ORDER MINISTERSTA OF FUEL AND POWER OF UKRAINE

of July 29, 2002 No. 449

About approval of Rules of connection of electroinstallations of consumers to special automatic equipment of switching off of loading (SAON)

(as amended of the Order of the Ministry of Fuel and Energy of Ukraine of 31.07.2012 No. 554)

According to requirements of the Law of Ukraine "About power industry" concerning preserving integrity and ensuring reliable and effective functioning of the Integrated power system of Ukraine and for the purpose of determination of relations of subjects of power industry, consumers and local executive bodies in case of development and use of the special automatic equipment of shutdown of loading (SAESL)

I ORDER:

1. Approve Rules of connection of electroinstallations of consumers to special automatic equipment of switching off of loading (SAON) which are attached.

2. Consider such which is not applied on territor

AI of Ukraine, industry regulating document GKD 34.35.511-98 "Special Automatic Equipment of Shutdown of Loading (SAESL). Rules of connection of electroinstallations of consumers to SAON", approved by the Department of Energy of Ukraine on September 11, 1998.

3. To department concerning power industry (to Datsishin B. Ya.) provide provision on state registration in the Ministry of Justice of Ukraine of the order "About Approval of Rules of Connection of Electroinstallations of Consumers to the Special Automatic Equipment of Shutdown of Loading (SAESL)".

4. To impose control of execution of this order on the Deputy State secretary Andriychuk Yu. A.

 

Minister

V. Gayduk

It is approved:

Chairman of the National commission

regulations of power industry

Ukraine Yu.V.Prodan

 

Approved by the Order of Mintoplivoenergo of Ukraine on July 29, 2002 No. 449

Rules of connection of electroinstallations of consumers to special automatic equipment of switching off of loading

І. General provisions

1.1. These Rules determine procedure for connection of electroinstallations of consumers to special automatic equipment of switching off of loading (further - SAVN), procedure for operational use of SAVN for increase in reliability of work of the Integrated power system of Ukraine (further - OES of Ukraine), and also separate energorayon and nodes of loading.

1.2. These Rules determine order of interaction of the state company "The national energy company "Ukrenergo" (further - GP "NEK "Ukrenergo"), its structural divisions (electric utility systems) with the eletroperedayushchy organizations, and also consumers of electrical energy during development, servicing and application of SAVN.

1.3. Requirements of these Rules extend to all subjects of managing in power industry irrespective of form of their property.

1.4. In these Rules requirements of such normative legal acts are applied:

The law of Ukraine "About power industry";

The regulations on the Ministry of Fuel and Energy of Ukraine approved by the Presidential decree of Ukraine of April 6, 2011 No. 382;

Regulations on the state energy supervision of the modes of the consumption of electrical and heat energy approved by the resolution of the Cabinet of Ministers of Ukraine of August 7, 1996 No. 929 (in edition of the resolution of the Cabinet of Ministers of Ukraine of February 13, 2006 No. 131);

Regulations on procedure for imposing on subjects of managing of penalties for violation of the law in industry of power industry and the sphere of heat supply approved by the resolution of the Cabinet of Ministers of Ukraine of July 21, 1999 No. 1312;

The instructions for use electrical energy approved by the resolution of the National commission of regulation of power industry of Ukraine of July 31, 1996 No. 28, registered in the Ministry of Justice of Ukraine on August 2, 1996 for No. 417/1442 (with changes);

User Rules for Operating Electrical Equipment approved by the order of Mintoplivenergo of July 25, 2006 No. 258, registered in the Ministry of Justice of Ukraine on October 25, 2006 for No. 1143/13017 (with changes);

Rules of use of system antiemergency automatic equipment of prevention and liquidation of dangerous decrease in frequency in the power supply systems approved by the order of Mintoplivenergo of December 1, 2003 No. 714, registered in the Ministry of Justice of Ukraine on December 18, 2003 for No. 1177/8498 (further - GND 34.20.567-2003);

The instruction about creation and application of schedules of restriction and emergency shutdown of consumers, and also antiemergency systems of decrease in power consumption approved by the order of Mintoplivenergo of November 23, 2006 No. 456, of Ukraine registered in the Ministry of Justice on February 19, 2007 for No. 151/13418 (further - SOU-N of EE 20.568:2007);

Rules of safe operation of electroinstallations of the consumers approved by Gosnadzorokhrantrud's order of Ukraine of January 9, 1998 No. 4, registered in the Ministry of Justice of Ukraine on February 10, 1998 for No. 93/2533 (further - NPAOP 40.1-1.21-98);

Regulations for electrical installation (PUE - 86) - the 6th prod., reslave. and additional - M.: Energoatomizdat, 1986 (Rules ulashtuvannya elektroustanovka (PUE-86) approved by the Department of Energy and electrification of the USSR) (further - PUE - 86);

The collection of the leading Glavtekhupravleniya's materials of the Ministry of Energy of the USSR. Electrotechnical part (SRM-92). The edition fourth processed and added - M.: SPO of ORGRES, 1992 (Zb_rnika ker_vny mater_al_v Golovtekhupravl_nnya M_nenergo SRSR. Elektrotekhn_chna of chastin, zatverdzheny Golovny naukovo-tekhn_chny upravl_nnyam M_n_sterstva of power that elektrif_kats і ї SRSR v_d 07 grudnya 1989 to fate).

1.5. In these Rules terms are used in such value:

The button (key) of SAVN - the switching device by means of which launch of special automatic equipment of switching off of loading in the manual mode is performed;

the avalanche power failure (in power supply system) - rapid undervoltage as a result of violation of static firmness of power supply system and growth of deficit of reactive capacity;

the avalanche fall of frequency (in power supply system) - the rapid decrease in frequency in power supply system caused by growth of deficit of active capacity;

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.