RESOLUTION OF COUNCIL OF MINISTERS OF THE REPUBLIC OF BELARUS

of August 9, 2013 No. 704

About approval of the Regulations on procedure for financing of inspectorates of Inspection department and supervision of construction of the State committee on standardization

(The last edition from 25-09-2017)

In pursuance of Item 3 of the Presidential decree of the Republic of Belarus of August 1, 2013 "About some questions of bodies of the state construction supervision" the Council of Ministers of the Republic of Belarus DECIDES: No. 336

1. Approve Regulations on procedure for financing of inspectorates of Inspection department and supervision of construction of the State committee on standardization it (is applied).

2. To provide to the Ministry of Architecture, the State committee on standardization reduction of regulatory legal acts in compliance with this resolution and to take other measures for its realization.

3. This resolution becomes effective after its official publication.

Prime Minister of the Republic of Belarus

M. Myasnikovich

 

Approved by the Resolution of Council of Ministers of the Republic of Belarus of August 9, 2013 No. 704

Regulations on procedure for financing of inspectorates of Inspection department and supervision of construction of the State committee on standardization

1. This Provision determines procedure for financing of inspectorates of Inspection department and supervision of construction by areas and Minsk and specialized inspection of Inspection department and supervision of construction of the State committee on standardization (further - inspections of the Gosstroynadzor) due to the target assignments made by customers, builders - legal entities and individual entrepreneurs (further - customers, builders) from the cost of installation and construction works (further - SMR) on construction objects, reconstruction, restoration, improvements, capital repairs (further - construction), including procedure for transfer and the amount of the specified target assignments.

2. The target assignments made by customers, builders from the cost of SMR on construction objects on financing of inspectorates of the Gosstroynadzor (further – target assignments), are provided in summary estimate calculation of construction cost of object in the amount of 0, of percent from the cost of SMR for the objects financed from republican and (or) local budgets, including the state trust budget funds, state non-budgetary funds, and objects of the Chinese-Belarusian industrial park "Great Stone", and for the objects financed from other sources – in the amount of percent 0,28.

If financing of asset construction (except for objects of the Chinese-Belarusian industrial park "Great Stone") is performed at the expense of different sources, the amount of target assignments is determined in proportion to the extent of appropriate source of financing of SMR.

3. Transfer of target assignments is made by customers, builders on the settlement account of the relevant inspectorate of the Gosstroynadzor in the amount of, determined by summary estimate calculation of construction cost of object in current prices for date of the appeal to inspectorate of the Gosstroynadzor for registration of objects and receipt of permissions to production of SMR, in the following procedure:

on objects with project duration of construction up to 12 months the advance payment in the amount of 20 percent from all estimated amount of target assignments is inclusive transferred;

on objects with project duration of construction over 12 months the advance payment in the amount of 10 percent from all estimated amount of target assignments is transferred.

Other part of means on the objects specified in paragraphs second and third to part one of this Item is listed quarterly proceeding from actual cost of the executed amounts of SMR taking into account earlier made advance and quarter assignments.

Final transfer of target assignments is made to the appeal of the customer, the builder to inspectorate of the Gosstroynadzor behind issue of the conclusion about compliance of the object accepted in operation, the project documentation, safety requirements and operational reliability (further – the conclusion) proceeding from the cost of SMR in current prices for date of implementation of final transfer taking into account earlier made advance and quarter assignments, with creation of calculation of target assignments for construction object in form according to appendix in duplicate (one – for the customer, the builder, the second – for inspection of the Gosstroynadzor).

Full text available with active License only!

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 38000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.