of February 20, 2015 No. 109
About approval of the Standard agreement about purchase of service in maintenance of readiness of electric power of the generating installations which are again put into operation
According to the subitem 7) article 5 of the Law of the Republic of Kazakhstan of July 9, 2004 "About power industry" PRIKAZYVAYU:
1. Approve the enclosed Standard agreement about purchase of service in maintenance of readiness of electric power of the generating installations which are again put into operation.
2. To provide to department of power industry of the Department of Energy of the Republic of Kazakhstan in the procedure established by the legislation of the Republic of Kazakhstan:
1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;
2) the direction on official publication of its copy within ten calendar days after its state registration in the Ministry of Justice of the Republic of Kazakhstan in periodic printing editions and in information system of law of Ad_let;
3) placement of this order on official Internet resource of the Department of Energy of the Republic of Kazakhstan and on the intranet portal of state bodies;
4) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Department of legal service of the Department of Energy of the Republic of Kazakhstan of data on execution of the actions provided by subitems 2) and 3) of this Item.
3. To impose control of execution of this order on the supervising vice-Minister of Energy of the Republic of Kazakhstan.
4. This order becomes effective after ten calendar days after day of its first official publication.
Minister of Energy of the Republic of Kazakhstan
B. School student
Approved by the Order of the Minister of Energy of the Republic of Kazakhstan of February 20, 2015, No. 109
__________________________ "___" ________________ 20 __.
(place of agreement) (date of the conclusion)
_____________________________________________________________________
(the name of the power making organization)
the supplier providing service in maintenance of readiness of electric power, hereinafter referred to as, on behalf of
____________________________________________________________________,
(position, First name, middle initial, last name)
acting on the basis of the ________________________________________,
on the one hand, and __________________________________________________
____________________________________________________________________,
(name of the organization, certificate of state registration,
date and body of issue)
hereinafter referred to as the system operator, on behalf of
____________________________________________________________________,
(position, First name, middle initial, last name)
acting on the basis of the __________________________________, and also the order of authorized body from "___" _________ years
No. ________ (further - the Parties) by results of the tender for construction of the generating installations which are again put into operation in compliance
with the order of authorized body from "___" ________ years No. ____, signed this agreement (further - the Agreement) as follows:
1. In this Agreement the following concepts and determinations are used:
1) settlement period - the period of time equal to one calendar month from 00-00 o'clock the first day till 24-00 o'clock (Central European time) the last day of month for which calculation of service in maintenance of readiness of electric power is made;
2) national dispatch center of the system operator (further - NDTs SO) - the structural division of the system operator performing functions of the central supervisory control of the modes of production, transfer and consumption of electrical energy and capacity in single electric utility system of the Republic of Kazakhstan;
3) authorized body - the state body performing management in the field of power industry;
4) service in maintenance of readiness electric the moshchnostiusluga rendered by the power making organizations to the system operator on the maintenance of readiness of electric power of the generating installations certified in accordance with the established procedure to execution of loading.
Other concepts and determinations used in this Agreement are applied according to the legislation of the Republic of Kazakhstan in the field of power industry.
2. The supplier shall provide, and the system operator to accept and pay service in maintenance of readiness of electric power of the generating installations which are again put into operation (further - service) according to Item 9 of this Agreement.
3. Acquisition of service is performed by the system operator from the date of certification of the generating installation of the supplier put into operation.
4. The price, amount of service and the duration of the agreement are determined by authorized body following the results of the held tender for construction of the generating installations which are again put into operation according to the procedure, established according to the Law of the Republic of Kazakhstan of July 9, 2004 "About power industry" (further - the Law).
5. The system operator shall:
1) to perform the activities according to requirements of the legislation of the Republic of Kazakhstan in the field of power industry;
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions. This section provides answers to questions set by users.
The document ceased to be valid since January 1, 2018 according to Item 2 of the Order of the Minister of Energy of the Republic of Kazakhstan of December 3, 2015 No. 683