ORDER OF THE GOVERNMENT OF THE REPUBLIC OF KAZAKHSTAN

of December 4, 2012 No. 1542

About approval of Service regulations of trunk oil pipelines

According to the subitem 4) of article 5 of the Law of the Republic of Kazakhstan of June 22, 2012 "About the main pipeline" the Government of the Republic of Kazakhstan DECIDES:

1. Approve the enclosed Service regulations of trunk oil pipelines.

2. This resolution becomes effective after ten calendar days after the first official publication.

 

Prime Minister of the Republic of Kazakhstan

S. Akhmetov

Approved by the order of the Government of the Republic of Kazakhstan of December 4, 2012 No. 1542

Service regulations of trunk oil pipelines

1. General provisions

1. These rules of operation of trunk oil pipelines are developed according to the Law of the Republic of Kazakhstan on June 22, 2012 "About the main pipeline" and establish method of operation of trunk oil pipelines owners of the trunk oil pipelines and their objects operating, being on preservation and liquidated, and also the operators who are not owners, the physical persons and legal entities which are carrying out works on objects of trunk oil pipelines.

2. In these rules it is used the following basic concepts:

1) accident - destruction of the buildings, constructions and (or) engineering devices applied on hazardous production facility, uncontrollable explosion and (or) emission of dangerous substances;

2) the automated system - the system consisting of personnel and complex of the automation equipment of its activities, realizing information technology of accomplishment of the established functions of control and management;

3) running repair (equipment) - the repair which is carried out for providing or maintenance of the equipment and constructions, consisting in replacement and (or) recovery of separate parts;

4) division - oil transportation administration; central base of production servicing; head oil pumping station; oil pumping station; fixed emergency and recovery mark; emergency and recovery Item; setup laboratory and other services necessary for ensuring oil transportation and safe operation of trunk oil pipelines;

5) conference circuit (channel) - the selective and group loudspeaker communication provided to the operating-technical personnel organizing oil transportation;

6) supervisory control - centralized operation by the technological modes of operation of trunk oil pipeline for oil transportation;

7) repair - complex of actions (transactions) for recovery of operability or operability of complete or partial operation life of trunk oil pipeline line part and (or) its objects;

8) repair (equipment) - complex of transactions on recovery of operability, working capacity, service life and constructions of trunk oil pipeline;

9) major repair (equipment) - the repair which is carried out for recovery of operability and service life and constructions, complete or close to complete recovery, with replacement or recovery of any its parts including basic;

10) in-line inspection - the complex of works providing the defect information of the oil pipeline with use of intrapipe diagnostic shells;

11) intrapipe diagnostic shell (defectoscope) - the device moved in pipe with flow of the repumped product, supplied with control facilities and data loggings about defects of wall of the oil pipeline and welds;

12) the operator - the owners of trunk oil pipeline or the legal entity owning trunk oil pipeline on other legal cause, performing oil transportation on trunk oil pipeline and (or) its operation or the organization authorized by them rendering operator services;

13) production and technological communication - the communication provided on departmental communication network for management of intra productive activity and engineering procedures in case of operation of trunk oil pipelines;

14) the reservoir park - complex of the interconnected reservoirs for accomplishment of technological transactions of acceptance, storage and transfer of oil;

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.