Document from CIS Legislation database © 2003-2018 SojuzPravoInform LLC

RESOLUTION OF THE CABINET OF MINISTERS OF UKRAINE

of March 28, 2018 No. 209

About approval of the Procedure for conclusion from operation of bulk distribution lines of oil, gas and products of their conversion

According to article 42 of the Law of Ukraine "About oil and gas" the Cabinet of Ministers of Ukraine decides:

1. Utverditporyadok of conclusion from operation of bulk distribution lines of oil, gas and products of their conversion which is applied.

Prime Minister of Ukraine
V. Groysman

Approved by the Resolution of the Cabinet of Ministers of Ukraine of March 28, 2018 , No. 209

Procedure for conclusion from operation of bulk distribution lines of oil, gas and products of their conversion

1. This Procedure determines the sequence of actions by conclusion from operation of bulk distribution lines of oil, gas and products of their conversion (their parts) which are state-owned property (further - the bulk distribution line), in case of inexpediency of their further operation, useful life, critical condition of objects, construction of bypass lines and so forth.

2. For the purpose of preparation of materials on conclusion from operation of the bulk distribution line which is considered on balance of the subject of managing of oil and gas complex (further - the subject of managing), according to the decision of the head of the subject of managing the working commission which part workers of the subject of managing are, and in case of need - representatives project and research establishments and other specialists is created.

3. For acceptance of the Ministry of Energy and Coal Mining of the decision on conclusion from operation of the bulk distribution line the subject of managing gives:

the petition for need of conclusion from operation of the bulk distribution line which is constituted in any form and is signed by the head of the subject of managing;

the feasibility statement on feasibility of conclusion from operation of the bulk distribution line with calculation of efficiency of such action and effects of possible influence on defense capability of the state;

the conclusion project, research establishment of oil and gas industry about impossibility/inexpediency of further operation of the bulk distribution line;

information on influence of conclusion from operation of the bulk distribution line to accomplishment of the obligations provided by the international loan agreements according to which the state guarantees, and documentary confirmation of lack of objections of creditors concerning approach of early repayment according to credit obligations of subjects of managing of the main pipeline transport according to which the state guarantees are provided are provided;

the statements (conclusions) about technical condition of the equipment of the bulk distribution line which are drawn up on each unit of equipment also shall contain information on their functional purpose, level physical and obsolescence, and also the sheet of defects;

acts of technical condition of objects of the bulk distribution line (the equipment, buildings and constructions, etc.) which shall contain data on their quantity, the conclusions about feasibility/inexpediency of their further operation;

the sheet about the objects of the bulk distribution line (the equipment, buildings and constructions, etc.) which are subject to conclusion from operation with indication of original and residual cost, quantity and cost of capital repairs;

the inventory report of the objects of the bulk distribution line which are subject to conclusion from operation;

the protocol on feasibility of conclusion from operation of the bulk distribution line constituted and signed by the working commission and approved by the head of the subject of managing;

the conclusion about the cost of the bulk distribution line which is subject to conclusion from operation and the valuation report of property;

the conclusion on environmental impact assessment;

the actions plan on social protection of the workers who are subject to reducing as a result of conclusion from operation of the bulk distribution line approved with the industry trade-union organization or primary trade-union organization of the subject of managing (in case of its availability) and territorial employment service;

the actions plan on conclusion from operation of the bulk distribution line with indication of the list of works and calculation of the costs necessary for providing conclusion from operation and storage of fixed assets, and also the offer on further use of such funds;

Full text available with active License only!

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 38000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.

Search engine created by SojuzPravoInform LLC. UI/UX design by Intelliants.