ORDER OF THE MINISTRY OF THE NATURE OF RUSSIA

of June 25, 2010 No. 218

About approval of requirements to structure and execution of the project documentation on development of the fields of solid minerals, liquidation and preservation of mine workings and primary conversion of mineral raw material

According to Item 14 of the Regulations on preparation, coordination and approval of engineering designs of development of the fields of the minerals and other project documentation on performance of works connected with use of subsurface areas by types of minerals and types of the use of natural resources approved by the order of the Government of the Russian Federation of March 3, 2010 N 118 (The Russian Federation Code, 2010, N 10, the Art. 1100), the Regulations on the Ministry of Natural Resources and Environmental Protection of the Russian Federation approved by the order of the Government of the Russian Federation of May 29, 2008 N 404 (The Russian Federation Code, 2008, N 22, the Art. 2581, N 42, the Art. 4825, N 46, Art. 5337; 2009, N 3, Art. 378, N 6, Art. 738, N 33, Art. 4088, N 34, Art. 4192, N 49, Art. 5976; 2010, N 5, to the Art. 538, N 10, of the Art. 1094, N 14, of the Art. 1656), I order:

Approve the enclosed requirements to structure and execution of the project documentation on development of the fields of solid minerals, liquidation and preservation of mine workings and primary conversion of mineral raw material.

 

Minister Yu.P.Trutnev

Appendix

to the order of the Ministry of Natural Resources and Environmental Protection of the Russian Federation of June 25, 2010 No. 218

Requirements to structure and execution of the project documentation on development of the fields of solid minerals, liquidation and preservation of mine workings and primary conversion of mineral raw material

I. Requirements to structure of the project documentation on development of the fields of solid minerals

1. General explanatory note.

1.1. Basis for project development.

1.2. Basic data and conditions for preparation of the project documentation:

license for mineral right;

design assignment;

administrative documents on coordination of the location of object (act of the choice of the platform);

reporting documentation on results of engineering survey;

specifications on external engineering support;

other initial and allowing documents.

1.3. Basic provisions (technical and economic solutions) of the project.

2. Geological structure of the mine (career) field.

2.1. General information and environment.

2.2. Geological study of the mine (career) field.

2.3. Assessment of complexity of geological structure of the mine (career) field.

2.5. Hydrogeological conditions.

2.6. Characteristic of mineral.

2.7. Passing minerals and useful components.

2.8. Production wastes.

2.9. Mining-and-geological service conditions.

2.10. Borders and inventories of the mine (career) field.

3. Technical solutions.

A. Shakhty (mines).

1. Design capacity and operating mode of the mine.

2. Choice of system of development.

3. Opening of the mine field.

3.1. Scheme of opening.

3.2. Key parameters of mine workings.

3.3. Technology of carrying out mine workings.

4. Mine development. System of development and schedules of working off.

4.1. Mine development. Mountain and preparatory and cut works.

4.2. System of development and schedules of working off. (Amounts and terms of works, procedure for input of operational objects in development).

5. Mine ventilation.

5.1. Choice and reasons for the scheme of airing.

5.2. Calculation of air for indicators.

5.3. Choice of fans of the main airing.

5.4. Calculation of depression of mine workings.

6. Goaf stowing. Leaving of breeds in mine workings.

7. Underground transport. Delivery of people, freights and materials.

8. Drainage and water outflow.

9. Safe engineering when conducting mining operations.

10. Measures of protection of objects of the land surface from adverse effect of mining operations.

11. Technological complex on the surface of the mine (mine).

12. Non-productive departments. Repair and warehouse complex.

B. Pits (cuts).

1. Design capacity and operating mode of pit.

2. Opening and procedure for working off of the field of pit.

2.1. Procedure for working off.

2.2. Opening of the field of pit.

3. System of development.

3.1. General information.

3.2. Choice of system of development.

3.3. Calculation of key parameters of pit (section). Elements of system of development.

3.4. Drilling and blasting operations.

3.5. Equipment, machines and mechanisms for overburden and mining works.

3.6. General scheme of works and schedule of quarrying. (Amounts and terms of works, procedure for input of operational objects in development).

4. Hydromechanization of mining operations (in the presence).

4.1. System of development.

4.2. Route of the main pulpovod.

4.3. Dump economy.

4.4. Water supply of hydroelectric power plants.

5. Dump economy.

5.1. General characteristic of dump works.

5.2. Stability of dumps.

5.3. Dumping method. Mechanization of dump works.

5.4. Parameters of dumps.

5.5. Procedure for dumping of dumps. Schedule of dump works.

5.6. Dump equipment.

6. Open-cut transport.

7. Safe engineering when conducting open mining operations.

8. Drainage of the field of pit (section).

9. Methods of airing of pit (section).

10. Technological complex on surface.

10.1. Acceptance and processing of mineral.

10.2. Loading and warehouse complex.

10.3. Repair and warehouse economy.

4. Quality of mineral.

4.1. The expected quality of the extracted mineral.

4.2. Consumer requirements to quality of products.

4.3. The expected quality of products.

4.5. Quality control of the got and shipped products.

5. The organization and technical solutions when conducting works in danger areas.

6. Production management, company. Organization and working conditions of workers.

7. Architectural and construction decisions.

7.1. Basic data.

7.2. Architectural concepts.

7.3. Constructive and space-planning decisions.

8. Engineering facilities. Networks and systems.

8.1. Utility power system.

8.2. Water supply system.

8.3. System of water disposal and sewerage.

8.4. Heating, ventilation and air conditioning.

8.5. Heat supply and thermal networks. Thermal mode of mining.

8.6. Pneumatic economy.

8.7. Communication and alarm system.

9. Master plan and external transport.

9.1. Short characteristic of the area and platform of construction.

9.2. Master plan.

9.3. External transport.

10. Organization of construction.

10.1. Characteristic of the area and conditions of construction.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.