RESOLUTION OF COUNCIL OF MINISTERS OF THE REPUBLIC OF BELARUS

of March 3, 2005 No. 235

About approval of the Regulations on procedure for forming of the contract (contractual) price and calculations between the customer and the contractor when constructing facilities

(as amended on 31-01-2014)

According to Item 6 of the Presidential decree of the Republic of Belarus of February 7, 2005 No. 58 "About carrying out the contract biddings in construction and recognition voided separate decrees, provision of the presidential decree of the Republic of Belarus" Council of Ministers of the Republic of Belarus DECIDES:

1. Approve enclosed:

Regulations on procedure for forming of the contract (contractual) price and calculations between the customer and the contractor when constructing facilities;

1(1). Operation of this resolution does not extend to the organizations concerning which materials of preliminary coordination of the site area are provided to the relevant local executive and administrative organ in the location of the parcel of land or there are decisions of the relevant local executive and administrative organ on coordination of placement of construction object and (or) on permission of carrying out design and exploration work accepted before entry into force of this resolution.

Action of the Regulations on procedure for the forming of the contract (contractual) price and calculations between the customer and the contractor when constructing facilities approved by this resolution does not extend to objects which architectural planning design assignment is received after January 1, 2012.

1(2). To make to the Ministry of Architecture within the competence explanations on application of this resolution.

2. It is excluded

3. To republican state bodies to bring the regulatory legal acts into accord with this resolution.

 

Prime Minister of the Republic of Belarus

S. Sidorsky

Approved by the Resolution of Council of Ministers of the Republic of Belarus of March 3, 2005 No. 235

Regulations on procedure for forming of the contract (contractual) price and calculations between the customer and the contractor when constructing facilities

1. This Provision determines procedure for forming of the contract (contractual) price and calculations between the customer and the contractor when constructing facilities, is obligatory to application when constructing facilities on which obligatory carrying out the contract biddings according to the Presidential decree of the Republic of Belarus of February 7, 2005 No. 58 "About carrying out the contract biddings in construction and recognition voided separate decrees, provision of the presidential decree of the Republic of Belarus" (The national register of legal acts of the Republic of Belarus, 2005, No. 23, 1/6218) is established, and also can be applied when holding in accordance with the established procedure procedure of negotiations if the contract (contractual) price by results of negotiations is created using the integrated standard rates of construction cost of objects.

2. In this Provision the following terms and their determinations are used:

the price of the customer (investor) - the starting price of construction object (contract works) offered by the customer (investor) for decision date about carrying out the contract biddings or negotiations;

bid price of the contractor - the price of contract works and costs determined by contract organizations - applicants for receipt of the construction order for decision date about carrying out the contract biddings or negotiations;

the contract (contractual) price - the price determined by results of carrying out the contract biddings or negotiations based on bid price of the contractor - the winning bidder or the applicant participating in negotiations;

the integrated standard rates of construction cost of objektovnormativa of construction cost of objects representing value term of construction costs of objects counting on power unit (the areas, amount) objects and considering the national average level of prices for construction;

procurement and warehouse expenses - expenses of contract organizations on content of the structural divisions performing functions of production and technological picking of contract organizations, warehouse economy, cost recovery, connected with hardly removable losses (spoil of materials in case of their transportation and storage), determined according to standard rates of procurement and warehouse expenses;

basic estimated cost - the cost determined in accordance with the established procedure by estimate norms and the prices in estimate documentation;

weighted average prices - the prices calculated as the relation of the amount of works of amounts and the prices of materials, works and services, applied on all their producers in the region, to the amount of amounts of the specified resources;

the operating (current) prices, rates - the prices, rates created in accordance with the established procedure and operating for date of pricing of the customer and bid price of the contractor;

planned estimated price - the price of work (service) in operation, servicing, repair and transfer of the construction machines and mechanisms providing compensation of planned cost of work item (service), taxes, charges (duties), other contributions to the income of the relevant budgets provided by legal acts, except for included in unit cost of work (service) arrived;

contract works and costs of the contractor - complex of the works performed by the contractor and its costs accompanying construction in case of construction of objects on which accomplishment by results of the contract biddings or negotiations the construction contract is signed.

3. The price of the customer (investor) and bid price of the contractor are created on the basis:

the design estimates approved in accordance with the established procedure;

the integrated standard rates of construction cost of objects or the sheet of amounts and cost of works on form according to appendix 1 (at the choice of the customer);

the works schedule in form according to appendix 2;

the payment schedule in form according to appendix 3.

The integrated standard rates of construction cost of objects affirm the Ministry of Architecture and remain invariable within 5 years. At the same time the applicant organizations in case of submission of the competitive offer can apply the integrated standard rates of construction cost of objects developed in these organizations and which are not exceeding approved by the Ministry of Architecture to participation in the contract biddings.

4. The price of the customer (investor) and bid price of the contractor are determined in the prices of decision date about carrying out the contract biddings or negotiations taking into account taxes, charges (duties) and other contributions to the income of the relevant budgets according to the current legislation.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.