of February 20, 2015 No. 117
About approval of Rules and terms of determination of the next point of connection to power or thermal networks and connections of objects for use of renewable energy resources, objects for energy waste recycling
According to the subitem 368) of Item 15 of the Regulations on the Department of Energy of the Republic of Kazakhstan approved by the order of the Government of the Republic of Kazakhstan of September 19, 2014 No. 994, I ORDER:
1. Approve the enclosed Rules and terms of determination of the next point of connection to power or thermal networks and connections of objects for use of renewable energy resources, objects for energy waste recycling.
2. To provide to department on renewable energy resources of the Department of Energy of the Republic of Kazakhstan in the procedure for the Republic of Kazakhstan established by the legislation to provide:
1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;
2) the direction on official publication of this order within ten calendar days after its state registration in the Ministry of Justice of the Republic of Kazakhstan in periodic printing editions and in information system of law of Ad_let;
3) placement of this order on official Internet resource of the Department of Energy of the Republic of Kazakhstan and on the intranet portal of state bodies;
4) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Department of legal service of the Department of Energy of the Republic of Kazakhstan of data on execution of the actions provided by subitems 2) and 3) of this Item.
3. To impose control of execution of this order on the supervising vice-Minister of Energy of the Republic of Kazakhstan.
4. This order becomes effective after ten calendar days after the first official publication.
Minister
B. School student
Approved by the Order of the Minister of Energy of the Republic of Kazakhstan of February 20, 2015 No. 117
1. These rules and terms of determination of the next point of connection to power or thermal networks and connections of objects for use of renewable energy resources, objects for energy waste recycling (further – Rules) are developed according to the subitem 367) of Item 15 of the Regulations on the Department of Energy of the Republic of Kazakhstan approved by the order of the Government of the Republic of Kazakhstan of September 19, 2014 No. 994, and determine procedure for determination of the next point of connection to electric or thermal networks of connection of objects for use of renewable energy resources, objects for energy waste recycling.
2. In these rules the following concepts are used:
1) object for use of renewable energy resources – the technical devices intended for production of electrical energy with use of renewable energy resources, and constructions and the infrastructure technology necessary for operation of object for use of RES interconnected with them and which are on balance of the owner of object for use of renewable energy resources;
2) the system operator – the national company exercising centralized supervisory control, ensuring parallel work with power supply systems of other states, maintenance of balance in single electric utility system of the Republic of Kazakhstan, rendering system services and acquisition of support services at subjects of the wholesale market of electrical energy, and also maintenance and maintenance in operational readiness of national power grid and providing its development;
3) the closest point of connection to thermal networks - the closest point of insert of the pipeline from object for use of renewable energy resources in general system of heat supply of the settlement with the parameters corresponding to heat carrier parameters in general network of heat supply;
4) object for energy waste recycling - set of the technical devices and installations intended for energy waste recycling, and the constructions interconnected with them and the infrastructure technology necessary for energy waste recycling.
5) the customer (investor) - the person having intention and (or) who started project implementation of asset construction on use of renewable energy resources;
6) the closest point of connection to power networks - the closest place of physical connection of the power station of the power making organization using renewable energy resources or energy waste recycling, with power network of the power transferring organization corresponding on tension class.
3. Again constructed objects for energy waste recycling, and also objects for use of renewable energy resources and the reconstructed objects for use of renewable energy resources irrespective of the term of commissioning are connected to the closest point of power or thermal networks of the power transferring organization corresponding on class of tension or parameters of the heat carrier in general network of heat supply.
4. The application of the investor for determination of the next point of connection to power networks in any form is submitted to the power transferring organization and contains the following data:
1) name and type of installation;
2) preferable arrangement of the site;
3) admissible transfer of capacity of all installation (maximum in megawatt, with indication of Cos and (or) in megawatts (further - MW), megavoltamper;
4) the technology used by the offered power station;
5) date of expected commisioning;
6) nominal rates megavoltamper, MW, transitional reactive resistance on longitudinal axis, the relation of short circuit, constant of inertia of the power station with synchronous generators (engines);
7) nominal rate megavoltamper of the raising transformer and the reactive resistance of the direct sequence (in case of move / мin branches);
8) type and characteristics of the regulator of tension of the station.
5. The power transferring organization, within 5 (five) calendar days from the date of receipt of the request from the investor checks completeness of data, stipulated in Item 4 these rules.
In case of non-presentation by the investor of data, stipulated in Item 4 these rules in full, the power transferring organization within 5 (five) working days from the date of their receipt returns the request with indication of return reasons. The investor within 15 (fifteen) calendar days from the date of return of the request supplements the request with missing data and/or resolves comments of the power transferring organization for the purpose of reduction of the request in compliance with requirements of these rules.
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.