THE ORDER OF THE FEDERAL SERVICE OF THE RUSSIAN FEDERATION ON ECOLOGICAL, TECHNOLOGY AND ATOMIC SUPERVISION

of November 20, 2017 No. 488

About approval of Federal regulations and rules of industrial safety "Safety rules in case of development of coal fields by open method"

According to subitem 5.2.2.16 (1) Item 5 of the Regulations on Federal Service for Environmental, Technological and Nuclear Supervision approved by the order of the Government of the Russian Federation of July 30, 2004 No. 401 (The Russian Federation Code, 2004, No. 32, Art. 3348; 2006, No. 5, Art. 544; No. 23, Art. 2527; No. 52, Art. 5587; 2008, No. 22, Art. 2581; No. 46, Art. 5337; 2009, No. 6, Art. 738; No. 33, Art. 4081; No. 49, Art. 5976; 2010, No. 9, Art. 960; No. 26, Art. 3350; No. 38, Art. 4835; 2011, No. 6, Art. 888; No. 14, Art. 1935; No. 41, Art. 5750; No. 50, Art. 7385; 2012, No. 29, Art. 4123; No. 42, Art. 5726; 2013, No. 12, Art. 1343; No. 45, Art. 5822; 2014, No. 2, Art. 108; No. 35, Art. 4773; 2015, No. 2, Art. 491; No. 4, Art. 661; 2016, No. 28, Art. 4741; No. 48, Art. 6789; 2017, No. 12, Art. 1729; to No. 26, of the Art. 3847), I order:

1. Approve the enclosed Federal regulations and rules of industrial safety "Safety rules in case of development of coal fields by open method".

2. Consider not No. 45 which is subject to application the resolution of the Federal inspectorate for mining and industry of Russia of May 30, 2003 "About approval "Safety rules in case of development of coal fields by open method" (it is registered by the Ministry of Justice of the Russian Federation on June 16, 2003, registration No. 4694).

3. This order becomes effective after six months after its official publication, except for Items 545 and 546 of the approved Federal regulations and rules of industrial safety "Safety rules in case of development of coal fields by open method" which become effective since January 1, 2022.

Head

A. V. Alyoshin

Approved by the Order of the Federal Service of the Russian Federation on ecological, technology and atomic supervision of November 20, 2017 No. 488

Federal regulations and rules of industrial safety "Safety rules in case of development of coal fields by open method"

I. Basic provisions

1. These Federal regulations and rules of industrial safety "Safety rules in case of development of coal fields by open method" (further - Safety rules) are developed according to requirements of the Federal Law of July 21, 1997 No. 116-FZ "About industrial safety of hazardous production facilities" (The Russian Federation Code, 1997, No. 30, Art. 3588; 2000, No. 33, Art. 3348; 2003, No. 2, Art. 167; 2004, No. 35, Art. 3607; 2005, No. 19, Art. 1752; 2006, No. 52, Art. 5498; 2009, No. 1, Art. 17, Art. 21; No. 52, Art. 6450; 2010, No. 30, Art. 4002; No. 31, Art. 4195, Art. 4196; 2011, No. 27, Art. 3880; No. 30, Art. 4590, Art. 4591, Art. 4596; No. 49, Art. 7015, Art. 7025; 2012, No. 26, Art. 3446; 2013, No. 9, Art. 874; No. 27, Art. 3478; 2015, No. 1, Art. 67; No. 29, Art. 4359; 2016, No. 23, Art. 3294; No. 27, Art. 4216; 2017, No. 9, Art. 1282; No. 11, the Art. 1540) (further - the Federal Law No. 116-FZ).

2. These rules of safety extend to the legal entities and individual entrepreneurs performing the activities on hazardous production facilities connected with development of coal fields by open method (further - coal mine), designing, construction and operation of coal mine, designing, production, installation, operation and repair of technical devices, professional rescue services and (or) professional rescue units (further - PASS(F), and also on employees of other organizations which activities are connected with coal mines.

3. These rules of safety establish requirements which observance ensures industrial safety and also ensuring their readiness for localization and mitigation of consequences of accidents is directed to the prevention of accidents and incidents on coal mines.

4. The project organization for the decision of the technical lead (chief engineer) of coal mine exercises designer's service of observance of the project decisions made in the project documentation in the main parameters of coal mine and dumps (corners of slopes of ledges and boards of coal mine, and also dumps, parameters of platforms and berm ledges), and also to conditions of use of the mining-transport equipment.

5. Works on preservation and liquidation of coal mine shall be carried out on condition of documentation availability on preservation and liquidation of coal mine and positive experimental testimony of industrial safety.

6. For check new and enhancements of the existing systems of development of coal mine and their parameters trial development of coal mine or its part which is performed based on the project of working off of coal mine, and also development plans for the mining operations approved by the technical lead (chief engineer) of coal mine is allowed.

