of October 1, 2013 No. 1038
About approval of Rules of realization and financing of works on construction, reconstruction, repair, content, diagnostics, certification and tool inspection of highways public of the international and republican value
According to subitem 8-1) of article 11 of the Law of the Republic of Kazakhstan of July 17, 2001 "About highways" the Government of the Republic of Kazakhstan DECIDES:
1. Approve the enclosed Rules of realization and financing of works on construction, reconstruction, repair, content, diagnostics, certification and tool inspection of highways public of the international and republican value (further - Rules).
2. This resolution becomes effective after ten calendar days from the date of the first official publication, except for Item 3 of Rules which becomes effective since July 1, 2014.
Prime Minister of the Republic of Kazakhstan
S. Akhmetov
Approved by the Order of the Government of the Republic of Kazakhstan of October 1, 2013 No. 1038
1. These rules of realization and financing of works on construction, reconstruction, repair, content, diagnostics, certification and tool inspection of highways public of the international and republican value (further - Rules) are developed according to subitem 8-1) of article 11 of the Law of the Republic of Kazakhstan of July 17, 2001 "About highways" and determine procedure for realization and financing of works on construction, reconstruction, repair, content, diagnostics, certification and tool inspection of highways public of the international and republican value by the National operator by management of highways.
2. Financing of works on construction, reconstruction, repair, content, diagnostics, certification and tool inspection of highways public of the international and republican value is performed at the expense of the means provided in the republican budget for the corresponding year and borrowed funds.
3. Financing of works on running repair and content of paid highways (sites) public of the international and republican value is performed at the expense of the means received from collection of fare.
4. In these rules the following concepts are used:
1) customer - The national operator on management of highways;
2) the schedule of mobilization of the main machinery and equipment - the document constituted by months, included in the works agreement after signing, and in subsequent being integral part of the agreement which contains information on terms and obligations of contract organization on providing the project with the machinery and equipment necessary for agreement performance;
3) the general works schedule - the document constituted by months, included in the works agreement after signing, and in subsequent being integral part of the works agreement which contains summarized information on terms and obligations of contract organization on execution of specific scopes of work on the project, in physical and monetary value;
4) the annual works schedule - the document constituted on the basis of the general works schedule which contains the detailed information about terms and obligations of contract organization on execution of scopes of work on the project in the corresponding year;
5) diagnostics of highways - the events held for identification of the reasons and forecasting of possible violations of transport and operational condition of highways on the basis of detailed tool inspections with assessment of possibility of further operation and development of strategy of road repair work;
6) certification of highways - forming of the highways this about availability, their extent, technical condition, including structural elements, engineering constructions and the equipment, linear buildings and constructions;
7) tool inspection of highways - actions for determination of transport and operational condition of highways;
8) the table of corrective data - the table where the adjusted and not adjusted cost elements of materials, the equipment and the salary in form, according to appendix to these rules are specified;
9) the certificate of intermediate payment - the document confirming performance of works within the works agreement during the certain period of time with indication of cost;
10) basic date - the date prior to 49 calendar days, before date of opening of competitive price offers;
11) the project - the projects directed to construction, reconstruction and major repair of highways public of the international and republican value.
5. The customer enables the realization of construction, reconstruction and major repair of highways public of the international and republican value by involvement in accordance with the established procedure of contract organization, and also the expert or the organization rendering engineering services" according to the legislation of the Republic of Kazakhstan on architectural, town-planning and construction activities.
6. The works agreement, and also the contract for rendering engineering services consist within 28 calendar days after decision making about determination of contract organization.
At the same time when carrying out tender" the cost of contract works on the projects realized over 18 months is determined by determination of contract organization without application of the planned conversion factor determined on the basis of the monthly settlement indicator established by the Law of the Republic of Kazakhstan on the republican budget for the corresponding year.
7. The schedule of mobilization of the main machinery and equipment is constituted taking into account condition that the contract organization within three months from works start date completes mobilization of the main machinery and equipment.
The general working schedule is constituted for the entire period of performance of works. Works start date within the project date of submission of the notification the expert or the organization rendering engineering services, contract organization about the beginning of works is.
At the same time the notification on the beginning of works is issued after approach of all listed facts;
1) receipts of advance payment by contract organization (if it is provided by the works agreement);
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions. This section provides answers to questions set by users.
The document ceased to be valid since April 25, 2017 according to Item 1 of the Order of the Government of the Republic of Kazakhstan of April 17, 2017 No. 203