ORDER OF THE GOVERNMENT OF THE REPUBLIC OF KAZAKHSTAN

of December 4, 2012 No. 1530

About some questions of licensing of activities for the organization of construction of residential buildings due to fund raising of shareholders and modification and amendments in some decisions of the Government of the Republic of Kazakhstan

(as amended on 23-12-2015)

The government of the Republic of Kazakhstan DECIDES:

1. Approve the enclosed qualification requirements and the list of the documents confirming compliance to them for implementation of activities for the organization of construction of residential buildings due to fund raising of shareholders.

2. Determine the licensor by implementation of activities for the organization of construction of residential buildings due to fund raising of shareholders the Agency of the Republic of Kazakhstan for construction and housing and communal services.

3. Ceased to be valid according to the Order of the Government of the Republic of Kazakhstan of 23.12.2015 No. 1034

4. Recognize invalid:

2) the order of the Government of the Republic of Kazakhstan of January 25, 2012 No. 164 "About modification of the order of the Government of the Republic of Kazakhstan of June 17, 2010 No. 607 "About approval of Rules of licensing and qualification requirements to activities for the organization of construction of residential buildings due to fund raising of shareholders"" (SAPP of the Republic of Kazakhstan, 2012, No. 29, the Art. 395).

5. This resolution becomes effective after twenty one calendar days after the first official publication.

Prime Minister of the Republic of Kazakhstan

S. Akhmetov

Approved by the Order of the Government of the Republic of Kazakhstan of December 4, 2012 No. 1530

Qualification requirements and the list of the documents confirming compliance to them for implementation of activities for the organization of construction of residential buildings due to fund raising of shareholders

No. of payment order

Qualification requirements

Documents

Note

1

2

3

4

1

First stage

1)

availability of the parcel of land belonging to the project company on the property right or on the land use right

the copy of the title document on the parcel of land

 

2)

availability of project (project and estimate) documentation at stage of zero cycle of construction with positive experimental testimony

copy of experimental testimony

 

3)

agreement availability with agent bank

copy of the agreement

 

4)

availability of own disposable capital for construction of the residential building in the amount of at least fifteen percent from construction cost of the residential building or in the amount of at least equivalent to construction cost of zero cycle

the copy of the reference from bank

 

5)

experience of construction of residential buildings at the founder having more than fifty percent of the authorized capital in authorized capital of the project company including as the customer, at least three years

notarially attested copies of signed acts of commissioning, works agreements

 

6)

experience of commissioning in the procedure established by the legislation of the Republic of Kazakhstan at least hundred apartments at the founder having more than fifty percent of the authorized capital in authorized capital of the project company

notarially attested copies of signed acts of commissioning

 

7)

availability at the founder having more than fifty percent of the authorized capital in authorized capital of the project company of equity in the amount of at least hundred thousand monthly settlement indicators

notarially attested copy of the reference from bank

 

2

Second stage

1)

availability of project (project and estimate) documentation of construction object with positive experimental testimony

copy of experimental testimony

 

2)

completion of zero cycle of building of the residential building

copy of the act of intermediate acceptance

 

3)

availability of deposits of shareholders in the amount of at least fifteen percent from construction cost of the residential building in agent bank brought according to agreements on equity in housing construction

the copy of the reference from bank

 

4)

equity availability for completion of construction in full or equity in the amount of at least twenty five percent from construction cost of the residential building and the agreement with the investor on provision of the investments sufficient for completion of construction

the copy of the reference from bank

 

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.