7. Reduction of the operating coal mine in compliance with requirements of these rules of safety is performed in terms which are established by the head of coal mine. Before reduction of the operating coal mine in compliance with requirements of these rules of safety by the technical lead (chief engineer) of coal mine develops the actions proving and providing safe operation of coal mine. Before realization of the specified actions the technical lead (chief engineer) of coal mine shall send to the territorial authority of Federal Service for Environmental, Technological and Nuclear Supervision exercising federal state supervision in the field of industrial safety of coal mine, the plan of their realization.

II. Conducting mining operations

8. During change the mine foreman, and within a day - the yard foreman or his deputy who shall take measures for their elimination in the presence of abuses of regulations of safety shall inspect each workplace.

9. Tasks (job specifications) for works shall be drawn up in writing, with acquaintance of the worker under list. Forms and procedure for registration of tasks (job specifications) for works are determined by the technical lead (chief engineer) of coal mine.

10. Conducting works in the places having violations of these rules of safety except implementation of the works directed to their elimination is forbidden.

11. On works to which increased requirements of industrial safety are imposed written work permits shall be issued. Form and content of work permits is determined by the technical lead (chief engineer) of coal mine.

12. The work permit draws up also the admission on the territory of coal mine for performance of works of personnel of contract organization. In it completion date of works, dangerous factors shall be specified, borders of the site or object where the contract organization performs works are determined and bears responsibility for their safe production.

13. Explosive works on coal mines shall is carried out with observance of requirements of Federal regulations and rules of safety of "The safety rule the during the explosive works" approved by the order of Federal Service for Environmental, Technological and Nuclear Supervision of December 16, 2013 No. 605 (registration No. 31796) is registered by the Ministry of Justice of the Russian Federation on April 1, 2014.

14. On coal mines the operations procedure of workers and officials in case of detection of explosive materials shall be determined by them (further - VM) in the places which are not intended for storage of VM.

15. Excavations and drives to them in the places constituting danger of fall in them of people, animals, machines and mechanisms shall be blocked or protected.

16. Failures, sumps, funnels, invalid holes, drainage wells and other vertical developments shall be blocked or protected.

17. It is forbidden to encumber places of employment of the equipment and approaches to them with the mountain weight or any objects complicating movement of people, animals, machines and mechanisms.

18. Movement of people on the territory of coal mine is allowed on the arranged walking paths or on roadsides of highways towards to the direction of movement of vehicles, in the presence of individual protection equipment and light-reflective elements of clothes in night-time. All persons working at coal mine under list shall be acquainted with routes of movement.

19. In night-time walking paths and transitions through railway tracks and highways shall be lit.

20. On coal mine delivery of workers to work location on the vehicle equipped for this purpose shall be organized. Routes and speed of transportation of people affirm the technical lead (chief engineer) of coal mine.

21. The device of airfields on carriageway is forbidden.

22. Transportation of people in hopper-cars, bodies of dump trucks, cargo trolleys of the ropeways and other mining-transport oborudovaniye which are not intended for this purpose is forbidden.

23. For the message between ledges of coal mine it is necessary to establish strong ladders with bilateral hand-rail and inclination no more than 60 ° or congresses with bias no more than 20 °. Mid-flight ladders with height more than 10 m shall be width of at least 0,8 of m with horizontal platforms at distance from each other on height no more than 15 m. Installation sites of ladders on length of ledge are established by the development plan for mining operations. Steps and platforms of ladders need to be cleared of snow, ice, dirt and if necessary to strew with antiskid material.

24. Transition via belt conveyers is allowed only on the transitional bridges width of at least 0,8 of m equipped with handrail height m 1,1 suffices. In places of pass and journey under belt conveyers it is necessary to establish protective regiments for protection of people from possible defeat by the pieces of the transported material falling from tape.

25. On coal mine it is forbidden:

finding of people in the danger area of the working mechanisms, within prism of possible collapse on ledges and at the lower brow of slope of ledge;

work on ledges in zone of the hanging peaks, blocks, large boulders, and also navisy of snow and ice. In case of impossibility to make liquidation having pinned up or frill of ledge (board) all works in the danger area shall be stopped, people are removed, and the dangerous site shall be protected and the signs warning about the danger area are established.

26. In case of stop of works on coal mine or its site (sites) stay in its territory of faces which are not tied with ensuring its life activity or with accident liquidation is forbidden.

27. If there is threat of damage of the equipment, then it is removed from the danger area, in case of impossibility of its conclusion of the technician shall be deenergized or muffled.

