ORDER OF THE GOVERNMENT OF THE REPUBLIC OF KAZAKHSTAN

of April 29, 2014 No. 419

About approval of the rates which are not exceeding the level of selling price established in approved and approved with authorized or local executive body of the feasibility statement on the construction project of object for use of renewable energy resources, and terms of its action according to the feasibility statement for the power making organizations using renewable energy resources

(In edition of the Order of the Government of the Republic of Kazakhstan of 19.02.2015 No. 79)

According to Item 5 of article 2 of the Law of the Republic of Kazakhstan of July 4, 2013 "About modification and amendments in some legal acts of the Republic of Kazakhstan concerning support of use of renewable energy resources" the Government of the Republic of Kazakhstan DECIDES:

1. Approve the enclosed rates which are not exceeding the level of selling price established in the feasibility statement on the construction project of object for use of renewable energy resources approved and approved with authorized or local executive body, and terms of its action according to the feasibility statement for the power making organizations using renewable energy resources.

2. This resolution becomes effective from the date of its first official publication.

Prime Minister of the Republic of Kazakhstan

K. Masimov

Approved by the Order of the Government of the Republic of Kazakhstan of April 29, 2014 No. 419

The rates which are not exceeding the level of selling price, established in the feasibility statement on the construction project of object for use of renewable energy resources approved and approved with authorized or local executive body, and terms of its action according to the feasibility statement for the power making organizations using renewable energy resources

Name of the objects/organizations

Size of rate, tenge/kWh (excluding VAT)

End date of action of rate

Annual indexation of rate, %

1. Sarkandsky hydroelectric power station of Melissa Razbekova on the river Sarkand, Almaty region (Firm Tamerlan limited liability partnership)

11,80

22.07.2021.

4

2. Antonovsky hydroelectric power station on the river Lepsy, Almaty region (Kaynar-AKB limited liability partnership)

15,05

01.12.2023.

-

3. Uspenovsky hydroelectric power station on the river Horta tentek, Almaty region (Kaynar-AKB limited liability partnership)

15,11

25.11.2021.

-

4. It is excluded according to the Order of the Government of the Republic of Kazakhstan of 19.02.2015 No. 79

 

 

 

 

 

5. Hydroelectric power station on the river Karakystak around T. Ryskulov, Jambyl area (Energostroyproyekt limited liability partnership)

12,5

16.06.2020.

7

6. SES near the settlement of Flocks, Jambyl area (Kazekovatt limited liability partnership)

20,89

28.12.2024.

-


Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 38000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.