Document from CIS Legislation database © 2003-2025 SojuzPravoInform LLC

ORDER OF THE MINISTER OF INVESTMENTS AND DEVELOPMENT OF THE REPUBLIC OF KAZAKHSTAN

of December 13, 2017 No. 867

About approval of Acceptance procedures of the constructed object in operation by the owner independently, and also acceptance act forms

(as amended on 08-10-2024)

According to item 4 of article 74 of the Law of the Republic of Kazakhstan of July 16, 2001 "About architectural, town-planning and construction activities in the Republic of Kazakhstan" PRIKAZYVAYU:

1. Approve:

1) Acceptance procedures of the constructed object in operation by the owner independently according to appendix 1 to this order;

2) form of the acceptance act of the constructed object in operation by the owner independently according to appendix 2 to this order.

2. To provide to committee on cases of construction and housing and communal services of the Ministry for Investments and Development of the Republic of Kazakhstan:

1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;

2) within ten calendar days from the date of state registration of this order the direction it the copy on paper and electronically in the Kazakh and Russian languages in the Republican state company on the right of economic maintaining "The republican center of legal information" for official publication and inclusion in Reference control bank of regulatory legal acts of the Republic of Kazakhstan;

3) within ten calendar days after state registration of this order the direction it the copy on official publication in periodic printing editions;

4) placement of this order on Internet resource of the Ministry for Investments and Development of the Republic of Kazakhstan;

5) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Legal department of the Ministry for Investments and Development of the Republic of Kazakhstan of data on execution of actions, according to subitems 1), 2), 3) and 4) this Item.

3. To impose control of execution of this order on the supervising vice-minister of investments and development of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Minister of investments and development of the Republic of Kazakhstan

Zh. Kasymbek

Appendix 1

to the Order of the Minister of investments and development of the Republic of Kazakhstan of December 13, 2017 No. 867

Acceptance procedures of the constructed object in operation by the owner independently

Chapter 1. General provisions

1. These rules of acceptance of the constructed object in operation by the owner independently (further - Rules) are developed according to the Law of the Republic of Kazakhstan of July 16, 2001 "About architectural, town-planning and construction activities in the Republic of Kazakhstan" (further - the Law) and determine procedure for acceptance of the constructed object in operation by the owner independently.

2. Action of these rules extends to the objects specified in Item 1 of article 74 of the Law.

Chapter 2. Procedure for acceptance of the constructed object in operation by the owner independently

3. In case of acceptance of the constructed object by the owner availability independently is required:

1) the architectural and planning task issued by the local executive body performing functions in the field of architecture and town planning (except for reconstruction (re-plannings, re-equipments) rooms (separate parts) of the existing buildings which are not connected with changes of the bearing and protecting (outside) designs, engineering systems and the equipment and not providing additional withdrawal (cutting) of the parcel of land);

2) specifications (in need of connection, additional connection of object to sources of engineering and utility support and/or increase in loadings);

3) sketch (conceptual design) / engineering design;

4) executive geodetic surveying of actual position of engineering networks and/or buildings (constructions) (except for the objects specified in subitems 4), 11), 13), 16), 17), 19) of Item 2 of article 60 of the Law).

4. In case of completion of building and construction works, the owner after receipt of the notice in writing from the contractor on readiness of object (if the asset construction was performed by contract method) starts acceptance procedure of the constructed object in operation.

5. In case of acceptance of the constructed object in operation the owner:

1) is accepted by object in operation with execution of the acceptance act of the constructed object in operation by the owner independently in form, according to appendix 2 to this order (further - the act);

2) is checked by observance of requirements of the sketch (conceptual design) / the engineering design, the issued initial materials (documents) for designing of object and the existing normative and technical documents;

3) is checked by compliance of the performed building and construction works, the applied construction materials (products, designs) and the equipment to the sketch (conceptual design) / to the engineering design, and also the state (interstate) standard rates if the asset construction was performed by contract method.

The act of input of the constructed object approves 4) in case of reconstruction (re-planning, re-equipment) of rooms (separate parts) of the existing buildings and constructions which are not connected with change of the bearing and protecting (outside) designs, engineering systems and the equipment with the designer on compliance of developed earlier engineering design.

