ORDER OF THE MINISTER OF ENERGY OF THE REPUBLIC OF KAZAKHSTAN

of March 30, 2015 No. 245

About approval of Rules and conditions of power supply of the consumers having emergency reservation

According to Item 2 of article 21 of the Law of the Republic of Kazakhstan of July 9, 2004 "About power industry" PRIKAZYVAYU:

1. Approve the enclosed Rules and conditions of power supply of the consumers having emergency reservation.

2. To provide to department of power industry of the Department of Energy of the Republic of Kazakhstan in the procedure established by the legislation of the Republic of Kazakhstan:

1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;

2) the direction on official publication the copy of this order within ten calendar days after its state registration in the Ministry of Justice of the Republic of Kazakhstan in periodic printing editions and in information system of law of Ad_let;

3) placement of this order on official Internet resource of the Department of Energy of the Republic of Kazakhstan and on the intranet portal of state bodies;

4) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Department of legal service of the Department of Energy of the Republic of Kazakhstan of data on execution of the actions provided by subitems 2) and 3) of this Item.

3. To impose control of execution of this order on the supervising vice-Minister of Energy of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Minister of Energy of the Republic of Kazakhstan

B. School student

It is approved

Minister of Finance of the Republic of Kazakhstan

 

B. Sultanov

It is approved

Minister of national economy of the Republic of Kazakhstan

 

E.Dosayev

Approved by the Order of the Minister of Energy of the Republic of Kazakhstan of March 30, 2015 No. 245

Rules and conditions of power supply of the consumers having emergency reservation

1. General provisions

1. These rules and conditions of power supply of the consumers having emergency reservation (further - Rules) are developed according to Item 2 of article 21 of the Law of the Republic of Kazakhstan of July 9, 2004 "About power industry" (further - the Law) and determine procedure and conditions of power supply of the consumers having emergency reservation.

2. In these rules the following basic concepts are used:

1) objects of continuous power supply (further - ONE) - the objects of economic infrastructure of physical persons and legal entities owing to the technology reasons needing continuous power supply which shutdown can lead to death of people, to violation of work of critical infrastructure, catastrophic ecological, social or economic effects.

2) specific mode of work of power generation facilities - the forced regime introduced in case of large technology violations on power generation facilities.

Other concepts used in these rules are applied according to the legislation of the Republic of Kazakhstan in the field of power industry and state-owned property.

2. Procedure and conditions of power supply of consumers

Paragraph 1. The objects provided with emergency reservation

3. Join in the list of objects of continuous power supply for which the size of emergency armor is determined:

1) the objects ensuring safety of the state;

2) TV radio communications;

3) companies of water supply, sewerage and heat supply;

4) medical institutions;

5) the objects ensuring fire safety which content is provided by the budget;

6) objects of the metallurgical companies of continued production of titanium and magnesium by electrolysis method;

7) the objects of the aeronautical organization providing servicing of air traffic;

8) objects of poultry farms.

4. Condition for inclusion in the list of ONE is compliance of the scheme of external electric utility service of object on category of reliability of electric utility service according to the requirements established by the Regulations for electrical installation approved according to the subitem 19) of article 5 of the Law.

5. Objects are divided into ONE of republican and local value.

6. For each object included in the list by ONE which are power supplying and power transferring by the organizations together with the representative of ONE the statement of emergency armor according to the Instruction for creation of the act of the emergency and technology armor of power supply approved by the order of the Minister of Energy of the Republic of Kazakhstan of February 11, 2015 No. 75 (registered in the Register of state registration of regulatory legal acts No. 10510) is drawn up.

The act of emergency armor goes to the state body performing management in the field of power industry and local executive body. The act of emergency armor is appendix to the agreement on power supply and to the agreement on transfer of electrical energy.

7. The local executive body after receipt of acts of emergency armor determines the total electric power necessary for covering of emergency armor, respectively for each region.

8. Lists of ONE with indication of sizes of emergency armor for each ONE are transferred to the system operator.

Paragraph 2. Delivery of electrical energy for ONE

9. Delivery of electrical energy in the amount necessary for normal functioning of each ONE, is performed by the power supplying and power transferring organization on the basis of the bilateral agreement with ONE.

In case of the conclusion of the agreement:

1) ONE which is object of public institutions represent to the power supplying and power transferring organization the written confirmation of regional financial management about the means provided in the budget on expenses of the electrical energy this the organizations for consumption;

2) ONE which is object of physical persons or legal entities represent to the power supplying and power transferring organization the bank guarantee which is drawn up according to the procedure, established by the legislation of the Republic of Kazakhstan in the field of state regulation, control and supervision of the financial market and financial institutions.

The written confirmation of regional financial management and the bank guarantee are integral part of agreements on power supply and transfer of electrical energy.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.