Document from CIS Legislation database © 2003-2021 SojuzPravoInform LLC

ORDER OF THE GOVERNMENT OF THE RUSSIAN FEDERATION

of June 30, 2014 No. 602

About features of provision of specifications of connection (technology accession) of power receiving devices of consumers of electrical energy to objects of electric grid economy and capital construction projects to networks warm, gazo-, water supply and water disposal, and also determination of connection fee (technology accession) of the specified devices and objects in the territory of the innovative center "Skolkovo"

(as amended of the Order of the Government of the Russian Federation of 23.01.2016 No. 34)

According to part 19 of article 15 of the Federal Law "About the innovative Government of the Russian Federation center "Skolkovo" decides:

1. Approve the enclosed Regulations on features of provision of specifications of connection (technology accession) of power receiving devices of consumers of electrical energy to objects of electric grid economy and capital construction projects to networks warm, gazo-, water supply and water disposal in the territory of the innovative center "Skolkovo", and also about features of determination of payment for technology connection of power receiving devices of consumers of electrical energy to objects of electric grid economy.

2. Determine that:

the connection fee (technology accession) of capital construction projects to networks warm, gazo-, water supply and water disposal in the territory of the innovative center "Skolkovo" is not levied;

features of provision of specifications of connection (technology accession) of power receiving devices of consumers of electrical energy to objects of electric grid economy and capital construction projects to networks warm, gazo-, water supply and water disposal in the territory of the innovative center "Skolkovo", established by the Provision approved by this resolution extend to the connection specifications (technology accession) of the specified devices and objects in the territory of the innovative center "Skolkovo" provided before entry into force of this resolution.

Russian Prime Minister

D. Medvedev

 

Approved by the Order of the Government of the Russian Federation of June 30, 2014 No. 602

Regulations on features of provision of specifications of connection (technology accession) of power receiving devices of consumers of electrical energy to objects of electric grid economy and capital construction projects to networks warm, gazo-, water supply and water disposal in the territory of the innovative center "Skolkovo", and also about features of determination of payment for technology connection of power receiving devices of consumers of electrical energy to objects of electric grid economy

1. This Provision establishes features of provision of specifications of connection (technology accession) of power receiving devices of consumers of electrical energy to objects of electric grid economy and capital construction projects to networks warm, gazo-, water supply and water disposal in the territory of the innovative center "Skolkovo" (further - the innovative center) if provision of specifications on connection (technology accession) to networks of engineering facilities according to the procedure, stipulated in Clause 48 Town-planning codes of the Russian Federation, in connection with their simultaneous designing is impossible, and also features of determination of payment for technology connection of power receiving devices of consumers of electrical energy to objects of electric grid economy.

2. The concepts used in this Provision mean the following:

"object" - the power receiving device of the consumer of electrical energy or the capital construction project which is subject to construction (reconstruction) in the territory of the innovative center;

"group of objects" - set of the buildings, structures and constructions which are part of complex object, or set of the objects connected to networks of engineering facilities in single point (single points) of connection;

"preliminary specifications" - the specifications provided by the customer or the builder of the facility for production of resource, the customer or the builder of networks of engineering facilities or managing company to the customer or the builder of object (group of objects) if provision of specifications on connection (technology accession) to networks of engineering facilities according to the procedure, stipulated in Clause 48 Town-planning codes of the Russian Federation, in connection with their simultaneous designing it is impossible;

"resources" - cold and hot water, network gas, and also the electrical and heat energy used for provision of services on electro-warm, gazo-, to water supply and water disposal;

"networks of engineering facilities" - set of property objects of electric grid economy and networks warm, gazo-, the water supply and water disposal which are directly used in the course of electro-warm, gazo-, water supply and water disposal;

"connection of object to networks of engineering facilities" - the process giving the chance of implementation of connection of the under construction (reconstructed) objects to networks of engineering facilities and also to the equipment on production of resources;

"connection point" - junction of networks of engineering facilities with the devices and constructions necessary for connection (technology accession) of the under construction (reconstructed) object to objects of electric grid economy and networks warm, gazo-, water supply and water disposal;

"managing company" - the Russian legal entity on who according to the procedure, established by the President of the Russian Federation, project implementation of creation and ensuring functioning of the innovative center "Skolkovo" is assigned;

"the preliminary size of maximum demand (capacity)" - the size of the planned maximum demand (capacity) of object;

"the facility for production of resource" - set of the property objects which are directly used for production of electrical and heat energy, implementation of gas supply, production of cold and hot water, and also sewage treatment.

3. In the development plan for a land plot approved by managing company, information on connection specifications (technology accession) of object (group of objects) to networks of engineering facilities in connection with their simultaneous designing shall contain specifying on preliminary specifications.

4. The customer or the builder of object (group of objects) if provision of specifications on connection (technology accession) of object (group of objects) to networks of engineering facilities according to the procedure, stipulated in Clause 48 Town-planning codes of the Russian Federation, in connection with their simultaneous designing is impossible, provides to person performing architectural and construction designing of object (group of objects), preliminary specifications.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.