which it is granted according to the license to use subsoil and on which according to the engineering design of mining of minerals the mining operations connected with use of natural resources are conducted (further - the site of subsurface use).

If the mineral deposit is divided into 2 and more sites of subsurface use or 2 and more mineral deposits are united in borders of one site of subsurface use, right to use to which belongs to one subsoil user, or the site of subsurface use (mineral deposit) is developed based on several project documents, creation of one plan and one scheme of development of mining operations with general graphical part and the explanatory note is allowed. At the same time tabular materials with indicators of parameters of mountain developments are constituted separately on each site of subsurface use or the field respectively.

13. Subsoil users represent the statement for approval of plans and schemes of development of mining operations to body of the state mountain supervision till September 1 of the current year. Consideration of plans and schemes of development of mining operations is performed during the period from September 20 to December 25 the year previous planned, according to the schedule approved by body of the state mountain supervision (further - the schedule). The subsoil users who submitted applications for consideration of plans and schemes of development of mining operations join in the schedule in alphabetical order. Schedules are published on the official sites of body of the state mountain supervision and its territorial authorities on the Internet.

14. Plans and schemes of development of mining operations go the subsoil user to body of the state mountain supervision in 15 days prior to the date of consideration of plans and schemes of development of mining operations appointed in graphics on paper and in electronic form.

In the cases connected with need of evaluating observance of conditions of safe subsurface use, difficult and (or) long examinations, consideration of plans and schemes of development of mining operations can be prolonged according to the decision of body of the state mountain supervision for the term of no more than 30 days from the date of established by the schedule.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.