ORDER OF THE GOVERNMENT OF THE RUSSIAN FEDERATION

of September 30, 2011 No. 802

About approval of Rules of carrying out preservation of capital construction project

(as amended of the Order of the Government of the Russian Federation of 14.04.2022 No. 655)

According to part 9 of article 52 of the Town-planning code of the Russian Federation the Government of the Russian Federation decides:

Approve the enclosed Rules of carrying out preservation of capital construction project.

Russian Prime Minister

V. Putin

Approved by the Order of the Government of the Russian Federation of September 30, 2011 No. 802

Rules of carrying out preservation of capital construction project

I. General provisions

1. These rules establish procedure for preservation of capital construction project (further - object), and also features of decision making about preservation of capital construction project of state-owned property of the Russian Federation (further - object of state-owned property).

2. The decision on preservation of object is made in case of the termination of its construction (reconstruction) or in case of need suspensions of construction (reconstruction) of object for the term of more than 6 months with perspective of its renewal in the future.

3. In the cases specified in Item 2 of these rules, the builder (customer) provides reduction of object and the territory used for its construction (further - construction site), in the condition providing durability, stability and safety of designs, the equipment and materials, and also safety of object and construction site for the population and the environment.

4. The decision on preservation of object (except for object of state-owned property) and about source of funds for payment of the expenses connected with preservation of object is accepted by the builder (customer).

5. In the decision on preservation of object shall be determined:

a) the list of works on preservation of object created taking into account requirements of Item 9 of these rules;

b) persons responsible for safety and safety of object, including designs, equipment, materials and construction site (official or organization);

c) terms of development of the technical documentation necessary for work on preservation of object (further - technical documentation), and also work terms on its preservation;

d) the size of funds for work on preservation of object determined based on the act prepared by person performing construction (reconstruction) of object (further - the contractor), and approved as the builder (customer).

6. In these rules technical documentation is understood as set of the documents developed by the project organization for the contract with the builder (customer), including the graphical, settlement and text materials necessary for the organization and work on preservation of object.

7. Based on the made decision on preservation of object the builder (customer) together with the contractor carries out inventory count of the performed works on construction (reconstruction) of object with the purpose to fix actual state of object, availability of the project documentation, designs, materials and the equipment. At the same time:

a) schemes and drawings with the description of condition of object and specifying of amounts of completed work are carried out;

b) sheets in which data are specified are constituted:

about the designs, the equipment and materials applied (mounted) on object including about the designs, the equipment and materials which are not used on object and subjects to storage;

about availability of estimate documentation;

about availability of executive documentation (including magazines of work, including the general magazine of works), acts of survey of the hidden works, acts of the carried-out testing, approbations and other source documents.

8. After decision making about preservation of object the builder (customer) provides preparation of technical documentation. The amount and contents of technical documentation are determined by the builder (customer).

9. Are part of works on preservation of object including:

a) accomplishment of the designs accepting project loadings (including temporary);

b) installation of equipment, in addition fixing unstable designs and elements, or dismantle of such designs and elements;

c) release of reservoirs and pipelines from dangerous and combustible liquids, closing or welding of hatches and large openings;

d) reduction of processing equipment in safe condition;

e) shutdown of engineering communications, including temporary (except for those which are necessary for ensuring safety of object);

e) acceptance of the necessary measures interfering unauthorized access in object and on the territory of construction site.

10. The builder (customer) within 10 calendar days after decision making about preservation of object notifies on it the contractor, the body which issued construction permit (reconstruction), and also body of the state construction supervision if the construction (reconstruction) of object is subject to the state construction supervision.

11. The solution on renewal of construction (reconstruction) of the preserved object (except for object of state-owned property), and also about source of funds for payment of the expenses connected with reduction of object in condition in case of which continuation of construction (reconstruction) is possible is accepted by the builder (customer).

12. In case of renewal of construction (reconstruction) on earlier preserved object the builder (customer) performs:

a) technical inspection of object by results of which the necessary amount and cost of the works on recovery lost or destroyed for the period preservation of structural components or details of object are determined;

b) introduction (if necessary) changes in earlier prepared project documentation with the subsequent conducting state examination and the state ecological assessment of these changes if the legislation of the Russian Federation provides conducting such examination, or preparation of the new project documentation.

13. The builder (customer) shall beforehand, but not later than 7 working days before renewal of construction (reconstruction) of object, send to the body which issued construction permit (reconstruction) of object and also to body of the state construction supervision if the construction (reconstruction) of object is subject to the state construction supervision, the notification on renewal of construction (reconstruction) of object.

II. Features of decision making about preservation of object of state-owned property

14. The decision on preservation of object of state-owned property is made in the form of the act of the Government of the Russian Federation.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.