RESOLUTION OF THE CABINET OF MINISTERS OF THE AZERBAIJAN REPUBLIC

of February 2, 2005 No. 18

About approval of Instructions for use electric power

(as amended on 11-11-2021)

According to article 4 of the Law of the Azerbaijan Republic "About power industry" and for the purpose of ensuring execution of the fifth paragraph of Item 3 of the Presidential decree of the Azerbaijan Republic "About approval of the Agreement on the right to management of Bakelektroset joint-stock company of November 7, 2001 No. 597, considering the offer of the Ministry of Industry and Energy approved with the Ministry of Economic Development, the Ministry of Finance and the Ministry of Justice the Cabinet of Ministers of the Azerbaijan Republic decides:

1. Approve "Instructions for use by the electric power" (are applied).

2. This resolution becomes effective from the date of signing.

Prime Minister of the Azerbaijan Republic

Artur Rasi-Zade

Approved by the Resolution of the Cabinet of Ministers of the Azerbaijan Republic of February 2, 2005 No. 18

Instructions for use electric power

1. General provisions

1.1. The basic concepts used in these rules have the following values:

- the state electrical power company (single state system of power industry) - consolidation of the transferring power networks of high voltage (is higher than 110 kilovolts) managed from the single center, their dispatching controls and the producers of energy subordinated to them;

- the power supplying company - the legal entity guaranteeing to the population and other consumers electric power supply on the basis of permission;

- the independent producer of energy - the legal entity belonging to the state, different industries of economy and the private organizations, supplying with electrical and heat energy of consumers by means of the state electrical power company or the power supplying companies through the power network belonging to them;

- the consumer of electrical energy - the legal entity or physical person buying electrical energy and using it by means of electroreceivers;

- the subscriber (the main consumer) - the consumer whose electrical units are connected to power supply networks of the power supplying company and signed sale and purchase agreements of electrical energy;

- the subsubscriber - the consumer whose electrical units are connected to the subscriber's power supply networks (the main consumer); 

- the household subscriber (population) - the consumer using electrical energy in the household purposes in apartments of residential buildings, hostels, special apartment houses and also at dachas, in personal garages;

- the customer - the owner of the new, reconstructed electrical units for which the permitted capacity of operation is increased and which change the scheme of electric utility service which connection to the power supply network is provided according to these specifications, or the legal entity and physical person which took these structures in use;

- electrical units - the equipment necessary for production, transfer and distribution of electrical energy, and the structures relating to it;

- power network - the electrical units consisting from jointly the operating transformer substations of different capacity, distribution installations, cable and air power lines;

- distribution installation - the electrical units delivering electrical energy to consumers, being part of the power supply network;

- border of balance sheet accessory - the split-off point determined by balance sheet accessory of the power supply network between the state electrical power company and the power supplying company, the state electrical power company and the independent producer of energy which is power supplying with the company and independent producer of energy which is power supplying with the company and the subscriber, the subscriber and the subsubscriber;

- the guaranteed rate - the rate established for each kilowatt hour of the electric power given to power network within the mechanism of support in the relation of the producers chosen by auction or direct attraction on the territories of renewable energy resources.

1.2. These rules are constituted on the basis of the Laws of the Azerbaijan Republic "About use of energy resources", "About power industry", "About power" and other legal acts, and determine relations between the state electrical power company and the power supplying companies, independent producers of energy and consumers of electrical energy. Execution of these rules is obligatory for the state electrical power company and the power supplying companies, independent producers of energy and consumers of electrical energy irrespective of subordination, pattern of ownership, financing source.

1.3. The electrosupplying company on the basis of the sale and purchase agreement of electrical energy buys electrical energy from the state electrical power company, or the independent producer of energy and sells it to consumers.

Between the electrosupplying company and the subscriber the sale and purchase agreement of electrical energy shall be signed.

The act of border of balance sheet accessory and of operational responsibility of the parties is attached to this agreement.

Sale and purchase agreements of electrical energy shall be signed according to the same agreements (appendices No. 1-5), attached to these rules.

1.4. Consumers (subsubscribers) connected to network of the subscriber (the main consumer) sign with him the sale and purchase agreement of electrical energy. In the sale and purchase agreement of electrical energy signed between the subscriber and the power supplying company, and appendix to this agreement the information about the subsubscribers connected to its network including the name of management, consumption of electrical energy, settlement electric counters, rate and other data are specified (appendix No. 9).

The power supplying company can sign sale and purchase agreements of electrical energy directly with the subsubscriber. If the power supplying company signs with the subsubscriber the sale and purchase agreement of electrical energy, expense of electrical energy the subsubscriber and the transit losses of electrical energy (technology expense) relating to it shall be subtracted from expense of the main consumer.

1.5. If from distribution installations which entrances belong to the consumer who is on balance of the power supplying company the electrical energy to two or bigger number of other consumers moves, the power supplying company is granted the right to directly sign with them sale and purchase agreements of electrical energy and to carry out calculations for electrical energy. Transfer of distribution installation of the consumer on balance of the power supplying company is performed according to the current legislation.

1.6. Connection to network of the new or reinstalled electrical units of the state electrical power company, independent producer, energy consumer, increase in the permitted capacity, change of the scheme of electric utility service is performed according to these rules based on specifications on connection of electrical units to network, and the act of the admission to operation of the Agency on regulation of energy questions in case of the Department of Energy of the Azerbaijan Republic (further - Agency on regulation of energy questions).

1.7. The procedure for the choice of the electric power producer in the territory of renewable energy resources, and also features and conditions of the agreements signed with the electric power producer chosen by auction or direct attraction in the territory of renewable energy resources is established by the President of the Azerbaijan Republic.

