ORDER OF THE GOVERNMENT OF THE RUSSIAN FEDERATION

of November 30, 2021 No. 2115

About approval of Rules of connection (technological accession) to systems of heat supply, including rules of non-discriminatory access to services in connection (technological accession) to systems of heat supply, rules of non-discriminatory access to services in transfer of heat energy, the heat carrier, and also about change and recognition voided some acts of the Government of the Russian Federation and separate provisions of some acts of the Government of the Russian Federation

According to the Federal Law "About Heat Supply" Government of the Russian Federation decides:

1. Approve enclosed:

Rules of connection (technological accession) to systems of heat supply, including rules of non-discriminatory access to services in connection (technological accession) to systems of heat supply;

Rules of non-discriminatory access to services in transfer of heat energy, heat carrier;

changes which are made to the order of the Government of the Russian Federation of October 22, 2012 No. 1075 "About pricing in the sphere of heat supply" (The Russian Federation Code, 2012, No. 44, Art. 6022; 2018, No. 29, Art. 4432).

2. Recognize invalid:

paragraphs two and third Item 1 of the order of the Government of the Russian Federation of July 5, 2018 No. 787 "About connection (technological accession) to systems of heat supply, non-discriminatory access to services in the sphere of heat supply, change and recognition voided some acts of the Government of the Russian Federation (The Russian Federation Code, 2018, No. 29, the Art. 4432);

the order of the Government of the Russian Federation of May 15, 2019 No. 596 "About modification of Rules of connection (technological accession) to systems of heat supply, including rules of non-discriminatory access to services in connection (technological accession) to systems of heat supply" (The Russian Federation Code, 2019, No. 21, the Art. 2561);

item 4 of changes which are made to acts of the Government of the Russian Federation concerning increase in efficiency, reliability and quality of heat supply in the price zones of heat supply approved by the order of the Government of the Russian Federation of May 22, 2019 No. 637 "About introduction of amendments to some acts of the Government of the Russian Federation concerning increase in efficiency, reliability and quality of heat supply in price zones of heat supply" (The Russian Federation Code, 2019, No. 21, the Art. 2590);

Item of 5 changes which are made to acts of the Government of the Russian Federation, the power accepting installations of consumers of electrical energy, facilities for production of electrical energy, objects of electric grid economy, objects of heat supply and the heatconsuming installations approved by the order of the Government of the Russian Federation of January 30, 2021 No. 85 "About approval of Rules of issue of permissions to the admission in operation and on introduction of amendments to some acts of the Government of the Russian Federation" (The Russian Federation Code, 2021, No. 6, the Art. 984).

3. This resolution becomes effective since March 1, 2022 and is effective till March 1, 2027.

Russian Prime Minister

M. Mishustin

Approved by the Order of the Government of the Russian Federation of November 30, 2021 No. 2115

Rules of connection (technological accession) to systems of heat supply, including rules of non-discriminatory access to services in connection (technological accession) to systems of heat supply

I. General provisions

1. These rules determine procedure for connection (technological accession) for the heatconsuming installations, thermal networks and sources of heat energy to systems of heat supply, including procedure for ensuring non-discriminatory access to services in connection (technological accession) to systems of heat supply taking into account features of connection (technological accession) of the heatconsuming installations, thermal networks to heat supply objects for the purpose of consumption of heat energy in the form of vapor.

Non-discriminatory access to services in connection (technological accession) to systems of heat supply provides equal conditions of provision of the specified services to their consumers.

2. For the purposes of these rules the used concepts mean the following:

"the act of readiness" - the act of readiness of on-site and intra house networks and the equipment of the connected object to giving of heat energy and the heat carrier given in appendix No. 1. The specified document confirms accomplishment by the applicant of conditions of connection;

"the act of connection" - the act of connection (technical accession) of object to system of heat supply given in appendix No. 2. The specified document confirms connection completion, including data on balance sheet accessory (limits of the Section of thermal networks, the heatconsuming installations and sources of heat energy on the basis of ownership on the property right or on other legal cause are specified) and operational responsibility;

"border of networks of engineering facilities of the apartment house" - the place of physical connection of thermal networks of the applicant and contractor determined by external wall of the apartment house of the applicant;

"connection" - set of the organizational and technical actions giving the chance to the connected object after connection (technological accession) to system of heat supply to consume heat energy from this system of heat supply, including in connection with increase in earlier connected thermal loading, to provide transfer of heat energy on adjacent thermal networks or to issue the heat energy made on source of heat energy in system of heat supply;

"reserve of handling capacity of thermal networks" - difference between the maximum handling capacity of thermal networks from source of heat energy to accession point taking into account actual state of thermal network, including hydraulic losses, and the amount of contractual thermal loadings of objects of the consumers connected to system of heat supply by means of thermal networks from source of heat energy, contractual thermal loads of the consumers connected to system of heat supply by means of the thermal networks from source of heat energy reserved under agreements of rendering services in maintenance of stand-by thermal power, the thermal loadings specified in the accepted requests for the conclusion of the agreement on connection (technological accession) to system of heat supply (further - the agreement on connection), the signed agreements on connection, and the issued information on possibility of connection of capital construction project to system of heat supply, which effective period did not expire;