28. The actions plan on localization and mitigation of consequences of accidents according to the Regulations on plan development of actions for localization and mitigation of consequences of accidents on hazardous production facilities approved by the order of the Government of the Russian Federation of August 26, 2013 No. 730 shall be developed for each coal mine (The Russian Federation Code, 2013, No. 35, the Art. 4516). The actions plan on localization and mitigation of consequences of accidents of coal mine joins the Section determining operations procedure in case of accident by rescuing of people and liquidation of accident during initial stage of origin and the prevention of its development - the liquidation plan of accidents (further - PLA).

29. Personnel of coal mine and personnel of contract organizations shall undergo instructing in industrial safety and to be acquainted with PLA. Instructing in industrial safety and acquaintance with PLA carry out according to the program approved by the technical lead (chief engineer) of coal mine.

30. Educational alarms on each coal mine shall be carried out according to the schedule approved with the division manager of PASS(F) servicing coal mine.

31. Doctrines (educational trainings) on PLA with heads and specialists shall be carried out at least once in three months under the leadership of the technical lead (chief engineer) of coal mine.

Mining operations on carrying out trenches, development of ledges and dumping of dumps

32. Mining operations on carrying out trenches, development of ledges and dumping of dumps shall be conducted taking into account engineering-geological conditions and the used equipment according to the project approved by the technical lead (chief engineer) of coal mine projects of works.

33. In the project of works the admissible sizes of working platforms, berm, corners of slope, height of ledge, prism of collapse, distances from the mining-transport equipment to brows of ledge or dump shall be specified.

34. Effective period of the project of works is established by the technical lead (chief engineer) of coal mine depending on conditions of conducting mining operations. In case of change of mining-and-geological conditions conducting mining operations shall be suspended before review of the project.

35. Specialists and workers, the leading works established by the project shall be informed of the project of works under list of person of technical supervision of coal mine.

36. Conducting mining operations without the approved project of works, and also with departure from requirements of the project is forbidden.

37. Around industrial platforms of coal mine the sanitary protection zone which sizes are determined by the project shall be established.

38. Height of ledge shall be determined by the project taking into account results of researches of physicomechanical properties of rocks and mineral, and also mining-and-geological and hydrogeological conditions of their bedding and parameters of the equipment.

39. In case of use of hydraulic excavators and lift trucks the safe height of ledge shall be determined by calculations taking into account trajectory of movement of working body (ladle) of the excavator (lift truck).

40. In case of use of rope excavators height of ledge shall not exceed:

maximum height of cherpaniye of the excavator;

height or depth of cherpaniye of dragline, mnogokovshovy chain and rotor excavators.

41. Ledge height for excavators with the extended working equipment is established by the project and shall provide visibility of transport vessels from the excavator operator's cabin.

42. In case of development manually height of ledge shall not exceed: 6 m - for friable steady dense breeds, 3 m - for friable unstable loose breeds.

43. In case of development of breeds using drilling-and-blasting works increase in height of ledge up to the one-and-a-half height of cherpaniye of the excavator is allowed provided that face height on disorder does not exceed the maximum height of cherpaniye of the excavator. It is allowed to divide disorder on height into layers (subledges) or to develop actions for safe collapse of peaks and navisy.

44. Corners of slopes of working ledges shall be determined by the project of works taking into account physicomechanical properties of rocks and shall not exceed:

80 ° - during the operation of excavators like power shovel, hydraulic excavators, lift trucks, draglines and rotor excavators;

corner of natural slope of these breeds - during the operation of mnogokovshovy chain excavators the lower cherpaniye and development manually friable and loose breeds.

45. Limiting corners of slopes of ledges and boards of coal mine (corners of steady board), including temporarily preserved sites of boards, are established by the project and can be corrected in use according to geological and surveying service of coal mine, by results of additional researches of engineering-geological conditions of array of board of coal mine and to dumps by project development of reconstruction or documentation on modernization.

46. Width of working platforms taking into account their purpose, and also arrangement to them of the mining-transport equipment, transport communications, utility lines and communication is determined by the project of works.

47. The distance from the lower brow of ledge (disorder of mountain weight) and from the upper brow of ledge to axis of the next railway track is established by the project and there shall be at least 2,5 of m.

48. Forming of temporarily non-working boards of coal mine and renewal of mining operations on them shall be made on the projects of works providing necessary security measures.

49. The distance between the lower brows of slopes of ledge of dump to axis of railway track or axis of the conveyor is established by the project and there shall be at least 4 m.

50. Distance between adjacent berma in case of repayment of ledges and their statement in limiting provision, width, design and procedure for servicing safety berm are determined by the project, taking into account ensuring stability of design of board of coal mine, the safe mechanized their cleaning. In use parameters of ledges and safety berm shall be specified if necessary by results of researches of physicomechanical properties of rocks and shall be at least established by the project.

51. In case of repayment of ledges, statement them in limiting provision it is necessary to observe the corners of slope of ledges, boards of coal mine established by the project. In all cases width of safety berma shall be such that its mechanized cleaning was provided.

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.