ORDER OF THE GOVERNMENT OF THE RUSSIAN FEDERATION

of May 8, 2014 No. 421

About approval of Rules of decision making about preparation and realization of budget investments in objects of state-owned property of the Russian Federation from the budget of Social Insurance Fund of the Russian Federation

(as amended on 07-09-2022)

According to Article 79 of the Budget code of the Russian Federation the Government of the Russian Federation decides:

Approve the enclosed Rules of decision making about preparation and realization of budget investments in objects of state-owned property of the Russian Federation from the budget of Social Insurance Fund of the Russian Federation.

Russian Prime Minister 

D. Medvedev

 

Approved by the Order of the Government of the Russian Federation of May 8, 2014 No. 421

Rules of decision making about preparation and realization of budget investments in objects of state-owned property of the Russian Federation from the budget of Social Insurance Fund of the Russian Federation

1. These rules establish procedure for decision making about preparation and realization of budget investments in the form of capital investments in capital construction projects of state-owned property of the Russian Federation and (or) in acquisition of real estate units in state-owned property of the Russian Federation (further respectively - capital construction projects, real estate units) by budget funds of Social Insurance Fund of the Russian Federation (further respectively - Fund, the decision).

1(1). When implementing capital investments in capital construction projects or real estate units in course of execution of the budget of Fund implementation of budget investments in capital construction projects or real estate units on which the decision on provision of subsidy according to Article 78.2 of the Budget code of the Russian Federation is made is not allowed.

2. The draft decision is prepared by governing body of Fund concerning capital construction project of estimated or expected (extreme) cost or the real estate unit of the acquisition value (calculated in the prices of the corresponding years) in the amount of:

a) 3 billion rubles and more - in the form of the legal act of the Government of the Russian Federation;

b) less than 3 billion rubles for all cases - in the form of the legal act of governing body of Fund.

3. Selection of capital construction projects and real estate units is made by governing body of Fund taking into account:

a) priorities and the purposes of development of Fund for the medium-term and long-term periods, requirements of Fund for capital construction projects and real estate units;

b) orders and instructions of the President of the Russian Federation and orders of the Government of the Russian Federation;

c) results carried out in the evaluation procedure of efficiency of use of the budget funds of Fund allocated for capital investments determined by governing body of Fund;

d) availability of the urgent approved project documentation on the date of preparation of the draft decision. In case of lack of the specified project documentation on the date of preparation of the draft decision, but in the presence of positive efficiency evaluation of use of the budget funds of Fund allocated for capital investments the draft decision joins only expenses on preparation of the project documentation and carrying out the engineering researches which are carried out for preparation of such project documentation, carrying out audit of the project documentation, conducting state examination of the project documentation and results of engineering researches and also on conducting check of reliability of determination of estimated cost of capital construction projects. The project documentation is considered urgent in the presence of the positive conclusion of state examination of the project documentation and results of engineering researches including check of reliability of determination of estimated cost of construction of facilities of capital construction (further - the positive conclusion of state examination) from the date of which receipt there passed no more than 24 months, and in case of approval of the project documentation by the customer. If from the date of receipt of the positive conclusion of state examination there passed more than 24 months, relevance of the project documentation is confirmed by the legal act of Fund. Provisions of this subitem are not applied in case of selection of capital construction projects concerning which the conclusion of contracts which subject is at the same time performance of works on designing and construction of facilities of capital construction is planned.

4. The draft decision can include several capital construction projects and (or) real estate units.

5. The draft decision shall contain the following information:

a) the name of capital construction project according to the project documentation (according to the passport of the investment project concerning capital construction project in the form approved by Fund, in case of absence approved in the procedure for the project documentation established by the legislation of the Russian Federation on the date of preparation of the draft decision) or the name of the real estate unit according to the passport of the investment project concerning capital construction project (further - the investment project);

b) the direction of investment (construction, reconstruction, including with restoration elements, modernization, acquisition, project and prospecting works);

c) name of the main manager of budgetary funds and state customer;

d) name of the builder and customer;

e) capacity (capacity surplus) of capital construction project (real estate unit);

e) the term of commissioning of capital construction project (in the presence of the urgent approved project documentation on the date of preparation of the draft decision or if on capital construction project the conclusion of the contract which subject is at the same time performance of works on designing and asset construction of capital construction is planned) either acquisitions of the real estate unit or deadline of development of the project documentation and carrying out the engineering researches which are carried out for preparation of the project documentation (in the absence of the urgent approved project documentation on the date of preparation of the draft decision);

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.