RESOLUTION OF THE CABINET OF MINISTERS OF UKRAINE

of March 31, 2021 No. 289

Some questions of use of the means provided in the government budget for implementation of the state investment projects in the sphere of water resources management

According to part seven of Article 20 of the Budget code of Ukraine the Cabinet of Ministers of Ukraine decides:

1. Approve the Procedure for use of the means provided in the government budget for implementation of the state investment project "Construction of Water Supply Systems in the Settlements of the Lviv Region Using Imported Water" which is attached.

2. Bring in the resolution of the Cabinet of Ministers of Ukraine of May 8, 2019 No. 379 "Some questions of use of the means provided in the government budget for implementation of the state investment projects in the sphere of water resources management" (The Official Bulletin of Ukraine, 2019 No. 39, the Art. 1365) changes which are applied.

Prime Minister of Ukraine

D. Shmygal

Approved by the Resolution of the Cabinet of Ministers of Ukraine of March 31, 2021 , No. 289

Procedure for use of the means provided in the government budget for implementation of the state investment project "Construction of Water Supply Systems in the Settlements of the Lviv Region Using Imported Water"

1. This Procedure determines the mechanism of use of the means provided in the government budget according to the program "Implementation of the state investment project "Construction of Water Supply Systems in the Settlements of the Lviv Region Using Imported Water" (further - budgetary funds).

2. The main manager of budgetary funds is Ministry for Protection of the Environment and Natural Resources.

Executive in charge of the budget program is Gosvodagentstvo.

3. Budgetary funds are used for implementation of the state investment project "Construction of Water Supply Systems in the Settlements of the Lviv Region Using Imported Water" which underwent selection according to the Procedure for selection of the state investment projects approved by the resolution of the Cabinet of Ministers of Ukraine of July 22, 2015 No. 571 "Some questions of management of the state investments" (The Official Bulletin of Ukraine, 2015, No. 64, the Art. 2116).

4. Gosvodagentstvo based on offers and the reasons for Basin management of water resources of the rivers of the Western Bug and Sang considered by basin councils of Dniester and the Western Bug and Sang constitutes taking into account planned targets of the Section III of the state investment project in coordination with Ministry for Protection of the Environment and Natural Resources approves the actions plan on implementation of the investment project (further - the actions plan). The copy of the actions plan moves to the Ministry of Finance and Ministry of Economics.

5. Gosvodagentstvo brings in accordance with the established procedure in the terms determined for approval of estimates to Basin management of water resources of the rivers of the Western Bug and Sang the actions plan and amounts of their financing.

6. The design estimates on performance of works are developed taking into account requirements of construction regulations and rules, acts of inspection and defective acts according to the Approval procedure of construction projects and conducting their examination approved by the resolution of the Cabinet of Ministers of Ukraine of May 11, 2011 No. 560 (The Official Bulletin of Ukraine, 2011, No. 41, the Art. 1674).

7. The expenses connected with financing of capital construction at the expense of budgetary funds are performed according to the Procedure for public financing of capital construction approved by the resolution of the Cabinet of Ministers of Ukraine of December 27, 2001 No. 1764 (The Official Bulletin of Ukraine, 2001, No. 52, the Art. 2374).

8. Purchase of goods, works and services at the expense of budgetary funds is performed in the procedure established by the law.

9. Advance payment of the goods, works and services which are purchased for budgetary funds for the purpose of accomplishment of the actions plan is performed according to requirements of the resolution of the Cabinet of Ministers of Ukraine of December 4, 2019 No. 1070 (The Official Bulletin of Ukraine, 2020, No. 2, the Art. 64).

10. Acceptance in operation of the finished with construction of facilities, separate queues and start-up complexes is performed according to Procedure for acceptance in operation finished with the construction of facilities approved by the resolution of the Cabinet of Ministers of Ukraine of April 13, 2011 No. 461 "Questions of acceptance in operation finished with construction of facilities" (The Official Bulletin of Ukraine, 2011, No. 32, Art. 1359; 2015, No. 78, Art. 2599).

11. Reflection in primary and financial accounting of information on opening of accounts, registration, accounting of the budget obligations in bodies of Treasury and carrying out the transactions connected with use of budgetary funds are performed in the procedure established by the legislation.

12. Creation and submission of financial and budget reports about use of budgetary funds, and also control of their target and effective expenditure are performed in the procedure established by the legislation.

13. Information on condition of implementation of the state investment project is submitted the main manager of budgetary funds in Ministry of Economics for carrying out monitoring of condition of development (realization) the state investment projects in accordance with the established procedure.

Approved by the Resolution of the Cabinet of Ministers of Ukraine of March 31, 2021 No. 289

Changes which are made to the resolution of the Cabinet of Ministers of Ukraine of May 8, 2019 No. 379

1. In Item 9 of the Procedure for use of the means provided in the government budget for implementation of the state investment project "Providing with Drinking Water Supply of Rural Settlements of Kazankovsky, Novobugsky Districts and Reconstruction of Water Waste Construction of the Sofiyevsky Water Storage Basin of Novobugsky District of the Nikolaev Region" approved by the specified resolution, words and figures "the resolution of the Cabinet of Ministers of Ukraine of April 23, 2014 No. 117 (The Official Bulletin of Ukraine, 2014, No. 34, of the Art. 916)" shall be replaced with words also in figures "the resolution of the Cabinet of Ministers of Ukraine of December 4, 2019 No. 1070 (The Official Bulletin of Ukraine, 2020, No. 2, of the Art. 64)".

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.