ORDER OF THE GOVERNMENT OF THE RUSSIAN FEDERATION

of July 3, 2019 No. 850

About approval of Rules of disconnection of capital construction project from networks of engineering facilities

According to part 2 of article 55.31 of the Town-planning code of the Russian Federation the Government of the Russian Federation decides:

Approve the enclosed Rules of disconnection of capital construction project from networks of engineering facilities.

Russian Prime Minister

D. Medvedev

Approved by the Order of the Government of the Russian Federation of July 3, 2019 No. 850

Rules of disconnection of capital construction project from networks of engineering facilities

1. These rules determine procedure for disconnection of capital construction project from networks of gas distribution, thermal networks, power networks, water and sewerage networks (further - networks of engineering facilities) in case of asset demolition of capital construction.

2. These rules do not extend to cases of asset demolition of capital construction for the purpose of construction of new capital construction project, reconstruction of capital construction project.

3. When implementing disconnection of capital construction project from networks of engineering facilities (except for water and sewerage networks) according to these rules the requirements to procedure for interruption in supply (consumption) for appropriate resource in capital construction project established by the legislation of the Russian Federation in the field of gas supply, heat supply and about power industry also shall be fulfilled.

4. Disconnection of capital construction project from networks of engineering facilities in connection with its demolition is performed based on the decision of the owner of capital construction project or the builder on asset demolition of capital construction or in the cases provided by the Town-planning code of the Russian Federation, other Federal Laws based on the judgment or local government body.

5. For the purpose of disconnection of capital construction project from networks of engineering facilities the builder, either the executive body of the government, or local government body (further - the initiator of shutdown) sends to the organization performing operation of networks of engineering facilities (further - the operational organization), the statement for issue of conditions of disconnection of capital construction project from networks of engineering facilities provided by part 2 of article 55.31 of the Town-planning code of the Russian Federation (further respectively - the statement, shutdown conditions).

6. If the builder or executive body of the government has no data on the operational organization, it sends to local government body in the location of the parcel of land on which the capital construction project which is subject to demolition, request about provision of data on such organization is located.

7. The local government body within 5 working days from the date of receipt of the request specified in Item 6 of these rules provides to the builder or executive body of the government of the data on the operational organization, including its name, the location address or the address of the place of the actual implementation of activities of the legal entity.

8. Are specified in the statement:

surname, name, middle name (in the presence) the initiator of shutdown (if the initiator of shutdown - the builder who is physical person), its postal address;

the name of the initiator of shutdown (if the initiator of shutdown - the builder who is the legal entity, executive body of the government, local government body), the location address;

data on location of the parcel of land on which the capital construction project which is subject to demolition is located;

types of networks of engineering facilities from which it is planned to perform shutdown of capital construction project;

the planned date of disconnection of capital construction project from networks of engineering facilities;

data on the judgment or local government body about asset demolition of capital construction or about obligation availability on demolition of unauthorized construction according to the land legislation (in the presence of such decisions or obligations).

Are enclosed to the application:

notarized copies of constituent documents of the initiator of shutdown (if the initiator of shutdown - the builder who is the legal entity);

the documents confirming the power of the person which signed the application (except for case when such application is signed by the builder who is physical person or person, having the right to act without power of attorney on behalf of the builder who is the legal entity);

copies of documents of title on the capital construction project planned to disconnection from networks of engineering facilities and (or) copy of documents of title on the parcel of land on which such object is located;

Full text available with active License only!

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 38000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.