ORDER OF THE MINISTRY OF FUEL AND ENERGY OF UKRAINE

of June 12, 2014 No. 426

About approval of the Instruction on the safe organization and carrying out mass explosions of borehole charges on open mining operations

According to article 28 of the Law of Ukraine "About labor protection", "About the treatment of explosive materials of industrial function" and the Presidential decree of Ukraine of December 24, 2012 No. 726 "About some measures for optimization of system of the central executive bodies" I order to article 5 of the Law of Ukraine:

1. Approve the Instruction on the safe organization and carrying out mass explosions of borehole charges on open mining operations which is attached.

2. Recognize such which is not applied in the territory of Ukraine, the "Instruction on the organization and conducting mass explosions of borehole charges on open mining operations" approved by Committee of Ukraine on supervision of safe operation in the industry and to mountain supervision on March 16, 1992 (NPAOP 0.00-5.35-92).

3. To public service of mountain supervision and industrial safety of Ukraine in the procedure established by the legislation:

1) to provide submission of this order on state registration in the Ministry of Justice of Ukraine;

2) to enter the order in the State register of regulatory legal acts concerning labor protection.

4. This order becomes effective from the date of its official publication.

Minister

Yu.Prodan

 

Approved by the Order of the Ministry of Fuel and Energy of Ukraine of June 12, 2014 No. 426

The instruction on the safe organization and carrying out mass explosions of borehole charges on open mining operations

I. General provisions

1.1. This Instruction extends to all subjects of managing irrespective of their form of business and pattern of ownership (further - the companies) which activities are connected with carrying out mass explosions of borehole charges on open mining operations.

1.2. This Instruction determines requirements to the organization and carrying out mass explosions of borehole charges on open mining operations.

1.3. Requirements of this Instruction are obligatory for accomplishment by officials and workers of subjects of managing which are involved in preparation and carrying out mass explosions of borehole charges on open mining operations.

1.4. In this Instruction terms and concepts are used in the values determined by the Laws of Ukraine "About labor protection", "About the treatment of explosive materials of industrial function", by Safety rules in case of the treatment of the explosive materials of industrial function approved by the order of the Ministry of Fuel and Energy of Ukraine of June 12, 2013 No. 355, registered in the Ministry of Justice of Ukraine on July 5, 2013 No. 1127/23659 (further - NPAOP 0.00-1.66-13).

1.5. In this Instruction terms are used in the following values:

documentation - organizational and administrative (orders, orders) and organizational and technical (concord documents (if necessary), the schedule of carrying out mass explosions, the schedule of delivery of blocks (acts of readiness of blocks before loading and delivery on them explosive materials)) that regulates actions for safe preparation and carrying out mass explosion of borehole charges;

installation of explosive network - matching and connection of separate elements (final wires of electrodetonators, the detonating cord, elements of wave guides of not electric systems of initiation) in one explosive network according to certain scheme;

the passport of mass explosion - the technical document developed on the basis of the standard project of drilling-and-blasting works which contains complex of organizational and technical actions for safe preparation and carrying out specific mass explosion of borehole charges in typical conditions of production on open mining operations;

the project of conducting special drilling-and-blasting works - the technical document containing complex of organizational and technical actions for preparation and carrying out explosive works in conditions which are not typical.

1.6. The reducings used in this Instruction:

TORSO - the militarized mine-rescue service;

VM - explosive materials;

VV - explosives;

DSh - the detonating cord;

ED - electrodetonator;

To Loppa - the line of resistance on sole;

MV - mass explosion;

NSI - not electric systems of initiation.

II. General requirements

2.1. Preparation and carrying out MV are performed according to such project technical documentation:

the standard project of drilling-and-blasting works (further - the standard project);

project of drilling operations;

passport of GO;

passport of the block.

2.2. The standard project is developed with observance of requirements of the legislation based on the project of mining of minerals, results of experimental and industrial explosions, the latest researches and the accumulated know-how on conducting explosive works.

2.3. The standard project is approved, affirms, reviewed according to requirements of the current legislation.

2.4. The structure of the standard project, its structure, content and rules of registration of settlement and explanatory and graphical parts of the project shall conform to requirements of Item 6.3 of the Section V and NPAOP 0.00-1.66-13.

2.5. The project of drilling operations of the block is carried out based on the standard project of conducting explosive works taking into account specific geological and surveying data.

2.6. Shall be applied on the project of drilling operations of the block:

upper and lower brows of ledges;

contours of earlier blown up wells of the block (blocks) adjoining on the project block;

projections of the wells which are blown up on ledge is over the block, it is planned to explosion. At the same time planned wells shall be not closer than the 1st meter from projections of the wells which are blown up on ledge, being above;

arrangements of planned wells and their numbering;

surveying axes;

geological cuts.

The sequence number is assigned to each block.

2.7. Projects of drilling operations of blocks affirm the technical lead of the company, at the mining and processing companies - the technical lead of mountain division of the company.

2.8. The surveying service after approval of the project of drilling operations applies arrangements of wells on blocks.

2.9. The passport of MV consists after receipt of surveying data of condition of the indignant block(s) (depth, size to Loppa, places of their arrangement) and shall contain organizational and administrative documentation, graphical and settlement speak rapidly.

2.10. Are brought in settlement part of the passport of MV:

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.