Document from CIS Legislation database © 2003-2024 SojuzPravoInform LLC

I.O'S ORDER. MINISTER OF INDUSTRY AND CONSTRUCTION OF THE REPUBLIC OF KAZAKHSTAN

of October 23, 2023 No. 36

About approval of Rules of development, approval and approval of interregional schemes of territorial development

According to the subitem 376) Item 15 of the Regulations on the Industry ministry and the construction of the Republic of Kazakhstan approved by the order of the Government of the Republic of Kazakhstan of October 4, 2023 No. 864 "Some questions of the Industry ministry and construction of the Republic of Kazakhstan" of PRIKAZYVAYU:

1. Approve the enclosed Rules of development, approval and approval of interregional schemes of territorial development.

2. To provide to committee on cases of construction and housing and communal services of the Industry ministry and construction of the Republic of Kazakhstan in the procedure established by the legislation:

1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;

2) placement of this order on Internet resource of the Industry ministry and construction of the Republic of Kazakhstan.

3. To impose control of execution of this order on the supervising vice-Minister of Industry and construction of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Acting minister of the industry and construction of the Republic of Kazakhstan

I. Ospanov

It is approved

Ministry of national economy of the Republic of Kazakhstan

 

Approved by the Order of the acting minister of the industry and construction of the Republic of Kazakhstan of October 23, 2023 No. 36

Rules of development, approval and approval of interregional schemes of territorial development

Chapter 1. General provisions

1. These rules of development, approval and approval of interregional schemes of territorial development (further – Rules) are developed according to the subitem 376) of Item 15 of the Regulations on the Industry ministry and the construction of the Republic of Kazakhstan approved by the order of the Government of the Republic of Kazakhstan of October 4, 2023 No. 864 "Some questions of the Industry ministry and construction of the Republic of Kazakhstan" and establish procedure for development, approval and approval of interregional schemes of territorial development for two and more areas (or their parts), agglomerations, and also social and economic or ecological areas without borders of administrative and territorial units (further – Interregional schemes).

Chapter 2. Procedure for development, approval and approval of interregional schemes of territorial development

2. The interregional scheme is developed according to the general scheme of the organization of the territory of the Republic of Kazakhstan, serves for mutually approved (consolidated) architectural, town-planning and construction activities in the territories of two and more areas (or their parts), agglomerations, and also social and economic or ecological areas without borders of administrative and territorial units and determines:

1) zoning of the planned territory;

2) town-planning development and development of the territory;

3) measures for complex development of system of resettlement and placement of productive forces, transport, engineering, social and recreational infrastructures of regional and interregional values;

4) measures for rational environmental management, providing with resources, environmental protection.

3. The organization of development of Interregional schemes is performed by authorized body for architecture, town planning and construction (further – the Customer) together with local executive bodies (further – MIO).

The customer determines the developer (the general designer) according to the subitem 18) of Item 4-1 of Article 41 of the Budget code of the Republic of Kazakhstan.

4. The customer constitutes and approves design assignment according to appendix 1 to these rules in which determines structure of the Interregional scheme, procedure for receipt of basic data and approval of the Interregional scheme.

5. The design assignment establishes territory borders within which Interregional schemes are developed.

6. Initial materials for development of Interregional schemes are prepared according to design assignment the interested state bodies, and also the relevant MIO and transferred to developer (the general designer) within ten working days from the date of receipt of request.

7. The customer sends drafts of Interregional schemes for final consideration and approval in the interested state bodies which within ten working days direct the conclusions.

The draft of interregional schemes of territorial development of agglomerations is also approved with local councils of agglomerations.

8. The draft of the Interregional scheme before approval passes the complex town-planning examination according to Rules of conducting complex town-planning examination of town-planning projects of all levels, approved by the order of the Minister of national economy of the Republic of Kazakhstan of November 20, 2015 No. 706 "About approval of Rules of conducting complex town-planning examination of town-planning projects of all levels" (it is registered in the Register of state registration of regulatory legal acts for No. 12414).

9. Modification and amendments in the Interregional schemes which passed the complex town-planning examination and received the positive decision before its approval is not allowed.

10. The interregional schemes which did not pass the complex town-planning examination and did not receive its positive decision are not subject to approval.

11. Interregional schemes affirm the Government of the Republic of Kazakhstan.

12. The approved part of the Interregional scheme are basic provisions, the main drawing and the main technical and economic indicators of the draft of the Interregional scheme of territorial development according to appendix 2 to these rules.

13. Provision of the approved Interregional schemes in vector type for entering into the database of the state town-planning inventory is performed according to the Rules of maintaining and provision of information and (or) data from the state town-planning inventory of the Republic of Kazakhstan approved by the order of the Minister of national economy of the Republic of Kazakhstan of March 20, 2015 No. 244 "About approval of Rules of maintaining and provision of information and (or) data from the state town-planning inventory of the Republic of Kazakhstan" (it is registered in the Register of state registration of regulatory legal acts for No. 11111).

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.