RESOLUTION OF THE CABINET OF MINISTERS OF THE REPUBLIC OF UZBEKISTAN

of January 13, 1999 No. 14

About measures for the organization in the self-produced Republic of Uzbekistan of liquid chlorine, chlorproducts and the caustic soda

For the purpose of creation in the republic of capacities of import-substituting productions of chlorine liquid, hydrochloric acid and the caustic soda and in pursuance of the resolution of the Cabinet of Ministers of the Republic of Uzbekistan of March 25, 1998 the Cabinet of Ministers decides N129 "About the Program of Complex Development of the Companies of the Chemical Industry of Uzbekistan for 1998 - 2002":

1. Accept the offer of Uzkhimprom association on project implementation on creation on PO Navoiazot of capacities on production of 17 thousand tons of chlorine liquid, 12,6 thousand tons of hydrochloric acid, 6,7 thousand tons of hypochlorite of sodium and 26 thousand tons of the caustic soda a year.

2. Permit Uzkhimprom association to sign the contract with "Lurgi Anlagenbau Hemints Gmbh" (Germany) for preparation of technical documentation, supply of equipment, materials, also the technical guidance behind commissioning of processing equipment on production of liquid chlorine, hydrochloric acid, hypochlorite of sodium and the caustic soda with the term of input of capacities in 20 months after the introduction of the contract in force is performed supervision of erection.

3. Determine:

the general customer of construction of production of chlorine liquid, chlorproducts and the caustic soda - Navoiazot production association;

the prime contractor on construction of the construction this proizvodstvanavoiysky management with involvement of subcontractors;

the general designer - Uzniikhimproyekt institute;

terms of designing, supply of equipment, installation and commissioning of object according to the appendix N1.

4. Determine that financing of currency part of the project is performed:

in the amount of 85 percent of cost of the contract within the credit line Berliner Banka under insurance of society "Hermes" refinanced by National Bank of foreign economic activity of the Republic of Uzbekistan for a period of 7 years in the amount of 43010 thousand DM

in the amount of 15 percent of cost of the contract within the credit line Berliner Banka refinanced by National Bank of foreign economic activity of the Republic of Uzbekistan for a period of two years in the amount of 7590 thousand DM.

Repayment of the credits will be performed by PO Navoiazot at the expense of own sources in the terms established by the credit agreement (appendices N 2, 3 confidentially)

5. Confidentially

6. Confidentially

7. To National Bank of foreign economic activity of the Republic of Uzbekistan in two-month time to sign the credit agreement with Berliner Bankom on financing of this project.

8. Authorize the Minister of Finance in accordance with the established procedure to issue guarantees of the government of the Republic of Uzbekistan Berliner Banku, to National Bank of foreign economic activity of the Republic of Uzbekistan on the currency and amount-based loans attracted for this project.

9. To the Ministry of Justice of the Republic of Uzbekistan according to the current legislation to draw up the legal conclusions on guarantees of the Government of the Republic of Uzbekistan.

10. Determine that for PO Navoiazot for implementation of the specified project in case of calculation of the income tax the taxable basis decreases by cost amount, directed to loan repayment, received on this project.

11. To impose control over the implementation of this resolution on the Prime Minister of the Republic of Uzbekistan Sultanov U. T.

 

Chairman

Cabinet of Ministers I. Karimov

Appendix № 1

to the resolution of the Cabinet of Ministers of January 13, 1999 No. 14

Schedule of designing of technology part and supply of equipment of metalwork by "Lurgi Anlagebau Hemints Gmbh"

+--------------------------------------------------------------------+
¦N   ¦Наименование                         ¦Начало        ¦Окончание ¦
¦п.п.¦                                     ¦              ¦          ¦
+--------------------------------------------------------------------¦
¦                          I. Проектирование                         ¦
+--------------------------------------------------------------------¦
¦    ¦Рабочие чертежи технологического     ¦              ¦          ¦
¦1.  ¦оборудования                         ¦1 месяц       ¦6 месяцев ¦
+----+-------------------------------------+--------------+----------¦
¦    ¦Рабочие чертежи монтажа оборудования ¦              ¦          ¦
¦2.  ¦и трубопроводов                      ¦1 месяц       ¦14 месяцев¦
+----+-------------------------------------+--------------+----------¦
¦3.  ¦Рабочая документация                 ¦              ¦          ¦
¦    ¦электротехнической части и КИПиА     ¦2 месяца      ¦7 месяцев ¦
+--------------------------------------------------------------------¦
¦                       II. Поставка оборудования                    ¦
+--------------------------------------------------------------------¦
¦4.  ¦Технологические стальные конструкции ¦3 месяца      ¦12 месяцев¦
+----+-------------------------------------+--------------+----------¦
¦5.  ¦Основное и вспомогательное           ¦              ¦          ¦
¦    ¦оборудование                         ¦3 месяца      ¦12 месяцев¦
+----+-------------------------------------+--------------+----------¦
¦6.  ¦Материалы, арматура и трубопроводы   ¦8 месяцев     ¦17 месяцев¦
+----+-------------------------------------+--------------+----------¦
¦7.  ¦Электротехнические материалы и       ¦              ¦          ¦
¦    ¦приборы КИПиА                        ¦6 месяцев     ¦17 месяцев¦
+--------------------------------------------------------------------¦
¦         III. Строительство, монтаж и пусконаладочные работы        ¦
+--------------------------------------------------------------------¦
¦8.  ¦Шефмонтаж основного оборудования и   ¦              ¦          ¦
¦    ¦подготовка к вводу                   ¦12 месяцев    ¦20 месяцев¦
+----+-------------------------------------+--------------+----------¦
¦9.  ¦Монтаж и ввод в эксплуатацию         ¦              ¦          ¦
¦    ¦вспомогательного оборудования        ¦12 месяцев    ¦20 месяцев¦
+----+-------------------------------------+--------------+----------¦
¦10. ¦Шефмонтаж обвязки трубопроводов      ¦14 месяцев    ¦20 месяцев¦
+----+------------

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.