ORDER OF THE MINISTER OF ENERGY OF THE REPUBLIC OF KAZAKHSTAN

of January 13, 2015 No. 5

About approval of Rules of approval of the construction project of the new main pipeline

According to the subitem 8) article 6 of the Law of the Republic of Kazakhstan of June 22, 2012 "About the main pipeline", PRIKAZYVAYU:

1. Approve the enclosed Rules of approval of the construction project of the new main pipeline.

2. To provide to development department of the oil industry of the Department of Energy of the Republic of Kazakhstan in the procedure for the Republic of Kazakhstan established by the legislation:

1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;

2) within ten calendar days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan the direction on official publication in periodic printing editions and information system of law of Ad_let;

3) placement of this order on official Internet resource of the Department of Energy of the Republic of Kazakhstan and the intranet portal of state bodies;

4) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Department of legal service of the Department of Energy of the Republic of Kazakhstan of data on execution of the actions provided by subitems 2) and 3) of this Item.

3. To impose control of execution of this order on the supervising vice-Minister of Energy of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Minister of Energy of the Republic of Kazakhstan

B. School student

It is approved

Minister of national economy of the Republic of Kazakhstan

January 31, 2015

 

_________________ E.Dosayev

It is approved

Minister of investments and development of the Republic of Kazakhstan

January 29, 2015

 

_________________ A. Isekeshev

Approved by the Order of the Minister of Energy of the Republic of Kazakhstan of January 13, 2015 No. 5

Rules of approval of the construction project of the new main pipeline

1. General provisions

1. These rules of approval of the construction project of the new main pipeline (further - Rules) are developed according to the subitem 8) of article 6 of the Law of the Republic of Kazakhstan of June 22, 2012 "About the main pipeline" and determine procedure for approval of the construction project of the new main pipeline.

2. In these rules the following concepts are applied:

1) the feasibility statement (further - the feasibility study) on construction - the preproject documentation containing: basic data with descriptions of the purpose of investment, reasons for investment soundness, including: the expected economic, social, commercial effect of functioning of object, and also data on the key technical and technological parameters of construction object and calculations with determination of technical and economic indicators of object;

2) the construction project (the construction project) - the project (project and estimate) documentation containing space-planning, constructive, technology, engineering, nature protection, economic and other solutions, and also estimate calculations for the organization and maintaining construction, engineering training of the territory, improvement. Projects of preservation of construction of incomplete objects and post-utilization of the objects which developed the resource also belong to construction projects;

3) the main pipeline - the single production and technological complex consisting of the linear part and objects providing safe transportation of products, conforming to requirements of technical regulations and national standards;

4) authorized body - the central executive body performing management and cross-industry coordination in the field of the main pipeline.

2. Procedure for approval of the construction project

3. For review the construction project of the new main pipeline person having intention to perform construction of the main pipeline (further - the interested person) represents to the feasibility study authorized body.

4. The authorized body no later than thirty calendar days from the date of receipt of the feasibility study considers it and makes the decision on approval or on refusal in approval of the construction project of the new main pipeline.

5. In case of approval of the feasibility study for the construction project of the new main pipeline the authorized body considers it on compliance to the following requirements:

1) availability of resource base for the project according to the balance of production and distribution of oil of the Republic of Kazakhstan approved by authorized body;

2) the choice of the route and platforms of the main pipeline taking into account natural features of the territory, arrangement of settlements, transport ways and communications.

6. In case of discrepancy of the feasibility study for the construction project of the new main pipeline to requirements, stipulated in Item 5 these rules, the authorized body refuses approval of the feasibility study for the construction project of the new main pipeline. In case of refusal in approval of the feasibility study for the construction project of the new main pipeline the authorized body within three working days in writing notifies on it the applicant with indication of causes of failure.

In case of compliance of the feasibility study for the construction project of the new main pipeline to requirements, stipulated in Item 5 these rules, the authorized body within three working days approves the feasibility study.

7. After approval of the feasibility study for the construction project of the new main pipeline the interested person represents the construction project of the new main pipeline to authorized body.

8. The authorized body no later than thirty calendar days from the date of receipt of the construction project of the new main pipeline in writing approves or refuses approval of the construction project of the new main pipeline.

9. In case of lack of the construction project of the new main pipeline, and also the positive conclusion of state examination of the construction project of the new main pipeline issued by department of authorized body for architecture, town planning and construction approved with the feasibility study authorized body, the authorized body refuses approval of the construction project of the new main pipeline.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.