6. Signature date of the act is considered date of the commissioning of the facility accepted by the owner independently.

7. The act is the exclusive initial document in case of registration of property right for the constructed object.

8. The act with appendix of executive geodetic surveying of actual position of engineering networks and/or buildings (constructions) is subject to obligatory accounting in the local executive bodies performing functions in the field of architecture and town planning in information system of the state town-planning inventory.

Appendix 2

to the Order of the Minister of investments and development of the Republic of Kazakhstan of December 13, 2017 No. 867

form

The acceptance act of the constructed object in operation by the owner independently

__________________________________

"___" ____________ 20 __ years

(name of the settlement)

Owner of object ________________________________________________

________________________________________________________________________

________________________________________________________________________
           (surname, name, middle name (in case of its availability), the address of the place of residence)
        and the contractor (if the asset construction was performed by contract method)

________________________________________________________________________

________________________________________________________________________
    (the name of the organization, surname, name, middle name (in case of its availability), position
     person performing construction, the address, phone, license No., the date of receipt)

ESTABLISHED:

1. Construction object/reconstruction (re-planning, re-equipment)

rooms (separate parts) of the existing buildings

__________________________________________________________________________

__________________________________________________________________________,
                  (name of object, location or address)

___________________________________________________________________________

it was performed by the owner independently

___________________________________________________________________________,
                           (surname, name, middle name (in case of its availability))

and/or with the contract organization attracted with it

____________________________________________________________________,
 (the name of the organization, surname, name, middle name (in case of its availability), position of person).

2. Are executed:

________________________________________________________________________

________________________________________________________________________

________________________________________________________________________.
                                                     (work types)

3. The asset construction is made on the basis:

________________________________________________________________________

________________________________________________________________________.
            (the name of the body which passed the decision, No. and date of the decision)

4. Construction/reconstruction (re-planning, re-equipment) of rooms

(separate parts) the existing buildings it was performed according to the sketch (conceptual design) /

to the engineering design, разработанному____________________________________________

______________________________________________________________________________

______________________________________________________________________________,
          (the name of the organization, surname, name, middle name (in case of its availability),
        position of person who developed the sketch (conceptual design) / the engineering design)

The sketch (conceptual design) is approved

______________________________________________________________________________

______________________________________________________________________________
         (the name of the organization, the issued letter approval, No. and date).

5. Building and construction works is carried out in terms:

Beginning of works _________________________________________________
                                           (month and year)

completion of works ______________________________________________.
                                            (month and year)

6. The object accepted in operation has technical characteristics

according to the appendix _____ to this act.

7. Actions for ensuring explosion safety, fire safety,

to protection of the surrounding environment

________________________________________________________________________

________________________________________________________________________.
                                         (data on accomplishment)

8. Based on the confirmation of conformity completed by construction object/reconstruction (re-planning, re-equipment) of rooms (separate parts) of the existing buildings to the state (interstate) normative requirements, architectural planning task, the approved sketch (conceptual design) / to the engineering design the owner solved

ACCEPT in operation:

_____________________________________________________________________________

___________________________________________________________________________.
                                          (name of object)

9. Compliance of the constructed object to normative requirements,

to architectural and planning task, sketch (conceptual design) / to technical

I confirm to the project.

Owner объекта_________________________________________________

________________________________________________________________________
    (surname, name, middle name (in case of its availability), the address of the place of residence, the signature, date)

The contractor (if the asset construction was performed by contract method)

________________________________________________________________________,
         (the name of the organization, surname, name, middle name (in case of its availability),
                          position, signature, date, seal (in the presence)

The project organization (in case of reconstruction (re-planning,

re-equipments) building and constructions (separate parts, rooms), not

the bearing and protecting (outside) designs connected with change,

engineering systems and equipment)

________________________________________________________________________

________________________________________________________________________.
     (the name of the organization, surname, name, middle name (in case of its availability),
                              position, signature, date, seal)

10. Total cost of the asset construction accepted in operation

Warning!!!

This is not a full text of document! Document shown in Demo mode!

If you have active License, please Login, or get License for Full Access.

With Full access you can get: full text of document, original text of document in Russian, attachments (if exist) and see History and Statistics of your work.

Get License for Full Access Now

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SoyuzPravoInform LLC.