It is registered

Ministry of Justice

Republic of Uzbekistan

On February 18, 2006 No. 1546

The ORDER of the STATE INSPECTORATE FOR SUPERVISION IN POWER INDUSTRY Uzgosenergonadzor

of December 26, 2005 No. 232

About approval of Rules of production, transfer and distribution of electrical energy

(The last edition from 13-09-2013)

Based on the Provision "About the State Inspectorate for Supervision in Power Industry (Uzgosenergonadzor)" approved by the resolution of the Cabinet of Ministers of the Republic of Uzbekistan of 01.03.2004 No. 96, I order:

1. Approve the enclosed Rules of production, transfer and distribution of electrical energy.

2. Enact this order after ten days from the date of its state registration in the Ministry of Justice of the Republic of Uzbekistan.

3. I reserve control of execution of this order.

Chief of inspection

B. Gulyamov

Approved by the Order of the chief of inspection Uzgosenergonadzor of December 26, 2005 No. 232

Rules of production, transfer and distribution of electrical energy

These rules according to the laws of the Republic of Uzbekistan "About rational energy use" (Sheets of Oliy Majlis of the Republic of Uzbekistan, 1997, Art. No. 4-5, 118) and "About power industry" (Collection of the legislation of the Republic of Uzbekistan, 2009, No. 40, Art. 431) establish single procedure for production process, transfer, distribution and sale of electrical energy, and also determine relations of the business entities participating in this process

Main terms and determinations

1. In these rules the following terms and determinations are used:

power industry - the sphere of production, transfer, distribution, sale and consumption of electrical energy (capacity);

single electric utility system - set of the companies for production of electrical energy, the high-level power networks, territorial power networks and supervisory control of them;

power network - set of the objects of electric grid economy intended for transfer or distribution of electrical energy;

transit of electrical energy - transfer of the electrical energy (capacity) on power networks of one state made in the territory of another and intended for the territory of the third state;

electroinstallation - set of the machines, devices, power lines and the service equipment (together with constructions and rooms, in which they are established) intended for production, transformation, transfer, distribution of electrical energy and its transformation to other type of energy;

power plant - the electroinstallation intended for production of electrical energy, containing construction part, the equipment for transformation of energy and the necessary service equipment;

block stations - the power plants of consumers connected directly or through power networks of consumers in single electric utility system and which are a part of the system of operational dispatching management;

the power companies - the companies (the companies for production of electrical energy, the main power networks company, the companies of territorial power networks, block stations, and also legal entities, which objects of electric grid economy are used as the high-level power networks) participating in production process, transfers, distribution and sale of electrical energy (capacity);

the single purchaser of electrical energy - division of specially authorized body in the field of power industry which is granted the right of the conclusion of purchase agreements of electrical energy at the companies for production of electrical energy, for sale of electrical energy to the companies of territorial power networks, on transfer of electrical energy with the main power networks company;

settlement period - period of time (month) for which the expense (amount) of consumption of electrical energy (capacity) shall be determined settlement between the consumer and the company of territorial power networks for the consumed electrical energy (capacity) is made;

the settlement metering device of electrical energy and capacity - the metering device of consumption of electrical energy (capacity), including adders and the Automated systems of accounting and control of consumption of electrical energy based on which indications the amount of the consumed electrical energy (capacity) which is subject to payment is determined;

settlement accounting of electrical energy - the measuring system of the actual amounts of electrical energy (capacity) in case of its production, transfer, distribution and consumption based on indications of settlement metering devices for implementation of settlement for electrical energy (capacity);

Full text available with active License only!

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 38000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.