of August 1, 2024 No. 288
About approval of rules of approval of engineering designs of mining regarding accounting of losses in case of production of solid minerals
According to Item 8-1 of article 72 of the Code of the Republic of Kazakhstan "About subsoil and subsurface use" I ORDER:
1. Approve the enclosed rules of approval of engineering designs of mining regarding accounting of losses in case of production of solid minerals (further – Rules).
2. To provide to committee of geology of the Industry ministry and construction of the Republic of Kazakhstan in the procedure established by the legislation:
1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;
2) placement of this order on Internet resource of the Industry ministry and construction of the Republic of Kazakhstan.
3. To impose control of execution of this order on the supervising vice-Minister of Industry and construction of the Republic of Kazakhstan.
4. This order becomes effective after ten calendar days after day of its first official publication.
Minister of Industry and constructions of the Republic of Kazakhstan
K. Sharlapayev
It is approved Ministry of Finance of the Republic of Kazakhstan |
|
It is approved Ministry of national economy of the Republic of Kazakhstan |
|
Appendix
to the Order of the Minister of Industry and construction of the Republic of Kazakhstan of August 1, 2024 No. 288
1. These rules of approval of engineering designs of mining regarding accounting of losses in case of production of solid minerals are developed according to Item 8-1 of article 72 of the Code of the Republic of Kazakhstan "About subsoil and subsurface use" (further – the Code) and determine rules of approval of engineering designs of mining regarding accounting of losses in case of production of solid minerals, except for uranium.
2. The normalized losses are understood as the losses in subsoil which are technologically connected with the accepted methods and systems of development in case of production of the solid minerals which level is proved by technical and economic calculations provided by the engineering design of mining.
3. Accounting of losses in case of production of solid minerals is performed based on data on the normalized losses provided by the engineering designs of development of fields which are appendix to plans of mining operations.
Engineering designs of development of fields affirm authorized body on studying of subsoil from the date of adoption of the relevant decision and affects the mining period according to the plan of mining operations.
The copy of the approved plan of mining operations, including graphic applications, with indication of the mining operations of data on the normalized losses approved as a part of the plan and the engineering design of mining encloses to the cover letter for submission of the engineering design of mining to authorized body on studying of subsoil.
4. In case of modification of the plan of mining operations which affect indicators of the normalized losses engineering designs of development of fields are subject to reapproval.
5. The normalized losses in case of production of solid minerals are determined depending on specific mining-and-geological conditions, the applied schemes, methods and systems of mining.
6. For fields which contain several types of minerals data on the normalized losses are represented by each type of minerals, data on which contain in the Single inventory of the state fund of subsoil.
7. The authorized body on studying of subsoil within fifteen working days after submission of the engineering design of mining with data on the normalized losses and the proving documents has the right to send to the subsoil user reasonable objection by the amount of the normalized losses. In case of the direction of such objection in the specified time the normalized losses are determined by authorized body by studying of subsoil independently based on the available data on the normalized losses on similar projects or proceeding from earlier provided data.
to Rules of approval of engineering designs of mining regarding accounting of losses in case of production of solid minerals
Form
I claim __________________ ____________________________
(surname, name and middle name
(in case of its availability) date
Locus sigilli
authorized body
Engineering design of mining
1. Name of the subsoil user: _______________________________
2. Reasons for the normalized losses: ______________________________
3. Technical and economic calculations of the normalized losses: ______________
4. Data on the normalized losses:
№ of payment order |
The name of the field, the location on administrative territorial unit, No. ___ date _____ contracts/licenses |
Mineral type |
Calendar year |
Annual amount of production, thousands of tons/thousands of cubic meters |
The normalized losses, % (thousands of tons/thousands of cubic meters) |
1 |
2 |
3 |
4 |
5 |
6 |
Subsoil user head
__________________________________________________________________________
(surname, name and middle name (in case of its availability), the signature, date)
"____" ____________ 20 ___.
Locus sigilli of the subsoil user
(except for persons which are subjects of private entrepreneurship)
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions. This section provides answers to questions set by users.