of March 30, 2023 No. PP-104
O measures for further reforming of the hydroenergy sphere
For the purpose of ensuring execution of the Presidential decree of the Republic of Uzbekistan of April 8, 2022 No. UP-101 "About the Next Reforms on Creation of Conditions for Stable Economic Growth by Improvement of the Entrepreneurial Circle and Private Sector Development":
1. For the purpose of further building-up of capacities of hydropower to agree with offers of the Department of Energy, the Ministry of investments, the industry and trade and JSC Uzbekgidroenergo (further - Society) about bringing until the end of total 2028 of capacity of hydroelectric power stations to 5 507,8 MW, including creation of additional 3 279,8 MW of capacities for the realization account of the project on construction of total pumped storage power plants capacity of 1600 MW.
2. Approve the List of the equipment, component parts and the spare parts necessary for construction and operation of small hydroelectric power stations, and also recommended for localization in 2023 - 2025 on cooperation basis according to appendix No. 4
.3. Determine that:
requirements of the resolution of the President of the Republic of Uzbekistan of December 10, 2021 "About additional measures for further development of hydropower" are applied No. PP-44 to the projects provided by appendices No. No. 1 and 2 to the resolution of the President of the Republic of Uzbekistan of July 12, 2024 No. PP-252 "About acceleration of measures for reforming of the hydroenergy sphere
;after creation of wholesale and retail electricity markets the payment for the electric power developed by the regulating hydroelectric power stations, including pumped storage power plants will be performed based on separate procedure (payment for capacity);
Society can take part in quality of the state partner or in cooperation with private investors in the projects realized on the basis of public-private partnership in cases when these projects are interconnected and also the projects realized by it can make direct impact on hydroelectric power station as a part of Society;
realization in accordance with the established procedure of the assets belonging to JSC Suvsanoatmash as a part of Society by means of the public biddings, and also implementation of projects of production of installations of hydroelectric power stations at the expense of the means which arrived from realization and own means of Society with involvement of foreign partners is allowed.
4. Agree with offers of the Department of Energy, the Ministry of Economics and finance, Agencies on management of the state assets and Societies about:
construction at the expense of means of Society of the roads conducting to the territories in which perspective projects, and other necessary infrastructure facilities along with development of the design estimates with involvement of the contract organizations determined within the investment projects realized by Society in the above-stated territories are implemented;
provision of permission to the organizations in system of this Society on participation in the public procurements conducted in accordance with the established procedure by other organizations in system of Society;
inclusion of JSC Gidroproyekt involved in development of the design estimates of the investment projects realized by Society as the single supplier in the Unified register of suppliers created by the Ministry of Economics and finance;
provision of permission to Society and the organizations in its system on the conclusion of direct agreements on purchase of floating constructions with the MACLEC Technical Project Laboratory Pvt Ltd company (India);
to transfer of packet of the state shares of JSC Uzsuvloyikha to Society due to increase in the state share in its authorized capital.
5. To the ministry of investments, the industry and trade together with the Ministry of Economics and finance, the Department of Energy and Society:
in three-months time to hold negotiations with the relevant international financial institutions, foreign government financial institutions and foreign commercial banks on attraction of financial sources on perspective projects;
following the results of negotiations to provide inclusion of perspective projects in the address list of the investment projects realized with attraction of the foreign credits on behalf of the Republic of Uzbekistan or under guarantee of the Republic of Uzbekistan in a month.
At the same time:
for attraction of the foreign credits for perspective projects without provision of a guarantee for the Republic of Uzbekistan JSC Natsionalnye elektricheskiye seti Uzbekistana undertakes the obligation of the guaranteed purchase of the electric power developed within project data within at least 25 years on the rate established by the project and approved with the Interdepartmental tariff commission under the Cabinet of Ministers;
before approval of the feasibility statement on perspective projects on the credits required on these projects, the guarantee of the Republic of Uzbekistan is not provided.
6. To provide to society till February 1, 2024 development of the preproject documentation of perspective projects in interaction with potential investors with involvement of the domestic and foreign project organizations.
7. Determine that Society implements package of measures for diversification of industry, providing:
further effective use of the empty land in the territories adjacent to hydroelectric power stations and water storage basins, by construction on them solar photopower plants;
the beginning of development since August 1, 2023 of the additional electric power by widespread introduction of free-flow innovative technologies on the rivers and canals in regions of the republic;
implementation till June 1, 2023 together with the Ministry of Economics and finance of "the green certificate" for the electric power developed on hydroelectric power stations;
establishing production of hydroaggregates based on jurisdictional enterprises capacity to 1 MW - till January 1, 2024, capacity to 15 MW - till January 1, 2025;
projects implementation of construction of hydroelectric power stations and pumped storage power plants capacity over 5 MW on the basis of conditions of public-private partnership.
8. Establish procedure according to which in Society the modern principles of corporate management providing take root:
implementation of the principles of ecological, social and corporate management (ESG) and obtaining till 2025 of the rating of ESG;
creation in system of Society of service of the corporate and strategic consultant, and also finishing number of independent members as a part of the supervisory board to four people;
implementation since September 1, 2023 of practice of disclosure of information according to environmental standards;
increase since July 1, 2023 in operating efficiency of Society by comparison by benchmarking method with the leading profile foreign companies.
9. Implement the "Digital Transformation of the Sphere of Hydropower" project providing until the end of 2024:
consolidation of hydroelectric power stations and water storage basins in the single protected corporate network;
automation of instrumentations and implementation of system of obtaining, storage, processing and data analysis in water storage basins;
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions. This section provides answers to questions set by users.