"reserve of capacity of source of heat energy" - difference between the located thermal power of source of heat energy and the amount of contractual thermal loadings of objects of the consumers connected to system of heat supply by means of thermal networks from source of heat energy, contractual thermal loads of the consumers connected to system of heat supply by means of the thermal networks from source of heat energy reserved under agreements of rendering services in maintenance of stand-by thermal power, the thermal loadings specified in the accepted requests for the conclusion of the agreement on connection the signed agreements on connection and the issued information on possibility of connection of capital construction project to system of heat supply which effective period did not expire;

"connection point" - the place of physical connection of thermal networks of the contractor and thermal networks of the applicant on border of the parcel of land of the connected object if other is not determined by terms of the contract about connection, and for the apartment house - the place of physical connection of networks of engineering facilities of the house with thermal networks of the contractor. In case of connection of complex building the connection point for each capital construction project which is part of complex building including for objects of municipal, social, transport infrastructure, is determined on border of the parcel of land of the connected object according to the boundary-setting plan if other is not determined by terms of the contract about connection, and for the apartment house - on border of networks of engineering facilities of the apartment house;

"accession point" - the place of physical connection of thermal networks, actions for which creation are performed within agreement performance about connection, with the existing thermal networks or sources of heat energy of the contractor or the adjacent organization;

"applicant" - person having intention to connect object to system of heat supply, including to increase earlier connected thermal loading, and also the heatsupplying or heatnetwork organization in the cases provided by Items 6 and 26 of these rules;

"contractor" - the heatsupplying or heatnetwork organization corresponding to the criteria of reference of owners or other legal owners of thermal networks approved by the Government of the Russian Federation to the heatnetwork organizations owning on the property right or on other legal cause by thermal networks and (or) sources of heat energy heatsupplying or the heatnetwork organization planning accomplishment of actions for construction of sources of heat supply and (or) thermal networks if information on such actions is considered in the existing scheme of heat supply to which it is direct or through thermal networks and (or) sources of heat energy of other persons is performed connection of the object located in borders of heat supply of radius of effective heat supply determined according to the scheme (further - the radius of effective heat supply);

"the adjacent organization" - the organization owning on the property right or on other legal cause by technologically related thermal networks and (or) sources of heat energy in system of heat supply. The adjacent organization for the purpose of these rules is understood as also individual entrepreneur owning on the property right or on other legal cause by technologically related thermal networks and (or) sources of heat energy in system of heat supply;

"technologically related networks and (or) sources of heat energy" - the thermal networks and (or) sources of heat energy having mutual points of connection belonging on the property right or on other legal cause to the adjacent organizations and participating in single technological system of heat supply;

"information on possibility of connection" - the document containing data on possibility of connection of capital construction project within the thermal loading, and also data on the organization which provided such information requested by the applicant;

"connection specifications" - the document used for the purpose of architectural and construction designing of capital construction project, containing technical requirements for connection of capital construction project (including requirements to metering station of heat energy) and being the annex to the contract for connection (technological accession);

"complex building" - the building of the territory providing systematic construction, reconstruction of 2 and more capital construction projects connected by the unity of functions, processes, planning solutions, priority (staging) of implementation of construction, reconstruction according to the approved complex scheme of engineering support approved by the site planning of the territory and (or) the construction license. The construction, reconstruction of capital construction projects are performed taking into account need of creation, reconstruction of networks of engineering facilities taking into account the complex scheme of engineering support of the territory. Actions in the agreement on connection shall correspond to the approved complex scheme of engineering support of the territory.

3. The agreement on connection is public for the heatsupplying organizations, the heatnetwork organizations, including the single heatsupplying organizations.

If technically possible connection to system of heat supply in the corresponding point of connection refusal to the applicant in the conclusion of the agreement on connection concerning the object located in borders of radius of effective heat supply is not allowed.

If the scheme of heat supply does not determine the radius of effective heat supply for the corresponding objects, calculation of radius of effective heat supply is carried out by the contractor according to the methodical instructions for development of schemes of heat supply approved by the Ministry of Energy of the Russian Federation.

In case of refusal in the conclusion of the agreement on connection the contractor sends to the applicant the notification within 5 working days from the date of receipt of the request for the conclusion of the agreement on connection with indication of cause of failure. In case of disagreement with refusal the applicant has the right to address to the authorized body of local self-government of the settlement, city district, authorized body of the executive authority of the federal city responsible for development of the scheme of heat supply, for check of finding of object of the applicant in radius of effective heat supply.

In case of unreasonable refusal or evasion of the contractor of the conclusion of the agreement on connection the applicant has the right to take a legal action with the requirement of compulsion of the contractor to sign the agreement on connection.

4. The heatsupplying or heatnetwork organization to which applicants should address is determined according to the zones of operational responsibility of such organizations determined in the scheme of heat supply of the settlement, city district.

If the applicant has no data on the organization to which it is necessary to address for the purpose of the conclusion of the agreement on connection, he has the right to make in local government body the written request on submission of data on such organization with indication of the location of the connected object.

The local government body shall provide in writing data on the relevant organization, including its name and the location, within 2 working days from the date of the address of the applicant.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.