ORDER OF THE MINISTER OF ENERGY OF THE REPUBLIC OF KAZAKHSTAN

of January 17, 2025 No. 27-n/k

About approval of the normative and technical document by method of calculation of the size of the amount of ensuring mitigation of consequences of subsurface use on hydrocarbons

According to the subitem 2) of article 62 of the Code of the Republic of Kazakhstan "About subsoil and subsurface use", I ORDER:

1. Approve the normative and technical document by method of calculation of the size of the amount of ensuring mitigation of consequences of subsurface use on hydrocarbons according to appendix to this order.

2. In spheres of hydrocarbons and subsurface use of the Department of Energy of the Republic of Kazakhstan in the procedure established by the legislation of the Republic of Kazakhstan to provide to department of the state control:

1) within five working days from the date of signing of this order the direction it the copy in electronic form in the Kazakh and Russian languages in the Republican state company on the right of economic maintaining "Institute of the legislation and legal information of the Republic of Kazakhstan" the Ministries of Justice of the Republic of Kazakhstan for official publication and inclusion in Reference control bank of regulatory legal acts of the Republic of Kazakhstan;

2) placement of this order on Internet resource of the Department of Energy of the Republic of Kazakhstan after its official publication.

3. To impose control of execution of this order on the supervising vice-Minister of Energy of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Minister of Energy of the Republic of Kazakhstan

A. Satkaliyev

Appendix

to the Order of the Minister of Energy of the Republic of Kazakhstan of January 17, 2025 No. 27-n/k

The normative and technical document by method of calculation of the size of the amount of ensuring mitigation of consequences of subsurface use on hydrocarbons

Chapter 1. Basic provisions

This normative and technical document by method of calculation of the size of the amount of ensuring mitigation of consequences of subsurface use on hydrocarbons (further – the specifications and technical documentation) is constituted according to the subitem 2) of article 62 of the Code of the Republic of Kazakhstan "About subsoil and subsurface use" (further – the Code) for the purpose of uniformity of calculation of the size of the amount of ensuring mitigation of consequences of subsurface use in case of creation of basic project documents and analyses of development in the field of subsurface use on hydrocarbons.

Chapter 2. Scope

The specifications and technical documentation is applied to forming of the Section "Calculation of the Size of the Amount of Ensuring Mitigation of Consequences of Subsurface Use" in basic project documents and analyses of development in the field of subsurface use on hydrocarbons.

Chapter 3. Method of calculation of the size of the amount of ensuring mitigation of consequences of subsurface use on hydrocarbons

3.1. General provisions

According to Item 7 of article 126 of the Code, ensuring obligation fulfillment on mitigation of consequences of investigation, is created by means of fee of money in the amount of the amount determined in the project of prospecting works on the basis of market value of works on mitigation of consequences of investigation of hydrocarbons prior to carrying out the transactions provided by such project document. In case of approval of the amendment to the project of prospecting works providing value addition of works on mitigation of consequences of investigation, or the project of test operation the corresponding additional amount of the chosen method of providing it shall be granted prior to work, provided by such project document.

According to Item 9 of article 126 of the Code, the amount of ensuring obligation fulfillment is determined by mitigation of consequences of production in the project of mining on the basis of market value of works on mitigation of consequences of hydrocarbon production and is subject to recalculation at least once in three years within the analysis of development.

When calculating the size of the amount of ensuring mitigation of consequences of subsurface use on the sea field are subject to accounting of costs for dismantle of sea objects (artificial islands, dams, installations, pipelines and other sea objects) according to item 4 of article 157 of the Code.

According to item 4 of article 128 of the Code, financing of works on liquidation of the technological objects which are carried out outside mitigation of consequences of subsurface use on hydrocarbons is performed at the expense of means of the subsoil user.

When calculating the necessary amount of ensuring mitigation of consequences of subsurface use in calculation only the existing technological objects (including wells) at the time of field conclusion from operation are considered.

The specific standard rate is calculated depending on hydrocarbon production amounts for the profitable period. In case of production on the field and sale of commodity condensate and gas, amounts of condensate and gas are given to oil equivalent on average nominal value of sale of oil.

Market value of works on mitigation of consequences of subsurface use is determined by averaging of price offers of cost of liquidation of the objects provided by three potential suppliers having the relevant allowing documents and to have experience of mitigation of consequences of subsurface use within the last three years.

3.2. Basic data for calculation of the size of the amount of ensuring mitigation of consequences of subsurface use

The list of the data necessary for calculation of the size of the amount of ensuring mitigation of consequences of subsurface use with indication of the used reducings, is provided in Table 1.

Table 1. List of the data necessary for calculation of the size of the amount of ensuring mitigation of consequences of subsurface use

№ of payment order

Name

Explanations to filling of basic data

The used reducing

1

Quantity of wells for the end of the profitable period of mining

Quantity of the wells, gas and oil producing, delivery, supervisory funds and suspended wells which are subject to liquidation on the end of the period of mining.

Клс

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.