2. Specifications for connection of electrical units

2.1. Issue of specifications on connection to network of electrical units of the new, or new constructed power supplying companies, independent producers of energy and consumers, and also those with the changing scheme of power supply is performed according to "Rules of issue of specifications on connection to network of electrical units". Specifications of connection to network of electroinstallations of the independent producer of energy are determined by renewable energy resources by the agreement on connection to network signed between the independent producer of energy and the state electrical power company or which is power supplying with the company, and connection to network at the same time is performed according to requirements of this agreement.

2.2. In specifications on connection to network of electrical units of object the following is specified:

2.2.1. connection points (substation, power plant or the power line), tension which are expected cable or the air-lines feeding the object expected tension level in connection points with in some cases demand for consumption of heat energy, development of versions of the scheme of the feeding thermal networks;

2.2.2. reasonable requests about increase in capacity of the operating network (increase in cross section of wire, increase in capacity of transformers or their replacement, installation of reserve nests, etc.) according to the capacity provided for connection in connection with formation of new object (except for the household subscriber);

2.2.3. requirements for settlement limits of currents of short circuit (setting), protection of the relay, automatic equipment, communication, isolation and protection against supertension;

2.2.4. requirements imposed to qualitative indexes of electrical energy, compensation of reactive capacity and its consumption;

2.2.5. requirements imposed to accounting of electrical energy.

2.2.6. according to the standards existing in the Azerbaijan Republic (further - standards), the special requirements to installation of the devices controlling quality of electrical energy and the stabilizing installations, providing quality of energy in power networks and electroreceivers;

2.2.7. special requirements to the electrical units connected to power lines (possibility of reserve food and automatic protection on entrance, possibility of parallel work of power lines, separation into the feeding lines with reserve for the purpose of ensuring electric utility service of responsible loadings of electroreceivers in case of shortage of capacity in power supply system);

2.2.8. requirements to regulation of the daily load graph of consumers;

2.2.9. requirements to preparation of project decisions on the organization of operation of electrical units in the project (working project) of the company, the building, installation;

2.2.10. the list of the subsubscribers connected to network of the consumer with indication of the main perspective data on consumption of electrical energy and loadings.

2.3. Accomplishment of specifications is obligatory for the customer and designers. Effective period of specifications is established in case of allocation of the site under industrial construction or preparation of the order about designing of construction of residential objects, or reorganization of the companies and installations without occupation of the additional site, and this term is specified in specifications. The specified term according to existing rules shall be at least, than the term established for designing and completion of construction of the company, the building, installation, its queues or separate production structures. As a rule, effective period of specifications is established in two years. After effective period of specifications, the customer or designers shall together with the organization which issued them, to resolve question of prolongation of term of the specified conditions.

2.4. Compliance of the building, the company, installations, their queues or the project of separate production to specifications, "Rules of installation of electrical units" and requirements of regulating documents is considered and approved by the organization which issued specifications and Agency on regulation of energy questions. After approval of the project after the term of specifications its repeated approval is not required. If in some cases when designing the company, installation, its queue or any production, there is need for deviation from the approved project decision and specifications, similar withdrawal needs to be approved with the specified organization repeatedly. If in the considered construction projects withdrawal from specifications or the existing regulating documents comes to light, the organization which issued specifications and Agency on regulation of energy questions sends the customer the reasonable letter on refusal of connection to power network.

2.5. Before starting construction works on object with participation of the designer, the customer represents to the organization which issued specifications and Agency on regulation of energy questions the corresponding heads and working sketches of the project of the company, the building, installation, its queues or separate production. The organization which issued specifications and Agency on regulation of energy questions within ten days studies compliance of the approved construction projects to requirements of specifications, "Rules of installation of electrical units" and other regulating documents and approves the project.

If additional studying, term of consideration of the specified construction project in some cases is required it can be prolonged for a period of up to one month.

3. Commissioning of electrical units

3.1. All new, again established electrical units, and also electrical units with the scheme of power supply of the state electrical power company, the power supplying companies raised permitted to capacity utilization and changed, independent producers of energy, consumers, including subsubscribers, after accomplishment according to "Rules of installation of electrical units", construction regulations and other technical regulatory legal acts, shall be provided with the approved construction projects and technical documents of acceptance delivery according to established procedure.

3.2. Up to the permission to commissioning all new, reinstalled electrical units, and also electrical units with the increased permitted capacity and the changed scheme of power supply of the state electrical power company, the power supplying companies, independent producers of energy, consumers, including subsubscribers, after testing on acceptance delivery shall be accepted by the customer from the establishing organization for the act according to the existing rules. After that the customer shall provide to the inspector of the Agency on regulation of energy questions these installations, and also the documents specified in Item 3.2-1 of these rules for survey of the electrical units and receipt of permission to their input to operation. If the electrical unit of the customer conform to requirements of specifications, project documents, documents for acceptance delivery, "Rules of installation of electrical units", and also in the presence of the electrotechnical personnel prepared for servicing of the specified installation the inspector of the Agency on regulation of energy questions according to the Laws of the Azerbaijan Republic "About power" and "About licenses and permissions" issues the act of permission to commissioning of electrical units.

3.2-1. For issue by the Agency on regulation of energy questions of the act of permission to commissioning of electrical units over 150 kW, technical inspection is performed based on the following documents submitted by the statement and customers:

3.2-1.1. the specifications issued by the company of power supply or the state electrical power company;

3.2-1.2. the project of power supply approved with Agency on regulation of energy questions and the company of power supply;

3.2-1.3. the delivery and acceptance certificate between person which carried out construction and adjusting works and the customer;

3.2-1.4. copy of the order on purpose of person, responsible for electric economy;

3.2-1.5. protocol of measurement of resistance of contour of grounding

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.