of December 31, 2014 No. 1418
About the card of industrialization
For the purpose of implementation of the Presidential decree of the Republic of Kazakhstan of August 1, 2014 "About approval of the State program of industrial and innovative development of the Republic of Kazakhstan for 2015 - 2019 and about entering of amendment into the Presidential decree of the Republic of Kazakhstan of March 19, 2010 No. 957 "About approval of the List of state programs" the Government of the Republic of Kazakhstan DECIDES: No. 874
1. Approve the enclosed card of industrialization.
2. "National welfare fund "Samruk-Kazyna" represent to responsible state bodies and joint-stock company to the Ministry of the industry and infrastructure development of the Republic of Kazakhstan summary information on the project progress on monthly basis till the 10th following reporting.
3. Quarterly till the 15th following reporting to provide to the ministry of the industry and infrastructure development of the Republic of Kazakhstan in the Government of the Republic of Kazakhstan information on monitoring of the project progress.
4. This resolution becomes effective since January 1, 2015.
Prime Minister of the Republic of Kazakhstan
K. Masimov
Approved by the Order of the Government of the Republic of Kazakhstan of December 31, 2014 No. 1418
№ |
Name of the project |
Responsible state body and/or national holding |
Region |
Applicant of the project |
Term realizatsii*/project status |
1 |
2 |
3 |
4 |
5 |
6 |
1. |
Increase in steel production up to 5 million tons per year |
MIIR |
Karaganda |
JSC Arselormittal TEMIIRTAU |
2010 – 2022 |
2. |
It is excluded |
||||
3. |
It is excluded |
||||
4. |
Construction of the rail and structural plant |
MIIR, akimat of the Aktyubinsk region |
Aktyubinsk region |
Aktyubinsk Rail and Structural Plant LLP |
2012 – 2015 |
5. |
Construction of automobile works of complete cycle and science and technology park on production of autocomponents in the city of Ust-Kamenogorsk |
MIIR |
East Kazakhstan region |
JSC AZIYA AVTO Kazakhstan |
2010 – 2022 |
6. |
Construction of the plant on production of mineral fertilizers |
MIIR |
Jambyl area |
EuroChem Fertilizer LLP |
2011 – 2021 |
7. |
Construction of the plant on production and processing of sheet glass capacity of 197,1 of one thousand tons per year in the city of Kyzylorda |
MIIR |
Kyzylorda area |
Orda Glass LLP |
2013 – 2021 |
8. |
It is excluded |
|
|||
9. |
Construction of the integrated gas-chemical complex (the first phase) |
ME, JSC NWF Samruk-Kazyna (in coordination) |
Atyrau |
Limited liability partnership "Kazakhstan |
2010 – 2022 |
10. |
Construction of the integrated gas-chemical complex (the second phase) |
ME, JSC NWF Samruk-Kazyna (in coordination) |
Atyrau |
KLPE LLP |
2010 – 2025 |
11. |
Production of motor fuel of the ecological class K5 |
ME |
West Kazakhstan region |
JSC Kondensat |
2012 – 2016 |
12. |
It is excluded |
||||
13. |
It is excluded |
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions. This section provides answers to questions set by users.
The document ceased to be valid since February 7, 2023 according to Item 1 of the Order of the Government of the Republic of Kazakhstan of February 7, 2023 No. 78